s chematic d esign n ew c onstruction study option c6 1
play

S CHEMATIC D ESIGN | N EW C ONSTRUCTION STUDY OPTION C6.1 On April - PowerPoint PPT Presentation

G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA T OWN C OUNCIL P RESENTATION A UGUST 6, 2019 Raymond Design Associates R ECAP | P ROJECT TO D ATE Fall, 2019: April July 2019: Anticipated town-wide February 2015: Development of


  1. G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA T OWN C OUNCIL P RESENTATION A UGUST 6, 2019 Raymond Design Associates

  2. R ECAP | P ROJECT TO D ATE Fall, 2019: April – July 2019: Anticipated town-wide February 2015: Development of schematic design ballot to vote for funding Roof Collapse at and cost estimates design/construction of Mitchell Elementary November 2017 – May 2018: the new Mitchell School followed by Community Workshops and Public procurement, Interviews, Elementary School sprinkler system Public Presentations to gather Selections, and MSBA approvals for pipe failure that led input and comments on the new hiring of Owner’s Project Manager to flooding of Mitchell School design and Architect “Central Wing” We Are Here January 14, 2016: June 2018 – April 2019: August 2019: Statement of Interest submitted to Study of location/site options (7 sites Anticipated MSBA Board of studied), grade configuration options Massachusetts School Building Directors meeting to receive Authority (MSBA) (PreK – 2 or PreK-3), and existing approval of Schematic Design. conditions of building and site at 500 February 15, 2017: South Street. MSBA voted Mitchell ES into Next step, Funding the Project! Eligibility Period.  PreK-2 Grade Configuration selected June 10, 2017:  Location at 500 South Street selected Bridgewater voters approve $800,000 to fund Feasibility Study MSBA approval and invitation to Schematic Design phase. Town Council Presentation | August 6, 2019 2

  3. S CHEMATIC D ESIGN | N EW C ONSTRUCTION – STUDY OPTION “C6.1” On April 10, 2019 the MSBA Board of Directors approved the Preferred Option (C6.1) and invited the project to proceed in to the Schematic Design Phase M EETS E DUCATIONAL R EQUIREMENTS  S AFETY & S ECURITY C ONCERNS A DDRESSED  B ETTER P ARKING AND V EHICLE C IRCULATION  S USTAINABILITY AND E NERGY E FFICIENCY  B ETTER S TUDENT H EALTH AND W ELLNESS F ACILITIES  O NE C ENTRAL E NTRANCE AND O NE M AIN O FFICE  M OST E FFICIENT / B EST V ALUE O PTION  http://bridgewaterschoolproject.com/why-build-option-c6-1/ Town Council Presentation | August 6, 2019 3

  4. S CHEMATIC D ESIGN | E DUCATIONAL S PACES  Grade levels in clusters  Flexible classroom spaces to meet educational program  Improved Special Education spaces  STEM/STEAM environments  Flexible layout / expansion  One Main Entrance / Increased Security / Centralized Admin  Natural daylighting  Ground floor spaces for before and after school programs Town Council Presentation | August 6, 2019 4

  5. S CHEMATIC D ESIGN | E DUCATIONAL S PACES Town Council Presentation | August 6, 2019 5

  6. S CHEMATIC D ESIGN | E DUCATIONAL S PACES Town Council Presentation | August 6, 2019 6

  7. S CHEMATIC D ESIGN | E DUCATIONAL S PACES Town Council Presentation | August 6, 2019 7

  8. S CHEMATIC D ESIGN | S ITE P LAN  Increased # of parking spaces (approx. 302)  Improved traffic and pedestrian circulation  Student safety / secure play areas  Improved accessibility  Separate bus and car queues (approx. 63 cars can queue on- site)  Separate bus exit on to RT 18 (right turn only)  Shaded areas and buddy benches in playgrounds Town Council Presentation | August 6, 2019 8

  9. S CHEMATIC D ESIGN | S ITE P LAN Town Council Presentation | August 6, 2019 9

  10. S CHEMATIC D ESIGN | C OMMUNITY - USE F EATURES  Single, separate after-hours entrance  High School sized basketball & volleyball court with 120 bleacher seats  Cafetorium with stage and seating for 375 (one of the largest meeting spaces in town)  Two-sided stage situated between Cafeteria and Gym to allow for expanded or programs  Access to family playgrounds and outdoor learning spaces Town Council Presentation | August 6, 2019 10

  11. P ROJECT C OSTS | E STIMATED P ROJECT B UDGET + R EIMBURSEMENT MITCHELL SCHOOL – NEW CONSTRUCTION Option C6.1 $800,000 FEASIBILITY STUDY (OPM, Designer, Environmental, Site, Other) $64,679,981 CONSTRUCTION (Demo, Foundation, Shell, Interiors, Mechanical-Electrical-Plumbing & Fire Protection, Fixtures, Sitework) $11,380,000 ADMINISTRATION, OPM, ARCHITECT, FF&E, OTHER MISC. (Legal, Printing, Advertising, Utility, Permitting, Moving, Inspections) $3,740,019 CONTINGENCY (Owners and Construction Contingency) $80,600,000 TOTALPROJECT MSBA Reimbursement Rate w/ Incentives for Eligible Costs 59.28% Example ineligible costs: legal fees, advertising, printing, moving, permits, utility costs Example capped costs: Construction Cost ($333/SF), Furniture, Fixtures and Equipment ($2,400/student), Site costs (8% max) Estimated MSBA “Effective” Reimbursement Rate of Total Project Costs 41.97% $33,828,113 Anticipated MSBA Reimbursement Anticipated Town Share $46,771,887 Town Council Presentation | August 6, 2019 11

  12. F UNDING THE P ROJECT | MSBA P OLICY MSBA Policy for Project Approval • To qualify for any funding from the MSBA, the District must follow the MSBA statute and regulations. The Schematic Design submittal informs the basis of the approved project scope, schedule and • Maximum Total Facilities Grant. In order for the MSBA to enter into a Project Scope and Budget Agreement with the District, the • District must: Submit a Schematic Design for the proposed project prior to the MSBA Board meeting • Receive approval from the MSBA Board for its proposed project • • Return 3 signed copies of the Project Scope and Budget Agreement to MSBA In order for the MSBA to enter into a Project Funding Agreement with the District, the District must • secure local authorization and funding within 120 days of the MSBA Board's vote. Town Council Presentation | August 6, 2019 12

  13. F UNDING THE P ROJECT | MSBA P OLICY MSBA policy if Town fails to vote to appropriate funding A failed vote “will likely result in the school district being required to submit a new SOI and await • invitation”. In a typical year, the MSBA receives more than 80 statements of interest and invites less than 15 districts in to their eligibility period. There is no guarantee that the district would receive another invitation to eligibility. • Loss of approx. $33.8 Million in potential state funds + reimbursement rates are subject to change in the future based on MSBA funding capacity and future changes to policy. The value of construction continues to rise at a steady rate. Construction cost reports list the • Boston region at a 4.42% annual increase from January 2018 to January 2019. Any future project is estimated to have a greater construction cost due to industry-wide cost increases. Town Council Presentation | August 6, 2019 13

  14. S CHEDULE | E STIMATED C ONSTRUCTION S CHEDULE Town Council Presentation | August 6, 2019 14

  15. S TAY I NFORMED | P ROJECT W EBSITE + E MAIL Please visit www.bridgewaterschoolproject.com for more information or to sign up for our newsletters! If you would like to contact us directly, please send us an email at: bridgewaterschoolproject@gmail.com T HANK Y OU ! Town Council Presentation | August 6, 2019 15

Recommend


More recommend