the deep heat mining project
play

THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. - PowerPoint PPT Presentation

THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. Hopkirk 1 & Markus O. Hring 2 DEEP HEAT MINING Association (CH-8162 Steinmaur) 1 Polydynamics Engineering, CH-8708 Mnnedorf 2 Hring Geo-Project. CH-8162 Steinmaur M.O.


  1. THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. Hopkirk 1 & Markus O. Häring 2 DEEP HEAT MINING Association (CH-8162 Steinmaur) 1 Polydynamics Engineering, CH-8708 Männedorf 2 Häring Geo-Project. CH-8162 Steinmaur M.O. Häring, R.J. Hopkirk 2006

  2. DHM PILOT PROJECT The DHM Association was set up at the request of the Federal Office of Energy (FOE) and started work in 1996, a Swiss R & D group having been active already then for 20 years . It defined and undertook the following tasks: • It would discover how feasible EGS now really was .............. and if it might probably become useful in Switzerland. • If yes, it would find several possible EGS sites and choose one for a pilot plant, • It would initiate, obtain finance for and plan this first pilot plant, ensuring that EGS technology has the best possible chance to prove itself. • If the technology proves itself, DHMA would continue to promote it and to encourage the necessary R & D and the motivation of young specialists. The FOE would provide “seeding money” for these tasks. Power plant construction and operation must be financed from private sources. 2. M.O. Häring, R.J. Hopkirk 2006

  3. SITE SELECTION Criteria for site selection for the PILOT PLANT: • Do the local utilities and population need its energy production and do they welcome the plant in their midst? • Are the geological and geothermal conditions as favourable as they can be to maximize the chance of success? • Is land available? • Is water available? • Will the project be environmentally acceptable in construction and in operation? 3. M.O. Häring, R.J. Hopkirk 2006

  4. SITE SELECTION - superposed maps of site-critical parameters: geology, crustal thickness and regions of large scale heat demand 4. M.O. Häring, R.J. Hopkirk 2006

  5. SITE SELECTION - Heat flow map Data from: “Geothermal map of Switzerland”, Medici & Rybach 1995 5. M.O. Häring, R.J. Hopkirk 2006

  6. SIGNIFICANT DECISIONS IN ORDER TO HELP MAKE EGS MORE ATTRACTIVE EVEN AT THE PILOT STAGE : 1. To aim for co-generation of electrical energy and heat to ensure greater income 2. To use a hybrid surface plant if possible, combining geothermal and other sources These two decisions point to Basle as first and Geneva as second choice • Both have expanding District Heating networks currently: – Basle: covering a maximum demand already over 300MW – Geneva: covering a maximum demand of ca. 45MW • Both offer additional energy sources (eg. incineration plants) • Aims for GEOTHERMAL generation alone in the first pilot plant: – 3MW(e) & 20 MW(th) 6. M.O. Häring, R.J. Hopkirk 2006

  7. Two sites in the Rhine graben EU Project Soultz-sous-forêts DEEP HEAT MINING Project, Basel Some similarities are likely between these two sites 7. M.O. Häring, R.J. Hopkirk 2006

  8. SITE SITUATION E-W section across the southern Rhine Graben seismic data from Bonjer 1997 8. M.O. Häring, R.J. Hopkirk 2006

  9. DEEP HEAT MINING Basel • geothermal power plant using EGS technology for co-generation of electricity and heat Heat exchanger • electricity und heat for 5'000 households: Monitoring w ell - 20 MW thermal power 5 - 6 km - 3 MW electrical power • annual reduction of CO 2 emissions: - 40'000 t stimulated Fracture system 9. 1 - 1.5 km M.O. Häring, R.J. Hopkirk 2006

  10. DHM Basel - how it fits in DHM Pilot Plant Kleinhüningen Minimum target output: • geothermal power plant using EGS Monitoring Station Monitoring Station St. Johann technology for co-generation of electricity Otterbach and heat for 5'000 households: - 20 MW thermal power - 3 MW electrical power • annual reduction of CO2 emissions 40 kt/a District heating grid Desired rock heat exchanger: • Initial rock temperature 200 - 230°C • Probable depth 5-6 km • Three-well unit system - well spacing at bottom-hole 700 - 1000 m 10. M.O. Häring, R.J. Hopkirk 2006

  11. Project plan Pre-project studies & pilot hole, 2001 1 assuring finance & permissions Monitoring System & 2006 2 1st deep well to 5‘000 m + Exploration 2nd deep well 3 2007 4 Circulation testing 3rd deep well 2008 5 System stimulation and testing Development & Construction 2009 6 Power plant construction 11. M.O. Häring, R.J. Hopkirk 2006

  12. Exploration Concept 12. M.O. Häring, R.J. Hopkirk 2006

  13. Financial Risk Management Exploration phase Construction phase 90 high risk level 80 70 60 Mio CHF 50 40 30 20 10 low risk level 1 2 3 4 5 6 Milestones 13. M.O. Häring, R.J. Hopkirk 2006

  14. Geothermal & monitoring well sites 14. M.O. Häring, R.J. Hopkirk 2006

  15. Vertical Seismic Profile (VSP) in OT2 Dec. 2004 15. M.O. Häring, R.J. Hopkirk 2006

  16. First indications of Basement stress field orientation induced breakouts main Rhinegraben flexure Monitoring well Otterbach 2 induced fractures 16. M.O. Häring, R.J. Hopkirk 2006

  17. The main site at Kleinhüningen Summer 2004 - Before site preparation January 2006 - concreting rig foundation 17. M.O. Häring, R.J. Hopkirk 2006

  18. DHM Basel - some more numbers Exploration phase: 2 geothermal wells 5’000 - 6‘000 m 3 new monitoring wells 250 - 600 m 3 monitoring stations in existing holes 600 - 2‘750 m Main (geothermal) wells: April 2006 - November 2007 All monitoring wells but one are complete Instrumentation is being tested & installed Budget limit for exploration phase: ca. 60 Mio CHF = Risk capital Budget estimate for entire pilot plant: ca. 100 Mio CHF KCA-Deutag T45 Drill Rig 18. M.O. Häring, R.J. Hopkirk 2006

  19. Vision for the future: Swiss EGS power plants Up to several tens of plants by 2050 - varying sizes, varying depths according to site characteristics and local energy demands ....... • Heat exchanger depth ranges 4 - 7 km • Source temperatures 150 - 250 °C • Number of wells per site 3 - 20 • Power outputs from geothermal energy alone - if for el. generation only 5 - 40 Mwe (i.e.: without hybrid cycles) - if for heat production only 30 - 200 MWth • Specific Investment 2 - 3 Mio CHF/MW installed • Generating costs 0.1 - 0.2 CHF/kWh - electrical energy 0.03 - 0.06 CHF/kWh - heat • CO2- Reduction (heat prod. only) 10 - 200 kt/a 19. M.O. Häring, R.J. Hopkirk 2006

  20. Closing remarks - a caution Use of EGS technology outside geothermal anomalies is itself still a vision Nothing is certain until EGS is proven to be commercially viable Several successful pilot plants are needed so that: underground heat exchangers can be created - at any promising site; - of the right size to fulfill a local energy demand. Much depends upon “getting it right first time” in these pilot plants and DHM Basel is one of these - for Switzerland it is all-important. Only then can EGS become accepted as an Available Energy Source 20. M.O. Häring, R.J. Hopkirk 2006

  21. THE END Thank you for your patience and attention! For the current status of DHM Basel see www.geothermal.ch For other aspects see www.dhm.ch 21. M.O. Häring, R.J. Hopkirk 2006

Recommend


More recommend