xcel energy
play

Xcel Energy Generator Interconnection SPS Sub-Regional Planning - PowerPoint PPT Presentation

Xcel Energy Generator Interconnection SPS Sub-Regional Planning Meeting May 9, 2019 Kevin Pera, P.E. Transmission Access 2 Generator Introspection: Why should I care? Utility Roles Developer Generator Owner Transmission Owner


  1. Xcel Energy Generator Interconnection SPS Sub-Regional Planning Meeting May 9, 2019 Kevin Pera, P.E. Transmission Access

  2. 2

  3. Generator Introspection: Why should I care? Utility Roles • Developer • Generator Owner • Transmission Owner • Load Serving Entity • Resource Planner New Generators Affect Grid Operation: • Transmission Loading • Losses • Voltage Stability • Power Responsiveness • Cost of Energy

  4. FERC Orders FERC Order 2003 & 2006 FERC Order 845, 845-A • Ten reforms, three categories Established Standard Generator Interconnection Procedures (GIP) – Improve certainty • Pro Forma Tariff – Promote more informed interconnection decisions • Large/Small Generator – Enhance interconnection process Interconnection Agreements (LGIA and SGIA) • All reforms either – require the Transmission Provider to do something or – allow the Interconnection Customer to do something.

  5. SPP Queue Reform Efforts 2019 Completely refreshes GIP 2009 • Three-stage process Clearing the serial queue • Increased deposits to match • Clustering assigned upgrade costs at each • Established three queues stage in the study process • Shortened suspension times 2014 Other GIP Faster to commercial Improvements • Increased deposits Faster to commercial • 11 months to generator construction • Interim GIA • Shortened suspension times • SGIP consolidation

Recommend


More recommend