rich street bridge partnering the pilot
play

Rich Street Bridge Partnering: The Pilot Chuck Kiner, District Six - PDF document

3/27/2012 Ohio Department of Transportation Rich Street Bridge Partnering: The Pilot Chuck Kiner, District Six Tom Graf, Kokosing Construction Jo John R. hn R. Kasic sich, , Governor Jerr Jerry W y Wray, Director w w w. t r a n s p o


  1. 3/27/2012 Ohio Department of Transportation Rich Street Bridge Partnering: The Pilot Chuck Kiner, District Six Tom Graf, Kokosing Construction Jo John R. hn R. Kasic sich, , Governor Jerr Jerry W y Wray, Director w w w. t r a n s p o r ta t i o n . o h i o . g ov Rich Street Bridge Rich Street Bridge 2012 Conaway Conference 2 1

  2. 3/27/2012 Hall of Famer – Ralph Kiner Hall of Famer – Ralph Kiner 3 Hall of Famer – Ralph Kiner Hall of Famer – Ralph Kiner 4 2

  3. 3/27/2012 “You’ve got to be very careful if you don’t know where you’re going, because you might not get there” Yogi Berra 5 “If you don’t know where you are going, how can you expect to get there?” Basil C. Walsh 6 3

  4. 3/27/2012 What is “Partnering”? What is “Partnering”? Partnering. A collaborative process for project cooperation and communication meant to achieve effective and efficient contract performance and completion of a project within budget, on schedule, safely and with requisite quality in accordance with the contract. 7 Rich street bridge project Rich street bridge project So what did we do? Brought in ReAlignment Group Identify key partners Best partnering practices Survey the partners Follow up w/ quarterly meetings Lessons learned 8 4

  5. 3/27/2012 Rich Street Bridge Project Rich Street Bridge Project Identify stakeholders Mission statements RFI process Dispute resolution, chain of command and notice Meeting frequency Milestones and key issues Public outreach Safety 9 Rich Street Bridge Project Rich Street Bridge Project Challenges? You bet. Design – over 100 RFI’s Coordination with adjacent projects Staff Changes Weather 10 5

  6. 3/27/2012 Rich Street team report Rich Street team report 1 1 Rich Street team report Rich Street team report 12 6

  7. 3/27/2012 Rich Street team report Rich Street team report 13 14 7

  8. 3/27/2012 Rich Street team report Rich Street team report 15 Rich Street team report Rich Street team report 16 8

  9. 3/27/2012 Rich Street team report Rich Street team report Section 6. ion 6. G Goal R Review view Continued Continued 17 Rich Street team report Rich Street team report 18 9

  10. 3/27/2012 Rich Street team report Rich Street team report 19 Rich Street Bridge Project Rich Street Bridge Project The Outcome/Bottom Line Partnering Works Good Communication Good Project Coordination Great looking project Bid Amount $21,871,269 with less than 2% in change orders No Claims 20 10

  11. 3/27/2012 High-water During Drilled Shaft High-water During Drilled Shaft Construction Construction 21 Drilled Shafts and Temporary False Drilled Shafts and Temporary False Work Erection Work Erection 22 11

  12. 3/27/2012 Temporary False Work Temporary False Work 23 Beam Erection (B-Segment) Beam Erection (B-Segment) 24 12

  13. 3/27/2012 Beam Erection (C-Segment) Beam Erection (C-Segment) 25 Beam Erection Beam Erection 26 13

  14. 3/27/2012 Beam Erection (A-Segment) Beam Erection (A-Segment) 27 Winter Protection to facilitate Winter Protection to facilitate Grouting of the Rib Tendons Grouting of the Rib Tendons 28 14

  15. 3/27/2012 Winter Protection to facilitate Winter Protection to facilitate Grouting of the Rib Tendons Grouting of the Rib Tendons 29 High-water in February of 2011 High-water in February of 2011 30 15

  16. 3/27/2012 High-water in March of 2011 High-water in March of 2011 31 Deck pour Deck pour 32 16

  17. 3/27/2012 A view from Above August 2011 A view from Above August 2011 (Courtesy of ODOT Aerial Engineering) (Courtesy of ODOT Aerial Engineering) 33 A view from Above August 2011 A view from Above August 2011 (Courtesy of ODOT Aerial Engineering) (Courtesy of ODOT Aerial Engineering) 34 17

  18. 3/27/2012 Installation of Deck Tendons Installation of Deck Tendons 35 Bridge Walkway Construction Bridge Walkway Construction 36 18

  19. 3/27/2012 Bridge Walkway Construction Bridge Walkway Construction 37 Temporary False work is coming down Temporary False work is coming down 38 19

  20. 3/27/2012 Under Deck Lighting Test Under Deck Lighting Test 39 Under Deck Lighting Test Under Deck Lighting Test 40 20

  21. 3/27/2012 Pylon Construction Pylon Construction 41 Pylon Construction Pylon Construction 42 21

  22. 3/27/2012 Pylon Construction Pylon Construction 43 Complete Deck, Sidewalk, and pylons Complete Deck, Sidewalk, and pylons 44 22

  23. 3/27/2012 Overview as March 9, 2012 Overview as March 9, 2012 45 Rich Street Bridge Night Rich Street Bridge Night Rendering Rendering 46 23

Recommend


More recommend