support services building
play

SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL - PowerPoint PPT Presentation

SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL CENTER PENN STATE AE SENIOR THESIS FINAL PRESENTATION WILL LAZRATION CONSTRUCTION MANAGEMENT - DR. RILEY SUPPORT SERVICES BUILDING WILL LAZRATION PRESENTATION OUTLINE


  1. SUPPORT SERVICES BUILDING PENN STATE MILTON S. HERSHEY MEDICAL CENTER PENN STATE AE SENIOR THESIS FINAL PRESENTATION WILL LAZRATION CONSTRUCTION MANAGEMENT - DR. RILEY

  2. SUPPORT SERVICES BUILDING WILL LAZRATION PRESENTATION OUTLINE CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � I. PROJECT BACKGROUND II. INTRODUCTION OF ANALYSIS III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions II. Re-Design IV. ANALYSIS #2: ROOFING I. Part I: Roofing Type Comparison II. Part II: Elimination of Offset Roof V. ANALYSIS #3: RENEWABLE ENERGY SOURCES I. Part I: Geothermal System II. Part II: Installation of PV Array I. Site Analysis II. System Design VI. SUMMARY & CONCLUSION VII. ACKNOWLEDGEMENTS

  3. SUPPORT SERVICES BUILDING WILL LAZRATION PROJECT BACKGROUND CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � I. PROJECT BACKGROUND ������ � ����������������������������� II. INTRODUCTION OF ANALYSIS � ���������������������� III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions ��������� II. Re-Design � ������������������������ ���������� IV. ANALYSIS #2: ROOFING �������� ����������� I. Part I: Roofing Type Comparison � ��������� II. Part II: Elimination of Offset Roof � ������������ �!!!����"���#��� V. ANALYSIS #3: RENEWABLE ENERGY � "$�������%�&'�����(���������)$���� I. Part I: Geothermal System II. Part II: Installation of PV Array ������������������� SSB Site I. Site Analysis � *��������������+�*���(�,"��,"$��� II. System Design � ���������)�%�+����-�.��/� VI. SUMMARY & CONCLUSION � ���0��������+�1 ��2�3�22 4!!�5�� � �������������*����+��, ,�! !�� 6,2 ,�! VII. ACKNOWLEDGEMENTS

  4. SUPPORT SERVICES BUILDING WILL LAZRATION PHOTOVOLTAIC ARRAY SYSTEM DESIGN CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � ARRAY ORIENTATION & TILT COMPARISON I. PROJECT BACKGROUND Annual AC Energy Yearly Output per Module vs. Array Tilt Angle Array Orientation Min. Row Spacing Size of System Average Solar Radiation kWh/ Panel/ II. INTRODUCTION OF ANALYSIS Angle Max # of Panels (Deterate Factor of 0.8) to Avoid Shading (kW) (kWh/m^2/day) Year Due South Orientation (kWh) III. ANALYSIS #1: FOUNDATION RE-DESIGN 410.00 Rotated 31° 11'-10" 252 80.64 4.41 97,118 385.39 Yearly Output per Module 35° I. Initial Conditions Due South 9'-9" 253 80.96 4.55 101,033 399.34 400.00 (kWh/year/module) II. Re-Design Rotated 31° 10'-5" 248 79.36 4.42 95,832 386.42 30° 390.00 IV. ANALYSIS #2: ROOFING Due South 8'-8" 269 86.08 4.54 107,280 398.81 380.00 I. Part I: Roofing Type Comparison 370.00 II. Part II: Elimination of Offset Roof 9:00 AM 12:00 PM 3:00 PM 360.00 V. ANALYSIS #3: RENEWABLE ENERGY 350.00 I. Part I: Geothermal System 340.00 II. Part II: Installation of PV Array 0 5 10 15 20 25 30 35 40 45 50 I. Site Analysis Array Tilt Angle (°) II. System Design VI. SUMMARY & CONCLUSION Minimum Row Spacing Determined by Shadow Lengths VII. ACKNOWLEDGEMENTS Rotated 31° Orientation with 35° Tilt Due South Orientation with 35° Tilt

  5. SUPPORT SERVICES BUILDING WILL LAZRATION PHOTOVOLTAIC ARRAY SYSTEM DESIGN CONSTRUCTION MANAGEMENT PENN STATE MILTON S. HERSHEY MEDICAL CENTER PRESENTATION OUTLINE � � � � Feed From Inverter to Combiner Panel/Box Sizing I. PROJECT BACKGROUND � Max current from inverter data sheet: 91A/phase II. INTRODUCTION OF ANALYSIS 15kV Utility In DC Power From Array � 91A x 1.56 (NEC Multiplier) = 142A III. ANALYSIS #1: FOUNDATION RE-DESIGN I. Initial Conditions � NEC Table 310.15(B)(2)(a): Multiplier for 4-6 current carrying 500 kVA Transformer 500 kVA II. Re-Design conductors in a raceway = 0.8 Satcon 75kW Transformer Inverter IV. ANALYSIS #2: ROOFING � NEC Table 310.16 (90°C Wire): 2/0 AWG = 195A I. Part I: Roofing Type Comparison Inverter 1 set of (4) 2/0 AWG Main Electrical Room Net Meter 195A x 0.8 = 156A > 142A => OK II. Part II: Elimination of Offset Roof Production Meter Combiner V. ANALYSIS #3: RENEWABLE ENERGY AC FUSED DISCONNECT SWITCH SIZING Panel/Box I. Part I: Geothermal System � Max current from inverter data sheet: 91A/phase Load Meter 400A AC Fused II. Part II: Installation of PV Array Disconnect Switch I. Site Analysis � 91A x 3 phases 1.25 (NEC Multiplier) = 342A II. System Design Main Distribution Panel � Ideal fused disconnect switch size: 350A => not available => 400A VI. SUMMARY & CONCLUSION VII. ACKNOWLEDGEMENTS � Interrupt Rating must be greater than; 500kVA / (.480kV * 3^ (1/2) = 600A

Recommend


More recommend