Siting/Conventional Facilities Status Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016 Agenda Progress over the last year Current Activities Plans for CD-1 2 S. Dixon | 2016 P2MAC 3/15/2016 Progress Over


  1. Siting/Conventional Facilities Status Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016

  2. Agenda • Progress over the last year • Current Activities • Plans for CD-1 2 S. Dixon | 2016 P2MAC 3/15/2016

  3. Progress Over the Past Year • Developed a cooling strategy for Linac and Transfer Line based on equipment loads Participants: M. Ball, C. Cameron, E. Huedem, J. Hunt, V. Lebedev, A. Vivoli 3 S. Dixon | 2016 P2MAC 3/15/2016

  4. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 4 S. Dixon | 2016 P2MAC 3/15/2016

  5. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac See following slides 5 S. Dixon | 2016 P2MAC 3/15/2016

  6. Progress Over the Past Year PIP-2 Transport • Technical Board Meeting – Line to Booster December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 6 S. Dixon | 2016 P2MAC 3/15/2016

  7. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 7 S. Dixon | 2016 P2MAC 3/15/2016

  8. Current Activities – Through August 2016 • Conceptual Design (phase 1) – Document the spatial and infrastructure requirements; – Develop conceptual design drawings; – Weekly meetings with stakeholders; Meeting Minutes (PIP-II-doc-70) • Wetland Delineation Update – Spring of 2016 • Siting Alternatives • One-for-One Replacement (space bank) Strategy 8 S. Dixon | 2016 P2MAC 3/15/2016

  9. Planned Activities for CD-1 • Architect/Engineer Selection (September/October 2016) – Work Scope based on Phase 1 drawings – Establish Source Evaluation Board – Send RFI to Candidate Firms • Conceptual Design (phase 2) (November 2016 – CD-1 Review) – Site Characterization – Soil Borings; – Further develop conceptual design drawings; – Detailed Cost Estimate – Detailed Schedule • Develop Resource Loaded Schedule 9 S. Dixon | 2016 P2MAC 3/15/2016

  10. Planned Activities for CD-1 • CD-1 Requirements (from 413.3B, 11-29-2010) – Acquisition Strategy – Project Execution Plan – Risk Management Plan – Independent Cost Estimate Review – One-for-One Replacement – High Performance and Sustainable Building – Preliminary Hazard Analysis Report – Integrated Safety Management Plan – Quality Assurance Program – Safeguards and Security Requirements – NEPA Strategy – Environmental Compliance Strategy 10 S. Dixon | 2016 P2MAC 3/15/2016

  11. Siting Strategies Mu2e G-2 Booster Transport Line PIP-2 Linac 11 S. Dixon | 2016 P2MAC 3/15/2016

  12. Siting Strategies 12 S. Dixon | 2016 P2MAC 3/15/2016

  13. Cross Section Gallery Linac Enclosure Typical Section 13 S. Dixon | 2016 P2MAC 3/15/2016

  14. Cross Section Equipment Envelope Preliminary Linac Enclosure Section 14 S. Dixon | 2016 P2MAC 3/15/2016

  15. Site Context View from Northwest From Fermilab Campus Master Plan 15 S. Dixon | 2016 P2MAC 3/15/2016

  16. Questions 16 S. Dixon | 2016 P2MAC 3/15/2016