25 th avenue grade separation
play

25 th Avenue Grade Separation JPB Board April 4, 2019 Agenda - PowerPoint PPT Presentation

25 th Avenue Grade Separation JPB Board April 4, 2019 Agenda Item#10 Agenda I. Project Need, Benefits & Description II. Construction Construction Status Construction Challenges III. Contract and Budget 2 Project Need,


  1. 25 th Avenue Grade Separation JPB Board April 4, 2019 – Agenda Item#10

  2. Agenda I. Project Need, Benefits & Description II. Construction – Construction Status – Construction Challenges III. Contract and Budget 2

  3. Project Need, Benefits and Description

  4. Project Location 4

  5. E. 25 th Ave Railroad Crossing • 92 Caltrain trains each weekday use this crossing, in addition to freight • No. 8 on California Public Utilities Commission (CPUC) priority list for railroad crossing safety. 5

  6. Project Benefits • Enhanced East-West connectivity • Improved pedestrian and motorist safety • Improved traffic flow • Fewer system-wide delays • Support Caltrain electrification • Improve Customer experience with new Station • Enable future California High Speed Rail (CAHSR) • Safe rail operations 6

  7. Factors Driving Award Date • Coordination with Peninsula Corridor Electrification Project (PCEP) required expedited Contract award: – Foundations Constructed as part of 25 th Grade Separation (GS). – Poles and wires installed by PCEP 7

  8. Risk Factors at Award • Fiber Optic relocation was pending resolution of negotiations with Union Pacific Railroad (UPRR) • Funding from CAHSR was pending 8

  9. Contract Award • Contract Awarded to Shimmick Disney JV July 2017 for $ 82,890,000 • Original Completion Date Jan. 2020. 9

  10. Project Funding, in Millions $ 180 Project Measure A $74 City of San Mateo $84 State Section 190 State HSR Prop 1A $12 $10 10

  11. Project Elements Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92  Five bridges  Approx. 1 mile of Mechanically Stabilized Earth (MSE) Wall  New elevated station at Hillsdale 11

  12. Elevated Track 12

  13. East-West Connection (28th Ave) 13

  14. Relocated Hillsdale Station 14

  15. Construction - Status

  16. Progress • Bridges – Beresford Creek Bridge Complete – Four (4) remaining Bridges substructure complete; superstructure ongoing. • Wall Construction – North of 25 th Complete this month – Betwn 25 th and 28 th Ongoing 16

  17. Bridges 17

  18. MSE Wall 18

  19. Construction - Challenges

  20. Project Impacts Utility Relocation – Major Utility relocations by Utility Companies, including:  Fiber Optic Duct Bank  PGE Gas Line  ATT Communication Duct Bank Station – Relocation and opening delayed by 10 months, with an anticipated opening of June 2020 20

  21. Impacts Due To Fiber Optic 21

  22. Working Around Live Fiber 22

  23. PG&E Gas Line Relocation 23

  24. AT&T 24

  25. Weather Impacts 2018-2019 “Atmospheric Rivers”  Caused Project Delays due to excess rain days  Created significant stormwater flows requiring substantial dewatering 25

  26. Weather Impacts 26

  27. Contract and Budget

  28. Contract and Budget • All impacts from the Fiber Optic delay in 2018 have been addressed and the project schedule has been re-baselined. • Fiber Optic delays continued through March 2019. Total Project Delayed up to 12 months. Current Anticipated Completion Date of January 2021. • Return to this board with a recommendation to: increase Contract Authority; No additional budget needed • No current impact to PCEP 28

  29. Questions

  30. Grade Separation (25th Ave) 30

  31. East-West Connection (31st Ave) 31