SiD and MDI Meeting CR-3 Implementation Plans and Intro to CR-4 V Kuchler 13 January, 2015
Overview • ILC Change Management Board • Change Request 3 Implementation Plan • Change Request 4 2 SiD and MDI Meeting 13 January 2015
Change Management Board (CMB) 3 SiD and MDI Meeting 13 January 2015
Change Request - 3 4 SiD and MDI Meeting 13 January 2015
CR-3 Implementation Plan • Implementation Team Named by CMB V Kuchler, K Buesser, T Markewicz, M Miyahara, J List, B List, T Sanuki • There are Complicating Factors TDR Contains Existing Drawings, Text and Cost Estimates The Scope of CR-3 Includes a Change in the Detector Hall Design and Access as Well as a Change of Location The Site has not yet Been “Officially Selected” by the Japanese Government as the Host Site The Current Design will be Subject to More Changes Before a Complete Site Specific Design is Completed The Change in the Detector Hall Location Will Affect One of More of the Horizontal Access Entry Locations and Overall Tunnel Lengths How to Properly Document the Effect of the Approved Change is the Challenge at Hand 5 SiD and MDI Meeting 13 January 2015
6 SiD and MDI Meeting 13 January 2015
7 SiD and MDI Meeting 13 January 2015
8 SiD and MDI Meeting 13 January 2015
9 SiD and MDI Meeting 13 January 2015
CR-3 Implementation Plan cont. • The Focus will be to Limit the Effort to the Detector Hall Area Only • B List has Put Together a List of Affected Existing Documents • These will Be Reviewed and an Evaluation of the Scope and Resources Needed will be Developed • This is the First Change Request that has been Approved So We are Developing a Process • A Method to Capture the Correct Amount of Documentation in EDMS will be Developed 10 SiD and MDI Meeting 13 January 2015
Change Request 4 11 SiD and MDI Meeting 13 January 2015
12 SiD and MDI Meeting 13 January 2015
Summary • CR-3 has been Approved • A Method for Documenting the Change and Collecting the Data in EDMS is Currently Being Developed • CR-4 has just been Submitted • Further Discussion of CR-4 will Take Place at the Next AD&I Meeting at the End of January • It is Likely that CR-4 will Initially Focus Only on the Civil Construction Impact and Not a Technical Review of How the Space will be Utilized 13 SiD and MDI Meeting 13 January 2015