Transmission Charging Methodologies Forum & CUSC Issues Steering Group 08 August 2018 1
Welcome Rachel Tullis, National Grid ESO 2
Housekeeping Fire alarms Facilities Red Lanyards 3
Actions TCMF Month Requestor Agenda Item Action Owner Notes Target Date Status We are planning to get get all archived modifications available on the website, however this will take some time due to the volume of material. Proposal forms, Oct-18 Make enquiries re missing website content Workgroup reports, FMRs and decision specifically in relation to previous mods (TCMF letters will be uploaded. In the meantime members asked to advise when they come across any specific requests can be sent to the Dec-17 PB AOB any additional missing content) RT cusc.team@nationalgrid.com. On-going CUSC It was requested by an attendee that a very brief Aug-18 Modification decription of each modification is added to the Abbreviations of code modifications will be Jul-18 - Update slide showing upcoming modifications to authority JH used on slides. Complete Ofgem has advised this will be towards the Charging Futures An attendee asked when the TCR consultation will end of the year. No exact date has been Aug-18 Jul-18 - update come out. BV given. Complete GG asked whether a transcript could be made available for the podcast series which is being There will not be a transcript but the Aug-18 Charging Futures hosted by NG about key themes on Ofgem's A&FLC podcasts will be available from the Charging Jul-18 GG update consultation BV Futures website and apple podcasts. Complete 4
Today’s TCMF CUSC Modifications Update Loss of Mains Protection Update Responses to Open Letter on the Five-Year View of TNUoS Compliance with 838/2010 Ofgem Updates Ofgem’s Access and Forward Looking Charges Consultation AOB
TCMF CUSC Modifications Update Joseph Henry, Code Admin
New Modifications • CMP303 - Improving local circuit charge cost-reflectivity (EDF Energy) • CMP303 looks to make part of the TNUoS charge more cost- reflective through removal of additional costs from local circuit expansion factors that are incurred beyond the connected, or to-be- connected, generation developers’ needs • Panel decided Modification would go to a workgroup • Code Administrator will source members 8
Upcoming Working Groups • CMP280/281 – w/c 27 August 2018 Removal of Demand Residual TNUoS and BSUoS on Imports for Generators • CMP286/287 – 17 August 2018 Improving TNUoS Predictability • CMP288/289 – 6 August 2018 Delays and Backfeeds 9
Upcoming Modifications to Authority • CMP301 – w/c 6 August 2018 HVDC Subsea Circuits 10
Workgroup Developments • CMP280/281 – Workgroup held 26 July 2018. Progress made against original proposal and potential alternative. Next workgroup planned. • CMP286/287 – Workgroup held 31 July 2018, where RFI responses discussed. Further analysis ongoing. Next workgroup 17 August 2018. • CMP288/289 – Two workgroups held since last TCMF. Good progress made, with next due to be scheduled for September. • CMP291/295 – First workgroup to be held 12 July 2018. CUSC Panel agreed for modifications to be progressed with GC0117. Sourcing dates for next. 11
Dashboard - CUSC New In-flight Modifications Modifications on Modifications Modifications put out for hold consultation 1 19 2 3 Workgroups Authority Workgroups Held (July) Decisions Scheduled August 6 0 3-5 12
Loss of Mains Protection Update Graham Stein, National Grid
Loss of Mains Protection
Loss of Mains Protection
Why It is an Issue Frequency Automatic frequency response ramps up over ~1 to 10 seconds 50Hz RoCoF based protection operates If the rate of change is <~500ms high enough, distributed generators shut down causing a If the volume of further fall in distributed generation frequency at risk is high enough, there is a risk that LFDD occurs Containment limit (49.2Hz) Low Frequency Demand Disconnection Stage 1 (48.8Hz) Instantaneous Infeed Loss Automatic Frequency Response Time 16 fully delivered
System Inertia Trend
Historic RoCoF Constraint Costs Steadily RoCoF constraint costs (£M) 70 increasing trend 59.2 60 2018/19 year to 50 date 40 expenditure 30.7 30.2 30 £38m 20 10 0 2015/16 2016/2017 2017/2018 18
Vector Shift Events Tx Demand National Solar Date/ Time Fault Increase Output Grain Bus Coupler 4 469MW 61% 17/03/2016 12:27 Grain- Kingsnorth 400kV circuit 200MW 17% 20/03/2016 16:13 Langage – Landulph 400kV circuit 22/05/2016 11:15 380 MW 52% Cowley-Leighton Buzzard-Sundon 07/06/2016 17:04 145MW 28% 400kV circuit 21/05/2017 18:20 Littlebrook 400kV Reserve Bar 200 MW 39% COTT – EASO – RYHA CCT 241MW 22% 08/06/2017 16:47 energised from EASO4 only Bramford – Sizewell 4 400kV circuit 10/07/2017 14:19 300 MW 37% 580MW DG Loss 17/07/2017 15:26 Kensal Green Reserve Bar less 160MW 50% demand loss 19
Distribution Code Changes GC0035 DC0079 (1) Applies at stations >5MW from August 2016 DC0079 (2) Applies to generation RoCoF to be set at 1.0Hzs -1 , connected under G59 from 0.5s definite time February 2018 Applies to both G59 and G83 Vector Shift unchanged generation connecting from RoCoF to be set at 1.0Hzs -1 , 0.5Hzs -1 , 0.5s allowed for July 2018 0.5s definite time for new synchronous commissioned non-type-tested generation at RoCoF to be set at 1.0Hzs -1 , prior to the change stations <5MW 0.5s definite time for new type-tested generation at Vector Shift banned for all stations <5MW new non-type-tested generation Vector Shift banned for all new type-tested generation For details of the previous DC0079 modification see: 20 http://www.dcode.org.uk/current-areas-of-work/dc-0079.html
Proposed Distribution Code Change Final DC0079 consultation published on 13 July 2018 Responses requested by 17 August 2018 Available at http://www.dcode.org.uk/consultations/open-consultations What’s in the consultation Proposals to apply retrospectively to all non-type-tested G59 generation 1.0 Hzs -1 , 0.5s definite time for RoCoF to remove Vector Shift Safety Risk Assessment Cost Benefit Analysis Outline Implementation Proposal 21
RoCoF cost forecast 22
Implementation Cost Low Estimate WG Estimate High Estimate Nature Of Work Number of Number of Number of Cost (£) Cost( £) Cost( £) Sites Sites Sites 1 Synch - reset RoCoF 355 71,074 477 95,379 260 52,070 2 Synch replace RoCoF 19 144,019 477 3,672,080 2,343 18,042,324 3 Synch reset VS to RoCoF 1,049 209,849 977 195,469 878 175,564 4 Synch replace VS with RoCoF 117 897,685 977 7,525,549 7,900 60,832,857 5 Asynch reset RoCoF 2,585 516,930 2,927 585,401 559 111,730 6 Asynch remove RoCoF 136 27,207 2,927 585,401 5,028 1,005,568 7 Asynch reset VS to RoCoF 41,176 8,235,255 20,625 4,124,951 3,304 660,876 8 Asynch remove VS 4,575 915,028 20,625 4,124,951 29,739 5,947,886 Expected Cost Low estimate High estimate Plant Category No of Sites £m £m £m P g >5MW 677 2.2 0.5 4.2 1MW< P g < 5MW 1445 4.6 1 8.9 P g <1MW 47890 24.1 19.5 83.8 23 Total 50012 30.9 21 96.9
Accelerated Vector Shift Change National Grid in collaboration with three DNOs initiated an accelerated VS change programme to mitigate the risk for summer 2018 Programme implemented under Balancing Service framework VS change 2018 DC0079 Duration Within a month before June Multi-year Target EG 800MW, 72 sites in specific More than 15GW and area 50,000 sites nationally Total cost £350k £31M Benefit Realised within year Realised once the whole programme complete Governance Tactical exercise between Steering committee with licensees stakeholder input 24
Next Steps There’s an opportunity to express views in response to DC0079 at http://www.dcode.org.uk/consultations/open-consultations Further work will be required to define how the DC0079 proposals will be implemented Conclusion and relevant developments will be brought back to TCMF in the Autumn 25
Five Year View of TNUoS Tariffs Update on our open letter Paul Wakeley, Revenue Manager
National Grid Revenue Team Paul Wakeley Forecasting, setting and billing TNUoS and Connection Charges to recover £3bn of TO Revenue per year from generators, demand, DNOs and suppliers Gillian Anthony Tom Selby Alice Grayson Andrew Havvas Paul Hitchcock O’Sullivan Tichivangana Jessica Jo Zhou Jennie Groome Liz Statham Luke Craddock Rivalland TNUoS Tariff forecasting and TNUoS Billing Connection Charging setting 27
Context Annual Obligation for NGESO to produce a paper Five Year View TCMF June 2018 of TNUoS scheduled for 2019/20 to 2023/24 Open Letter June/July 2018 28
Five Year View of TNUoS Tariffs We provided an updated to TCMF in June We published an open letter on 19 June seeking feedback on our proposed approach to sensitives in the five year forecast We received 9 responses from a cross section of the industry Thank you for taking the time to shape our report 29
Recommend
More recommend