www. velpaprojects .com
Finishing your property the VELPA way
Time plan Week 1 - 4 Week 5 - 8 Week 9 - 12 Week 13 - 17 Week 18 - 22 Week 23 - 27 Site Preparation Construction and alterations Electrical Plumbing Floor Screeding Plastering Soffits Tiling Decoration Aperatures Cleaning
Work Rates EXAMPLE According to our site visit, we budget a total of €71,600 for the completion of your project WORK RATES All works will be measured by a quantity surveyor and billed accordingly Description Unit Euro Site Preparation & Structure Alterations 1.5 €7,000 Electrical Sq.m €15,000 Plumbing Sq.m €9,000 Floor Screeding Sq.m €7,500 Plastering Sq.m €8,700 Soffits Sq.m €10,500 Tiling & Material Sq.m €7,500 Decoration Sq.m €3,000 Contingency 5% Sq.m €3,400 €71,600
WHEN DO WE START? Velpa Projects Ltd, 13, Triq l-Uqija, Ibragg, SWQ 2337, Malta T. +356 21 384 020 M. +356 79 440 408 E. info@velpaprojects.com