south gate storm drainage project
play

South Gate Storm Drainage Project Open House Agenda April 25, 2006 - PowerPoint PPT Presentation

South Gate Storm Drainage Project Open House Agenda April 25, 2006 Introduction Presentation Information Stations Sponsored by: Sponsored by: Presented by: Presented by: South Gate Blvd. Project General Questions and


  1. South Gate Storm Drainage Project � Open House Agenda – April 25, 2006 � Introduction � Presentation � Information Stations Sponsored by: Sponsored by: Presented by: Presented by:

  2. South Gate Blvd. Project General Questions and Concerns Submitted After 1 st Public Meeting Sept 22, 2005: � Time frame of project � Flooding associated with private systems � Low spots along street � Why project is necessary Project Area South Gate Boulevard from 35 th Street to Highway 2

  3. South Gate Blvd. Project � Time Frame: Summer 2006 � Reported Problem Areas � Blues Bike Shop � Manzitto Construction/Day Care � Parking lot at 33 rd and Pioneers � Low spot on South Gate between Daniel Road and Pioneers � Why Project is Necessary

  4. South Gate Blvd. Project � Proposed Project Elements: � New Storm Sewer � New Inlets � New Overland Flow Path � Options Considered � Sidewalk to Curb Area � In-Street (selected)

  5. South Gate Blvd. Project � Proposed Project Elements: � New Storm Sewer provides additional capacity for runoff along South Gate and Pioneers

  6. South Gate Blvd. Project � Addition of Overland Flow Path Overland Flow Path provides outlet for extreme events that exceed system capacity

  7. South Gate Blvd. Project � Project Phasing

  8. South Gate Blvd. Project � Project Phasing 300’ 300’ 300’

  9. South Gate Blvd. Project � Information Stations � Questions and Comments � Written Comment Sheets Storm Sewer System Outlet at Highway 2 (Taken April 2005)

Recommend


More recommend