site restoration standards
play

SITE RESTORATION STANDARDS George Desch, VT ANR NDCAP December 1, - PowerPoint PPT Presentation

SITE RESTORATION STANDARDS George Desch, VT ANR NDCAP December 1, 2016 : Non-radiological SRS : Vermont jurisdiction PSB and parties have established SRS 2013 Order process for establishing complete SRS CONTEXT Site


  1. SITE RESTORATION STANDARDS George Desch, VT ANR NDCAP – December 1, 2016

  2. : Non-radiological SRS : Vermont jurisdiction PSB and parties have established SRS 2013 Order – process for establishing complete SRS CONTEXT

  3.  Site Restoration to begin immediately after radiological D&D  Restore site to Unrestricted use: VT - IROCPP; ISFSI exception  Removal of all structures  No rubblization  All other Vermont laws apply SITE RESTORATION STANDARDS

  4.  12/31/2014 - complete assessment of non-radiological conditions  Subsequently - Parties to work in good faith to establish SRS  Parties may agree to different standards and timing of Site Restoration if property were to be used for commercial/industrial use SITE RESTORATION STANDARDS

  5.  Complete site assessment not submitted  State of VT has requested complete site assessment  Parties have discussed additional site restoration standards; no agreement in place. CURRENT STATUS