Welcome! January 29, 2016 Quarterly Meeting Jacquie Vargas Building Coordinator Program Director, Communications Manager Facilities Services E-mail: jmvarga5@Central.UH.EDU
INTRODUCTION AVP / AVC F ACILITIE S Jacquie Vargas Communications Manager Facilities Services E-mail: jmvarga5@Central.UH.EDU
AVP / AVC F ACILITIE S David Oliver Associate Vice Chancellor/Associate Vice President Facilities/Construction Management E-mail: jdoliver@uh.edu
F ACILITIE S/ CONSTRUCTION MANAGE ME NT
OUTAGE S UPDATE Mike Wheeler Karl Keilbach Sr. Project Manager, FMP, Supvr, Electrical LEED A.P. Facilities Operation and Maintenance Facilities Services Facilities Services Email: mdwheel2@Central.UH.EDU Email: kkeilbac@Central.UH.EDU
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D. • The four remaining item on the Hartford Steam Boiler (HSB) dated July 14, 2014, were corrected. Repair several overhead conductors and grounding cables Replace three (3) transformers in Engineer 1 • Cougar Sub station. Preventative Maintenance (PM) and tested all yard equipment Demo & remove lighting in Sub station yard. • Support for FP&C Projects. STL & Fleming 15KV ATS replacement MREB electrical utilizes tie in for electrical service to building Kenmore Electric demo abandon sub feeder 4 in tunnel
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D. • Multiple buildings PM transformer vault and 480 switchgear • Investigation the cause of the sub feeder 1 failure Cause was found and corrective actions are being planned • Work was completed, campus power was restored as scheduled
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D. • Moving forward Items were discovered during outage that will require additional work • We will need to prepare a scope of work and schedule the repairs Some generators did not perform well • We will need to prepare a scope of work and schedule the repairs Facilities Services will be reaching out to the affected building once scope of work is finalized to schedule corrections.
2016 WINTE R OUTAGE The program continues • The Preventive Maintenance (PM) program has proven to be a success and it is planned to continue. Communication with campus, through Building Coordinators program to get the word out in advance As we make improvements to electrical system on campus we plan to be able to isolate the outages, if possible, to minimize service interruptions during PM’s
KE Y ACCE SS/ SE CURITY Malcom Davis Ron Harris Asst VC/VP, Public Safety Security Mgr., Electronic Access Control DPS Administration Department Public Safety E-mail: mdavis@uh.edu E-mail: rwharris@uh.edu
DOOR PRIZE ! And the winner is…
Thank you for coming.