CITY OF LITTLE ROCK Public Works Department Ward 2 2016 to 2018 Street and Drainage Program Meeting April 6, 2015 CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT Ward 2 Sales Tax/Bond Projected Allocation 2013-2015 2016-2018 2019-2021 Sales


  1. CITY OF LITTLE ROCK Public Works Department Ward 2 2016 to 2018 Street and Drainage Program Meeting April 6, 2015

  2. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT Ward 2 Sales Tax/Bond Projected Allocation 2013-2015 2016-2018 2019-2021 Sales Tax $ 2,600,000 $ 2,600,000 * $ 2,600,000 * Bond $ 8,800,000 $ 5,750,000 * Total $ 11,400,000 $ 2,600,000 * $ 8,350,000 * * Projected Funding 2 April 6, 2015

  3. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT Ward 2 - 2013 to 2015 Bond/Sales Tax Summary • A total of $2,600,000 in Sales Tax funding was allocated. • A total of $8,800,000 in Bond Issue funds was allocated. • In the 2013 to 2015 project request list, there were 61 jobs requested. • A total of 6 Bond Program jobs and 8 Sales Tax Program jobs were selected and are in the process of design, bidding, and construction. • Currently 3 jobs (21%) are in design, 7 jobs (50%) are currently in construction, and 4 jobs (29%) are totally complete. 3 April 6, 2015

  4. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT 4 April 6, 2015

  5. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT • Ward 2 Sales Tax Project Status Anticipated Request # Location Description Status Bid Quarter Westminister Dr Replace curb and gutter and install underground drainage system at #45 2-5b Project Complete Westminister Dr. Additional/continuation of drainage improvements from Windamere Dr. to 2-6a Windamere In Construction Carlyle Dr. Replace curb and gutter and install underground drainage system on Butler 2-9b Butler Rd Project Complete Rd at Allyson Circle. Install additional curb inlets along Tamela Dr Between Valley and Ramona 2-18a Tamela Dr Project Complete Dr. 5919 Lancaster Improve drainage ditch along rear property lines for houses fronting 2-20 In Construction Lancaster Rd and Lyndell Dr. Street reconstruction including curb, gutter, underground drainage system 2-28 Woodson Rd In Construction from Young Rd to Halifax Dr. (1270 lf) Replace curb and gutter, install underground drainage system from 8th to 2-32a Abigail St In Construction 10th Install curb, gutter and underground drainage from W 12th St north to I- In Design – 98% 2-32d Adams St 1 st - 2015 630. complete 5 April 6, 2015

  6. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT • Ward 2 Bond Project Status Anticipated Request # Location Description Status Bid Quarter Geyer Springs In Design - 1% B-2a Grant match for new overpass. AHTD Controlled Railroad Overpass complete B-2b Scott Hamilton Widen and improve roadway including sidewalks. In Construction B-2c Dailey Drive Sidewalk Install sidewalk From Baseline Rd South to Pulaski County SW Health Unit (575'). Project Complete Improve roadway section including sidewalk, curb, gutter, and underground B-2d West 10th St In Construction storm drainage. In Design - 60% B-2e Traffic Calming Install traffic calming measures along Fair Park Blvd 3 rd - 2015 complete Elm St and Maryland B-2f Elm St from 8th to Maryland, Maryland St west to Lewis In Construction St In Construction – 44% Overlay Program complete 6 April 6, 2015

  7. CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT Ward 2 - 2016 to 2018 Project Request Summary • Anticipated total of $2,600,000 in Sales Tax funding will be allocated. • Currently there are 7 new requests. • Deadline for Submission is May 1, 2015. • For access to the Project Infrastructure Request form, citizens may: 1. Pick up a copy here 2. Go to website at http://www.littlerock.org/citydepartments/publicworks.aspx Halfway down the page under “Civil Engineering”, click on “Infrastructure Request Form (Fillable)” link. 3. Send form to: City of Little Rock - Department of Public Works Infrastructure Project Requests 701 West Markham Little Rock, AR 72201 Email: PublicWorks@littlerock.org 7 April 6, 2015