The The Moor oors at at Arne Arne Pr Project Stakeholder Liaison Group Meeting From a photo: Graham 12 September 2018 Hatherley 1 Introductions 10 mins St Stak akeholder eholder 2 The Moors at Arne Project Brief introduction to the 15 mins


  1. The The Moor oors at at Arne Arne Pr Project Stakeholder Liaison Group Meeting From a photo: Graham 12 September 2018 Hatherley

  2. 1 Introductions 10 mins St Stak akeholder eholder 2 The Moors at Arne Project Brief introduction to the 15 mins project Liaison Liaison 2 Terms of Reference 10 mins 3 Contracting Clarify role of the Group 10 mins Group Gr oup etc 4 Update on the Project and 1) Flooding 40 mins Feedback / discussion 2) Public Access 3) Construction traffic Agenda Agenda 4) Location of main embankment 5) Siltation 6 Future topics for discussion Group and project team to 10 mins suggest topics 7 Next steps in the Project 10 mins 8 Date of next meeting 9 Close

  3. Project Team: Environment Agency Helen Morgan, In Intr troductio tions Neil Watson, Catherine Farrugia, Kevin House, Vanessa Dare RSPB Dante Munns Natural England Ian Alexander

  4. In Intr troductio tion to to the the Pr Project Neil Watson

  5. SM SMP & Str Strategy gy • Shoreline Management Plan (Policy 2012) • Poole & Wareham Strategy (2015) • Poole Harbour Habitat Creation Review

  6. SM SMP & Str Strategy gy • Shoreline Management Plan (Policy) • Poole & Wareham Strategy (Detail) • Poole Harbour Projects

  7. SM SMP & Str Strategy gy • Shoreline Management Plan (Policy) • Poole & Wareham Strategy (Detail) • Poole Harbour Projects The Strategy approach is Managed Realignment / Minimum Maintenance

  8. Habitat Creation Requirements

  9. Habitat Creation Requirements

  10. Habitat Creation Requirements

  11. Habi Habitat Cr Crea eation tion Obj Objectiv ctives es • Working with Natural Processes • Developing a mosaic of Intertidal habitats across the site including: Saltmash Mudflat Saline Lagoons Protecting rare and irreplaceable habitats in situ – Cladium Fen •

  12. The The Moor oors at at Arne Arne Pr Project

  13. The The Moor oors at at Arne Arne Pr Project Site Area: Red = RSPB Blue = Natural England Yellow = Arne Road

  14. The The Moor oors at at Arne Arne Pr Project

  15. The Moors at Arne V i e w

  16. Short Short Lis Listed ed Opti Options ons (1a) (1a) – L – Lagoons in in the the We West

  17. Short Short Lis Listed ed Opti Options ons (1b) (1b) – L – Lagoons in in the the Ea East

  18. Short Short Lis List Opti Options ons (1c) (1c) – E – Eastern Br Breaches eaches

  19. Engagement with public and stakeholders

  20. Project Appraisal Investigations • Fluvial • Tidal • Groundwater • Surface Water • Ground Investigations

  21. Hydrological Modelling • Method • Catchments • Ridge inputs • Stream water storage on the Moors • Impact of proposed embankment and outfall structure

  22. Inter ‐ tidal modelling • Flows • Salinity • Sediment movement • Interaction with R. Frome

  23. Ridge & Arne Moors Groundwater • Responding • Monitoring • Interpretation

  24. Ridge Surface Drainage Investigations • Responding to concerns • Survey and results shared • Impact on project understood • Liaison with Parish Council

  25. Ground Investigations/ material suitability • Factual description of survey • Key findings • Settlement & Maintenance • Mixing on site • Importation

  26. Project timeline • Consultation results

  27. Te Terms of of Re Reference

  28. • Clarify role of the Group Con Contracti acting • Behaviours

  29. 1. Flooding Upda Updates 2. Public Access 3. Construction Traffic 4. Location of main embankment 5. Siltation

  30. Upda Update: • Tidal Fl Floodi ooding ng • Surface water • Ground water

  31. • Surface water • Ground water • Tidal

  32. • Surface water • Ground water • Tidal

  33. Vi Visit sitor Access Access Pr Principles: • Dante • We do not want access to have a negative impact on wildlife • We do want to provide access that will be beneficial to people, especially within local communities RSPB Arne will be the main focus of access • We are not proposing any significant • infrastructure at Arne Moors Enable ‘non ‐ car’ access if possible • Limit access to permitted trails and viewing • points

  34. Upda Update: • Excavate material from the site as much Cons Constructi truction on as possible Tr Traffic • Reduce size and length of embankments as much as possible • Longer, lower embankments – allows use of a wider variety of materials

  35. Upda Update: Loc Location tion of of • Location of lagoons Ma Main em embankm bankmen ent

  36. Em Emer erging ging opti option on

  37. Upda Update: Silt Siltatio tion in in Ri River er Fr From ome • Analysis of historic surveys and and Upper Upper • Results expected later this year Wa Wareham Channel Channel • Plan to survey area before works start to establish the baseline conditions

  38. Futur Future to topics fo for discussion discussion

  39. • Groundwater Meeting 25 September Ne Next St Step eps • Public Exhibition – November

  40. Project Stages EA Internal Audit stages Long list options Strategic Outline Case Ne Next St Step eps Short list options We are here Preferred option Outline design Outline Business Case Detailed design Planning Application Construction Full Business Case drawings Construction

  41. Project Stages Timeline Long list options November 2016 Ne Next St Step eps Short list options Summer 2017 We are here Preferred option Outline design Spring 2019 Planning Application Detailed design Winter 2019/20 Construction Early Spring 2020 drawings Spring 2020 – Construction Autumn 2021

  42. Ne Next Me Meet eting • 18 th October?

  43. Thank you • TheMoorsAtArne@environment ‐ agency.gov.uk • https://www.dorsetcoast.com/groups/the ‐ moors ‐ at ‐ arne ‐ coastal ‐ change ‐ project/