Webinar 30 April 2015 1
Kevin Hoban Smart Street Project Manager 2
Agenda Introduction and overview Technical update Trial design Questions & answers 3
Webinar format 10 minutes 30 minutes presentation questions & answers Submit written questions online during the webinar or Press 01 on your telephone key pad to take part in the live Q&A at the end of the presentation 4
Our innovation strategy Offer new services and Maximise choice for the use of existing future assets Delivering Generate value to value for Innovative customers customers solutions ‘Fit and forget’ now to real problems Proven technology deployable today 5
Our smart grid development Leading work on developing smart solutions Deliver value from existing Customer choice assets Four flagship products (second tier) £36 million Capacity to Customers 6
Smart Street overview New controllable switching devices stabilise voltage Allows us to lower voltage levels Enables networks and appliances to work in harmony C L W W Low cost Quick fit Minimal disruption Low carbon Low loss Invisible to customers Faster connection of low carbon technologies 7
Key activities to date Jan 2014 April 2015 Site Customer Circuit Customer Technology Project selection design engagement mailings installation mobilisation complete Project Trial circuits Design Customer Engaged Technology team identified methodology engagement with installation appointed developed plan customers and On site then applied on trial commission Contracts surveys Project to trial circuits -ing signed with completed website live circuits ongoing project partners Circuit designs finalised Knowledge sharing and dissemination 8
Customer impact and objectives Pre-trial During/post-trial ! Customers have Occasional Reduction in Possible change seen increased planned supply fault duration in voltage activity while interruptions due during trial equipment is to equipment period installed installation Objective: To engage with Objective: To prove that customers customers and explain impact of will not perceive a change to their Smart Street trial electricity supply 9
Progress and next steps Go live of the Customers Technology Customer Engaged Customer Smart Street affected by installation engagement customer leaflet website and new street enquiries / plan submitted panels held designed and social media furniture complaints to Ofgem and and lessons distributed to forums installations resolved approved learned customers on notified published trial circuits Successful technical installation as a result of well planned strategy and customer engagement activities Further ECPs to Ongoing Next Brief ENW contact Produce report of gauge customer engagement with centre before trial customer steps perception & customers during go live research findings acceptability of trials trial 10
Damien Coyle Smart Street Technology Engineer 11
Technology – Spectrum Measures, optimises and responds CVR and losses benefits unlocked Spectrum Oversees network and customer needs Builds on CLASS smart voltage control 12
WEEZAP World leading LV vacuum circuit breaker Advanced measurement and protection capability Safe LV interconnection, live monitoring and control Improves supply reliability and restoration through fault management and detection 13
LYNX LV switch Allows active network meshing and un-meshing Advanced monitoring capabilities Ability to control the circuit locally or remotely 14
What customers will see – LV capacitors in street furniture 84 LV capacitors One on each closed ring Tried and tested 15
What customers will see - HV capacitors 3 ground mounted 4 pole mounted HV capacitors HV capacitors Located in urban areas Installed similar to pole in GRP housings mounted transformers 16
Technology overview 84 LV capacitors 40 link boxes installed installed Spectrum 5 installed 50 end-point on network controllers installed 5 OLTC IT integration Next 7 HV capacitors transformers to and to be installed steps be installed commissioning 17
Technology lessons learnt Equipment IT HV GM capacitors LV capacitors Development on A number of units had interoperability Footprint larger than to be reduced in size between control anticipated. to ensure footpath systems and various Required significant access was not new field devices, work with land owners restricted required engagement and local authorities to with all technical agree wayleaves and partners and planning permission manufacturers to identify possible issues early 18
Dan Harber Trials & Research Engineer 19
Agenda Trial network overview Test regimes Proposed test schedule Research overview 20
Smart Street trial overview 6 primary substations 67,500 customers Wigton & Egremont 11 HV circuits – 5 closable HV rings 4 pole mounted HV capacitors 3 ground mounted HV capacitors 38 distribution substations 5 OLTC transformers Wigan & Leigh Manchester 5 substation capacitors 79 LV circuit capacitors 21
Smart Street trial design Two years Five trial techniques One week on LV voltage control One week off LV network management One year’s worth of and interconnection Smart Street data HV voltage control To be designed to HV network management avoid placebo affect and interconnection Five trial regimes to Network configuration test full effects and voltage optimisation 22
Smart Street test regimes Smart Street trial Test regime 1. On-load tap changing distribution transformer only 2. On-load tap changing distribution transformer and capacitor(s) on LV circuits LV voltage control 3. Capacitors at distribution substation only 4. Capacitors at distribution substation and on LV circuits 5. Capacitor(s) on LV circuits only 1. LV radial circuits LV network management & interconnection 2. LV interconnected circuits 1. Voltage controllers at primary substation only HV voltage control 2. Voltage controllers at primary substation and capacitor(s) on HV circuits 1. HV radial circuits HV network management & interconnection 2. HV interconnected circuits 1. Losses reduction Network configuration & voltage optimisation 2. Energy consumption reduction 23
Proposed test schedule TRIAL 1 - LV TRIAL 2 – LV TRIAL 3 - HV TRIAL 4 - HV VOLTAGE CONTROL INTERCONNECTION VOLTAGE CONTROL INTERCONNECTION WEEK 1 OFF OFF OFF OFF WEEK 2 OFF OFF OFF OFF EQUIPMENT TESTED EQUIPMENT TESTED WEEK 3 ON ON IN ISOLATION IN ISOLATION WEEK 4 COMBINED TESTING ON COMBINED TESTING ON WEEK 5 OFF OFF OFF OFF WEEK 6 OFF OFF OFF OFF EQUIPMENT TESTED WEEK 7 ON COMBINED TESTING ON IN ISOLATION EQUIPMENT TESTED WEEK 8 COMBINED TESTING ON ON IN ISOLATION Trial 5: The optimisation will be applied during the trial on periods where week 4 allows for full optimisation 24
Overview of research workstream WP1 will look to •WP2 will look to WP3 will research •TNEI will provide quantify the produce the the cost benefits research support voltage design and and carbon and consultation optimisation and operation policies impact related to for the duration of loss reduction required to the Smart Street the trials techniques used convert UK solution in Smart Street networks into optimal meshed configurations 25
Next steps April 2015 Sep 2015 Sep 2017 Dec 2017 ECP and Technology Start of Project customer installation trials closedown research Project Continue with Trials will run findings and Qualitative installation of for 2 years in final research with transformers conjunction dissemination customers on and with research event for all trial circuits capacitors deliverables stakeholders Knowledge sharing and dissemination 26
& QUESTIONS ANSWERS 27
Webinar Please complete our online poll 28
Recommend
More recommend