Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018
Presentation Agenda PART A Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245) PART B Highway 49 and Old Highway 2/ York Road Intersection
Project Location Highway 49 / Old Highway 2 Intersection Airport Rd
PART A: Bay of Quinte Skyway Project Location (Site 11-245 ) AIRPORT ROAD BAY OF QUINTE NORTHPORT ROAD SKYWAY (SITE #11-245) COUNTY ROAD 49 BAY OF QUINTE
Historical Photo - 1966
Existing Bridge Configuration
Background Bay of Quinte Skyway Bridge, Highway 49 Constructed 1964-1967 17 span high level bridge, 847 m long Carries 2 lanes on N-S oriented traffic Steel girders, concrete deck 5 continuous spans, 6 expansion joints 1992-dual columns replaced with single shaft at 3 piers
Existing Condition Deck: Extensively deteriorated (corrosion) Substandard barrier walls Substandard lane width Girders: Many fatigue prone details general coating failure Substructure: Generally sound except Pier 14 (beneath EJ) Minor scour at Pier 13 footing Abutments cannot accommodate widening
Bridge Rehabilitation Work Replace superstructure Reconstruct abutments, including new caissons, new wingwalls Replace bridge bearings/alter bridge articulation Eliminate expansion joints over piers Rehabilitate and strengthen piers New approach slabs Reconstruct highway approaches to the bridge Illumination
Rehabilitated Bridge Configuration Continuous deck – no expansion joints over piers Road profile – same as existing
New Superstructure 225 mm thick concrete slab TL-5 walls 4 steel girders 11.55 m wide deck Two 3.75 m traffic lanes Two 1.5 m wide side clearances 90 mm asphalt and waterproofing 2% crossfall
Construction Overview New superstructure with Superstructure Replacement Scheme 4 steel girders 5 segments, replace 1 segment per year ‘Half-and-half’ staged construction with a single-lane of bi-directional traffic on the bridge controlled by temp. traffic signals for each Segment. All lanes available during seasonal shutdown
Expansion Joint (EJ) Replacement Full closure required for modular expansion joint installation . Legend: Eliminate existing EJ Replace EJ and ramp over Temporary EJ required
Construction Sequence Year Segment Major Work 1 - Advance work 2 C Replace segment 3 B Replace segment 4 D Replace segment 5 E Replace segment & Reconstruct abutment 6 A Replace segment & Reconstruct abutment 7 A Install EJ
Duration & Sequencing (1) 2018 (Year 1) Prepare site; procure structural steel for Segment C Structural steel repair (CIF) girders in west half of Segment C; Rehabilitate pier caps at Piers 8 and 11 Part B (Highway 49 / Old Highway 2 / York Rd. intersection) 2019 (Year 2) Replace Segment C superstructure Rehabilitate pier caps at Piers 5,6 and 7 to accommodate 2020 construction; Structural steel repair (CIF) girders in west half of Segment B Install traffic signals to accommodate 2020 construction 2020 (Year 3) Replace Segment B superstructure Rehabilitate pier cap at Pier 14 to accommodate 2021 construction; Structural steel repair (CIF) girders in west half of Segment D Install traffic signals to accommodate 2021 construction
Duration & Sequencing (2) 2021 (Year 4) Replace Segment D superstructure Structural steel repair (CIF) girders in west half of Segment E Install traffic signals to accommodate 2022 construction 2022 (Year 5) Replace Segment E superstructure Reconstruct south abutment and install modular type of expansion joint Rehabilitate pier caps at Piers 3 and 4 Structural steel repair (CIF) girders in west half of Segment A Install traffic signals for Segment A 2023 (Year 6) Replace Segment A superstructure and Reconstruct north abutment Install and maintain temporary ramp over expansion joint opening 2024 (Year 7) Install Modular Expansion Joint in Segment A Demolish Old Band Building
Construction Duration and Sequencing (3)
Construction Staging Year 2 – 2019 – Segment C Year 3 – 2020 – Segment B Year 4 – 2021 – Segment D 2019 Year 5 – 2022 – Segment E Year 6 – 2023 – Segment A 2020 2021 2022 2023
Seasonal Shutdown Seasonal shutdown each year, all traffic lanes available Work below the bridge deck is permitted; no traffic disruption Work on Highway 49 affecting traffic or requiring lane closures not permitted
Traffic Management: Full Mainline Closures of Hwy 49 Type of Full Closure Description Short Duration Full Closures o 30 minutes during night hours (9 p.m. – 6 a.m.) o Unlimited number Extended Duration Full o ½ - 2 hours during night hours (9 p.m. – 6 a.m.) Closures o Maximum 52 occurrences Full Night Closures o 9 p.m. – 6 a.m. o Police required o Maximum of 45 occurrences No full closures permitted in 2018 Advance notification required Penalties for late opening
Traffic Management: Full Mainline Closures of County Rd 35 Type of Full Description Closure Extended Duration o ½ - 2 hours during night (9 p.m. – 6 a.m.) o Police required o 5 occurrences Passage for emergency vehicles shall be readily available at all times
Restrictions on Crane Placement No heavy equipment or cranes on any section of existing bridge in a 2 girder configuration
Snow Removal Contractor responsible for snow and ice removal within work area Remove within 3 hours of a snowfall event Dispose at appropriate dump site Snow removal plan each year Snow removal against barrier by AMC, vacate work area
Utilities Bell and Hydro plant traverse Hwy 49 north of CR 35 Union Gas plant crosses beneath BOQ on west side of bridge Portions of abandoned Union Gas main may be present within the existing highway embankment near each end of BOQ Skyway Bridge
MBQ Fishing Rights Area between piers 10 and 12 to remain accessible for MBQ to exercise fishing rights during July and August each year Exception: only when construction work is performed between the piers Advise intention to restrict access prior to May 15
Abutment Reconstruction Reconstruction of abutments & wingwalls Staged construction Four - 1200 mm diameter caissons with steel liners at each abutment South abutment and caissons – Year 5 North abutment and caissons – Year 6
Navigation
Environmental Issues Navigable waters permit Noise By Law exemption (must be renewed) Archaeological clearance Aeronautical lighting SARS Fisheries timing restrictions Spills Prevention
Environmental Constraints Environmental Specifics Species at Risk observed Yes o At least 9 species o o Exclusionary Fencing to be installed prior to April 15 of 1 st year of construction Blanding’s Turtle Barn Swallow Netting required o Breeding season timing window: March 31 - August 27 o Qualified Avian specialist required to screen for breeding migratory birds o Tree Removal Prohibited between March 31 and August 27 o Within window – Qualified Avian Biologist to conduct a nesting survey o Timing window for Barge For Segment C – No activity permitted between April 1 and May 20, 2019 o Operations For Segment D – No activity permitted between April 1 and May 17, 2021 o No sediment plumes o Timing window for all other in July 1 to September 15 o water work
Existing Water Intakes
Spill Prevention and Response Contingency Submit Plan for all activities within 30 m of watercourse Barge, equipment and other operations shall be at least 50 m away from shore wells and municipal water intakes Provide worker training Review Plan annually
Police Jurisdictions Area Police Service to be Contacted Tyendinaga Mohawk Territory Tyendinaga Police Service Prince Edward County Ontario Provincial Police
PART B Highway 49 and Old Highway 2/ York Road Intersection
Highway 49 and Old Highway 2 Location: Intersection of Highway 49 and Old Highway 2/York Road Scope: Removal is existing NB channelized right turn Adjustment to existing traffic signal poles Ditching to ensure positive drainage to existing ditch Benefit: Improves safety for vehicles entering or leaving trading post, gas station
Highway 49 and Old Highway 2 Contract details: To be completed in Year one of Contract prior to October 31, 2018 Access to entrances to remain open Traffic permitted to travel on granular grade No open granular permitted on weekends
Summary Construction Start: Spring 2018 Late season work anticipated All Traffic lanes restored during seasonal shutdowns. Contract Completion: May 2024
Thank you
Recommend
More recommend