Los Alamos County Walkup Aquatic Center - Kiddie Pool Addition Schematic Design Presentation AUGUST 28, 2019
Schedule Kiddie Pool Addition WORKPLAN & COMMUNICATION PROCESS Los Alamos County Walkup Aquatic Center 2019 2020 2021 June 10 May 4 June 4 2019 August 20 2019 2019 SCHEMATIC DESIGN August 20 October 29 2019 DESIGN DEVELOPMENT 2020 PROGRESS PROGRESS October 29 February 4 PROJECT KICK-OFF 100% SD 50% SD 75% SD 2020 CONSTRUCTION DOCS/SPECS FINAL 2 3 4 1 April 2 PROGRESS PROGRESS DD START BIDDING/ 100% DD 60% DD 90% DD CONST. PERMIT FINAL PROGRESS PROGRESS 7 8 9 10 CD START 100% CD 60% CD 90% CD • Review Program & • 75% SD Progress • 100% Schematic • Preliminary Designs FINAL Building Areas Design Review 12 13 14 15 • Schematic Design • SD cost estimates • Budget/ Schedule • Begin Peer Review Progress: PERIODIC • Code analysis • DD Progress • 60% DD Progress • 90% DD Progress • 100% DD Site Plan, Floor • Discuss Overall • Geotech Progress Document PROJECT Plan, Elevations PROGRESS Milestones • Survey Update • Public Information • Los Alamos County • Discuss Comments Submission CLOSEOUT MEETINGS • Survey Update Meeting AHJ From FM + AHJ • Survey • CD Begin • 60% CD Progress • 90% CD Progress • CD Final • Site Walk-Through • Geotech Progress • Peer/ Owner Review • Estimate of Probable • Review With Owner • Los Alamos County • Building Envelope • Finalize Finishes • Fire Marshal • Public Information • Submit Plans/ Specs • Parking Variance Construction Cost Fire Marshal Meeting • Estimate of Meeting Meeting to County • Punch List (P&Z update) • HVAC Options Probable Cost • Finalize HVAC • Schedule IDRC, P&Z, • Meet With County • Review Layout Systems • County Utility • Finalize Building • Public Information • Review of ACAS submittal • Pool Consultant • Budget/ Schedule O+M Staff • Present to Aquatics Meeting Systems Meeting Operations • Pool Consultant Center Advisory • Pool Consultant • Schedule site plan • Pool Consultant • Pool Consultant Committee (ACAS) • MEP Review • Finalize Building • Page Turning Session • Final amendment, parking • MEP • Site Envelope With Owner Documentation waiver, plat approval • Utilities • Present to Parks + • Building Envelope (release of liens) Recreation Board • Building Envelope • Estimate Update • Estimate • HVAC life cycle costs • Building Envelope (PRB) • Estimate Update • Confirm Classroom • Present to Aquatics Layouts & PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: • Building Envelope Center Advisory Furnishings • OWNER • OWNER • OWNER • OWNER Committee (ACAS) • FBT • FBT • FBT • FBT PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: • 12 Month Warranty • CHH2O • Present to Parks + Walk • OWNER • OWNER • OWNER • OWNER Recreation Board • FBT • FBT • FBT • FBT (PRB) • B+P • LAC FM • AGI • ACAS June 10 July 15 August 5 June 24 PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: PARTICIPANTS: • CHH2O • AGI • PRB • OWNER • OWNER • OWNER • OWNER • FBT • FBT • FBT • FBT PARTICIPANTS: TBD TBD TBD TBD • LAC FM • ACAS • OWNER • PRB • FBT • General Contractor TBD TBD TBD TBD TBD Program Verification Budget Schedule Schematic Design Budget Utilities Systems Materials Budget Systems Utilities Fire Marshal Bidding Construction Warranty
POOL ADDITION PROGRAM ELEMENTS - 2,000 SF zero-entry pool, with spray features, lazy river, and an area for swim lessons. - Water slide with run-out area separate from main pool. - (3) family changing rooms - Pool support spaces, including mechanical, chemical storage, and electrical rooms. - Total project budget: $6.5 million - Construction is slated to begin in May 2020 and last for a year. Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project Site Plan & Program - August 28, 2019
EXISTING SEWER LINE EXISTING MANHOLE NEW SEWER LINE
EXISTING SEWER LINE EXISTING MANHOLE NEW SEWER LINE
Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project Aquatic Features - August 28, 2019
29'-0 5 " 16 STAIR START BELOW 8" A 8'-103 WALL BLOCKOUTS, CLOSURE PANELS, AND SEALING AROUND THE SLIDE AT WALL PENETRATIONS IS BY OTHERS (TYP) START DECK EL. 119.25' POOL DECK EL. 100.00' RUNOUT DECK EL. 100.00' 19'-3" Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project Aquatic Features - August 28, 2019
LOBBY NEW FINISH EXISTING FINISH 373 SF LOBBY VESTIBULE 118 SF VESTIBULE NEW ENTRANCE DESIGN VESTIBULE 190 SF LOBBY 415 SF Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project EXISTING ENTRANCE Entrance Design - August 28, 2019
Your Input is Important! Please drop comment cards in the box or hand to staff. Comments can also be sent to lacpw@lacnm.us Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project Comment Cards - August 28, 2019
Questions / Comments? Los Alamos County - Larry Walkup Aquatic Center Pool Addition Project Questions / Comments - August 28, 2019