25 th Avenue Grade Separation December 13, 2017 Agenda I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25 th Ave Railroad Crossing


  1. 25 th Avenue Grade Separation December 13, 2017

  2. Agenda I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions 2

  3. Overview

  4. Project Location 4

  5. E. 25 th Ave Railroad Crossing • 92 Caltrain trains each weekday use this crossing, in addition to freight • Lack of grade separation increases delays along corridor 5

  6. Project Description

  7. Project Elements Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92  Concrete bridge 25 th & 28 th Ave  Steel bridge at 31 st Ave  Concrete retaining walls  MSE walls 7

  8. Elevated Track 8

  9. Grade Separation (25th Ave) 9

  10. East-West Connection (28th Ave) 10

  11. East-West Connection (31st Ave) Ramp Access to Ped Viaduct 11

  12. Relocated Hillsdale Station 12

  13. Station Improvements 13

  14. Station Improvements – Mosaic Wall Station Signage 14

  15. Station Improvements Stairway Entrance to Platform 15

  16. Station Improvements - Platform New Station Platform, Shelters, Lights 16

  17. Station Improvements - Furnishings 17

  18. New Hillsdale Station Access 18

  19. Project Funding, in Millions Measure A $74 City of San Mateo $84 State Section 190 State HSR Prop 1A $12 $10 19

  20. Project Benefits

  21. Project Benefits • Safe rail operations • Fewer system-wide delays • Improved traffic flow • Improved pedestrian and motorist safety • Facilitate Caltrain electrification which will reduce noise and vibration 21

  22. Project Construction

  23. Schedule: Overview Activity Date Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Oct 2017 – Dec 2018 Hillsdale Station Temp Parking (available for public use) Nov 2017 – Mar 2019 Bridges and MSE Walls Nov 2017 – Oct 2019 E. 25 th Ave. (lane closures) May 2018 – Oct 2019 Bridge at E. 25th Ave (14FT clearance) 23

  24. Schedule: Overview cont. Activity Date Dec 2018 – May 2019 Station Closed Road Completed – 28 th Ave May 2019 Oct 2019 – Dec 2019 E. 25 th Ave. Closure (full) Oct 2019 – 31 st Ave Roads Completed Dec 2019 – 25 th Ave Project Completed Jan 2020 24

  25. Schedule: Night Work Overview Activity Date Nov 2017 – Dec 2017 Temporary Sheet Pile Shoring Nov 2017 – Feb 2018 Cast-in-drilled-hole pile construction Feb 2018 – July 2018 MSE walls March 2018 – July 2018 Bridge Final Track Cutover Nov 2018 25

  26. Existing Hillsdale Station Temporary Parking Lot Temporary Parking Lots Construction Activities 26

  27. Hillsdale Station Closure • Enhanced train service provided at Belmont Station • Enhanced Samtrans bus and shuttle service provided between Hillsdale and Belmont Stations 27

  28. Hillsdale Station Closure • Passengers who drive, get dropped off or use transit  use Belmont Station • Passengers who walk to Hillsdale  take Samtrans bus (ECR Line) or shuttle to Belmont Station • Shuttle schedule will match enhanced train schedule • Shuttle pick-up location at east triangular lot 28

  29. Example Lane Closure: 25th Ave 29

  30. Work Hours • Majority of construction activities will take place Mon-Fri during the day • Certain construction activities require work to be completed at night or on weekends when there is reduced or no revenue train service • JPB will notify community in advance of nighttime and weekend work

  31. Potential Impacts during Construction Noise and Vibration Impacts: • Temporary: Only during construction • Construction equipment and (Not to Scale) procedures selected to monitor noise and vibration impacts • Noise monitoring station at Peninsula Station (2901 ECR)

  32. Construction Impacts / Mitigation • Single tracking trains • Shoring Work o Pre-drilling (will also occur during day) o Different equipment obtained • Pile Work: Additional crew/equipment

  33. Next Steps

  34. Construction Notices Example of mailed notice 34

  35. Public Outreach & Community Engagement • Project website: www.caltrain.com/25thGS • Construction Outreach Hotline: 650.508.7726 • Email: SMGradeSep@Caltrain.com • Regular Updates and Public Meetings  Prior to Station Closure  Prior to Street Closure