the durner building 9 5 2019
play

The Durner Building 9/5/2019 The Durner Building 2449 Gilbert - PowerPoint PPT Presentation

The Durner Building 9/5/2019 The Durner Building 2449 Gilbert Avenue Estimated Total Project Cost $2,860,261 THE PROJECT The Ensemble Fire Co 16 & Hamilton House Paramount Building Comfort Station Durner Building 954 E McMillan In


  1. The Durner Building 9/5/2019

  2. The Durner Building 2449 Gilbert Avenue Estimated Total Project Cost $2,860,261 THE PROJECT

  3. The Ensemble Fire Co 16 & Hamilton House Paramount Building Comfort Station Durner Building 954 E McMillan In Progress Complete Complete Complete In Progress CoMADE Active Tenant REACH Homes Five Points Paramount Square Scholar House Trevarren Flats Poste In Progress Complete In Progress In Progress Complete In Progress LOCATION

  4. Durner Building In Progress LOCATION

  5. Previous Work • Roof replacement and repair • Repaired parapet wall • Filled in basement encroachment Current Work • Cleanout and stabilization • New/repaired windows and doors • Restored storefront system • Reconstructed cornice • Masonry repair CURRENT/PREVIOUS WORK

  6. • Mixed-use, mixed-income • 9 total residential units • 2 units reserved for residents earning 80% AMI or less • 3 one-bedroom, 6 studio apartments • 2,600 ground floor commercial • Affordable, accessible co-working space on the ground floor • Consistent with our equitable development scorecard FUTURE PLANS

  7. FUTURE PLANS

  8. FUTURE PLANS

  9. Estimated Total Project Cost $2,860,261 Estimated City NOFA Request $350,000 We are requesting a letter of support so that we may be eligible to apply for the gap funding we need! OUR ASK

Recommend


More recommend