ris risk informed informed emergency emergency
play

Ris Risk-Informed Informed Emergency Emergency Core Core Cooling - PowerPoint PPT Presentation

Ris Risk-Informed Informed Emergency Emergency Core Core Cooling Cooling Requirements Requirements (10 (10 CFR 50.46a) CFR 50.46a) March 24, 2011 Speakers Speakers and Topics and Topics Opening: Bill Borchardt, EDO


  1. Ris Risk-Informed Informed Emergency Emergency Core Core Cooling Cooling Requirements Requirements (10 (10 CFR 50.46a) CFR 50.46a) March 24, 2011

  2. Speakers Speakers and Topics and Topics • Opening: Bill Borchardt, EDO • Introduction: Eric Leeds, NRR • Rule Concept and Staff Views: William Ruland, NRR/DSS • Background and Rule Requirements: Richard Dudley, NRR/DPR • Generic Supporting Studies: Rob Tregoning, RES/DE 2

  3. Summary Summary of Rule Concept; of Rule Concept; Staff Staff Thoug Thoughts hts on Issuan on Issuance ce William Ruland Director, Division of Safety Systems Office of Nuclear Reactor Regulation

  4. § 50.46a 50.46a Final Rule Concept Final Rule Concept • Alternative to existing ECCS requirements ( § 50.46) • LOCAs divided into 2 regions based on break frequency – by transition break size (TBS) • Requirements unchanged for 1 st region (≤ TBS) 4

  5. § 50.46a 50.46a Final Rule Concept Final Rule Concept • In 2 nd region (> TBS) LOCA mitigation requirements relaxed for lower frequency breaks • Plant changes “enabled” by new requirements also evaluated by a risk-informed process 5

  6. § 50.46a Final Rule Concept 50.46a Final Rule Concept • Transition Transition break siz break size – PWRs – largest attached pipe to the main coolant piping – BWRs – largest attached feedwater or residual heat removal line inside containment 6

  7. ECCS A ECCS Analysis Requirements nalysis Requirements • Breaks < TBS – No change from current § 50.46 • Breaks > TBS – No single failure assumption – Credit for offsite power – Credit for non-safety equipment – Acceptance criteria: coolable geometry & long term cooling 7

  8. Staff Staff View Views on s on § 50.46a 50.46a Rule Rule • Maintains adequate protection • Provides design and operational flexibility • Incorporates stakeholder input • Regulatory analysis shows large potential benefits 8

  9. Staff Staff View Views on s on § 50.46a 50.46a Rule Rule • Risk assessment requirements consistent with Risk-Informed Fire Protection - 10 CFR 50.48(c) • Design constraints consistent with ACRS recommendations on defense-in-depth 9

  10. Staff Staff View Views on s on § 50.46a 50.46a Rule Rule • Rule has been much debated • Base changes on experience • Investment to evaluate benefits is unlikely until rule is issued • Potentially useful for GSI-191 10

  11. Staff Staff View Views on s on § 50.46a 50.46a Rule Rule • Uncertainties are important • Frequency curves developed by expert judgments based on best available information • Rule developed in consideration of uncertainties associated with rare events 11

  12. Stakeholder Stakeholder Concerns Concerns • Burden for beyond TBS breaks not commensurate with safety significance • TBS too large 12

  13. Stakeholder Concerns (con’t) • Requirements should not be relaxed until ECCS acceptance criteria in 50.46(b) are finalized • Current ECCS models and criteria are non-conservative and therefore relaxing other input conservatisms is unsafe 13

  14. Background and Rule Background and Rule Requir Requirements ements Richard Dudley Senior Project Manager Division of Policy and Rulemaking Office of Nuclear Reactor Regulation

  15. Background Background • Proposed rule November 2005 • Industry commented on rule burden • 2 public meetings • November 2006 ACRS concerns on defense-in-depth • Current rule balances safety with essential burden 15

  16. Overview of § 50.46a Rule Process and Requirements 16

  17. Conversion Conversion to to § 50.46a 50.46a • Demonstrate applicability of expert elicitation report and seismic study – To ensure the generic conclusions on adequate safety apply • NRC must review and approve licensee’s application 17

  18. For For Cha Changes nges Enabled b Enabled by y § 50.46a • Re-analyze ECCS for the new configuration • For non-safety equipment credited in >TBS analysis: – List in Administrative Controls section of Tech Specs (no LCOs) – Provide capability for on-site power 18

  19. For For Cha Changes nges Enabled b Enabled by y § 50.46a • Perform risk-informed evaluation – Demonstrate adequacy of: • defense-in-depth • safety margins • monitoring program – Demonstrate that risk acceptance criteria are met (“very small”) 19

  20. Opera Operationa tional Req l Requirem uirements ents • Review all future plant changes to ensure applicability of generic studies • Periodically confirm via PRA update that total risk increase “very small” • Do not operate in condition not meeting > TBS acceptance criteria for more than a short time 20

  21. App Applicability licability to New to New Rea Reactor ctors • Can use rule if new reactor is “ similar similar ” in design and operation • Applicant must propose and justify – “similarity” and appropriate TBS • NRC design-specific review – approve similarity and TBS 21

  22. Generic Generic Studies Studies Performed to Performed to Supp Support ort Determining Determining the the Transition Br Transition Break Size eak Size Robert Tregoning Senior Advisor for Materials Division of Engineering Office of Nuclear Regulatory Research

  23. Background Background • March 2003 SRM directed staff to estimate LOCA frequencies – Realistically conservative – Incorporate margins for uncertainty • LOCA frequencies documented in NUREG-1829 23

  24. NUREG NUREG-1829: 1829: Scope and Scope and Signi Significant Assumptions ficant Assumptions • Scope Scope: : Generic BWR and PWR passive-system LOCA frequencies • Assumptions – Typical plant history and operation – No future plant changes that affect LOCA frequencies 24

  25. NUREG NUREG-1829: 1829: Results Results • Panelists provided quantitative estimates supported by rationale – Rat Rationale: ionale: Good agreement – Est Estimate imates: s: Large uncertainty • Results sensitive to aggregation scheme 25

  26. NUREG NUREG-1829: 1829: Use of Results Use of Results • Use in § 50.46a – Starting point for TBS values – Account for other considerations – Promote regulatory stability • Additional staff evaluation – Assessed other LOCA contributors – Evaluated risk due to seismic events 26

  27. NUREG NUREG-1903: 1903: Scope and Scope and Signi Significant Assumptions ficant Assumptions • Scope Scope: : Determine if seismic risk is acceptable for breaks > TBS • Assumptions – Plant information remains applicable – Stresses associated with rare seismic event are representative 27

  28. NUREG NUREG-1903: 1903: Results Results • Direct piping failures – Negligible risk if piping is not degraded – Flaws leading to failure in degraded piping are expected to be large • Indirect piping failures – Acceptable risk for two plants studied – Results are highly plant-specific 28

  29. NUREG NUREG-1903: 1903: Use of Results Use of Results • Use in § 50.46a – Risks of seismically induced LOCAs are expected to be acceptable – TBS selection is appropriate • Limitations – Analyses may not be applicable – Indirect failure risks not generically evaluated 29

  30. Regulator Regulatory Guide Development y Guide Development • DG-1216 published for comment – Maximizes use of prior submittals – Provides multiple options • Stakeholder comments – Guidance is too complex – Costs may limit application of rule • Pilot plant study proposed 30

  31. Acronyms Acronyms NRC – Nuclear Regulatory Commission ECCS – emergency core cooling system TBS – transition break size LOCA – loss of coolant accident PWR – pressurized water reactor BWR – boiling water reactor DBA – design basis accident LCO – limiting conditions for operation 31

  32. Acronyms Acronyms ACRS – Advisory Committee on Reactor Safeguards GSI – Generic Safety Issue PRA – probabilistic risk assessment CFR – Code of Federal Regulations RG – Regulatory Guide 32

  33. Bac Backu kup Optional Optional Self Self-Appro Approval P val Process rocess • If self-approved change process is desired, submit risk-informed process • Criteria for self-approved changes: – “minimal” risk increase – § 50.59 is satisfied 33

  34. Bac Backu kup Applicability Applicability to New Reactors to New Reactors • Risk change acceptance criteria – Same as current plants, but further limited to not allow significant reduction in level of safety provided by new Part 52 design 34

Recommend


More recommend