rehabilitation of the bay of quinte skyway highway 49
play

Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid - PowerPoint PPT Presentation

Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018 Presentation Agenda PART A Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245) PART B Highway 49 and Old


  1. Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018

  2. Presentation Agenda  PART A  Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245)  PART B  Highway 49 and Old Highway 2/ York Road Intersection

  3. Project Location Highway 49 / Old Highway 2 Intersection Airport Rd

  4. PART A: Bay of Quinte Skyway Project Location (Site 11-245 ) AIRPORT ROAD BAY OF QUINTE NORTHPORT ROAD SKYWAY (SITE #11-245) COUNTY ROAD 49 BAY OF QUINTE

  5. Historical Photo - 1966

  6. Existing Bridge Configuration

  7. Background Bay of Quinte Skyway Bridge, Highway 49  Constructed 1964-1967  17 span high level bridge, 847 m long  Carries 2 lanes on N-S oriented traffic  Steel girders, concrete deck  5 continuous spans, 6 expansion joints  1992-dual columns replaced with single shaft at 3 piers

  8. Existing Condition Deck:  Extensively deteriorated (corrosion)  Substandard barrier walls  Substandard lane width Girders:  Many fatigue prone details  general coating failure Substructure:  Generally sound except Pier 14 (beneath EJ)  Minor scour at Pier 13 footing  Abutments cannot accommodate widening

  9. Bridge Rehabilitation Work  Replace superstructure  Reconstruct abutments, including new caissons, new wingwalls  Replace bridge bearings/alter bridge articulation  Eliminate expansion joints over piers  Rehabilitate and strengthen piers  New approach slabs  Reconstruct highway approaches to the bridge  Illumination

  10. Rehabilitated Bridge Configuration  Continuous deck – no expansion joints over piers  Road profile – same as existing

  11. New Superstructure  225 mm thick concrete slab  TL-5 walls  4 steel girders  11.55 m wide deck  Two 3.75 m traffic lanes  Two 1.5 m wide side clearances  90 mm asphalt and waterproofing  2% crossfall

  12. Construction Overview  New superstructure with Superstructure Replacement Scheme 4 steel girders  5 segments, replace 1 segment per year  ‘Half-and-half’ staged construction with a single-lane of bi-directional traffic on the bridge controlled by temp. traffic signals for each Segment.  All lanes available during seasonal shutdown

  13. Expansion Joint (EJ) Replacement  Full closure required for modular expansion joint installation . Legend: Eliminate existing EJ Replace EJ and ramp over Temporary EJ required

  14. Construction Sequence Year Segment Major Work 1 - Advance work 2 C Replace segment 3 B Replace segment 4 D Replace segment 5 E Replace segment & Reconstruct abutment 6 A Replace segment & Reconstruct abutment 7 A Install EJ

  15. Duration & Sequencing (1) 2018 (Year 1)  Prepare site; procure structural steel for Segment C  Structural steel repair (CIF) girders in west half of Segment C;  Rehabilitate pier caps at Piers 8 and 11  Part B (Highway 49 / Old Highway 2 / York Rd. intersection) 2019 (Year 2)  Replace Segment C superstructure  Rehabilitate pier caps at Piers 5,6 and 7 to accommodate 2020 construction;  Structural steel repair (CIF) girders in west half of Segment B  Install traffic signals to accommodate 2020 construction 2020 (Year 3)  Replace Segment B superstructure  Rehabilitate pier cap at Pier 14 to accommodate 2021 construction;  Structural steel repair (CIF) girders in west half of Segment D  Install traffic signals to accommodate 2021 construction

  16. Duration & Sequencing (2) 2021 (Year 4)  Replace Segment D superstructure  Structural steel repair (CIF) girders in west half of Segment E  Install traffic signals to accommodate 2022 construction 2022 (Year 5)  Replace Segment E superstructure  Reconstruct south abutment and install modular type of expansion joint  Rehabilitate pier caps at Piers 3 and 4  Structural steel repair (CIF) girders in west half of Segment A  Install traffic signals for Segment A 2023 (Year 6)  Replace Segment A superstructure and Reconstruct north abutment  Install and maintain temporary ramp over expansion joint opening 2024 (Year 7)  Install Modular Expansion Joint in Segment A  Demolish Old Band Building

  17. Construction Duration and Sequencing (3)

  18. Construction Staging Year 2 – 2019 – Segment C Year 3 – 2020 – Segment B Year 4 – 2021 – Segment D 2019 Year 5 – 2022 – Segment E Year 6 – 2023 – Segment A 2020 2021 2022 2023

  19. Seasonal Shutdown  Seasonal shutdown each year, all traffic lanes available  Work below the bridge deck is permitted; no traffic disruption  Work on Highway 49 affecting traffic or requiring lane closures not permitted

  20. Traffic Management: Full Mainline Closures of Hwy 49 Type of Full Closure Description Short Duration Full Closures o 30 minutes during night hours (9 p.m. – 6 a.m.) o Unlimited number Extended Duration Full o ½ - 2 hours during night hours (9 p.m. – 6 a.m.) Closures o Maximum 52 occurrences Full Night Closures o 9 p.m. – 6 a.m. o Police required o Maximum of 45 occurrences  No full closures permitted in 2018  Advance notification required  Penalties for late opening

  21. Traffic Management: Full Mainline Closures of County Rd 35 Type of Full Description Closure Extended Duration o ½ - 2 hours during night (9 p.m. – 6 a.m.) o Police required o 5 occurrences  Passage for emergency vehicles shall be readily available at all times

  22. Restrictions on Crane Placement  No heavy equipment or cranes on any section of existing bridge in a 2 girder configuration

  23. Snow Removal  Contractor responsible for snow and ice removal within work area  Remove within 3 hours of a snowfall event  Dispose at appropriate dump site  Snow removal plan each year  Snow removal against barrier by AMC, vacate work area

  24. Utilities  Bell and Hydro plant traverse Hwy 49 north of CR 35  Union Gas plant crosses beneath BOQ on west side of bridge  Portions of abandoned Union Gas main may be present within the existing highway embankment near each end of BOQ Skyway Bridge

  25. MBQ Fishing Rights  Area between piers 10 and 12 to remain accessible for MBQ to exercise fishing rights during July and August each year  Exception: only when construction work is performed between the piers  Advise intention to restrict access prior to May 15

  26. Abutment Reconstruction  Reconstruction of abutments & wingwalls  Staged construction  Four - 1200 mm diameter caissons with steel liners at each abutment  South abutment and caissons – Year 5  North abutment and caissons – Year 6

  27. Navigation

  28. Environmental Issues  Navigable waters permit  Noise By Law exemption (must be renewed)  Archaeological clearance  Aeronautical lighting  SARS  Fisheries timing restrictions  Spills Prevention

  29. Environmental Constraints Environmental Specifics Species at Risk observed Yes o At least 9 species o o Exclusionary Fencing to be installed prior to April 15 of 1 st year of construction Blanding’s Turtle Barn Swallow Netting required o Breeding season timing window: March 31 - August 27 o Qualified Avian specialist required to screen for breeding migratory birds o Tree Removal Prohibited between March 31 and August 27 o Within window – Qualified Avian Biologist to conduct a nesting survey o Timing window for Barge For Segment C – No activity permitted between April 1 and May 20, 2019 o Operations For Segment D – No activity permitted between April 1 and May 17, 2021 o No sediment plumes o Timing window for all other in July 1 to September 15 o water work

  30. Existing Water Intakes

  31. Spill Prevention and Response Contingency  Submit Plan for all activities within 30 m of watercourse  Barge, equipment and other operations shall be at least 50 m away from shore wells and municipal water intakes  Provide worker training  Review Plan annually

  32. Police Jurisdictions Area Police Service to be Contacted Tyendinaga Mohawk Territory Tyendinaga Police Service Prince Edward County Ontario Provincial Police

  33. PART B Highway 49 and Old Highway 2/ York Road Intersection

  34. Highway 49 and Old Highway 2  Location:  Intersection of Highway 49 and Old Highway 2/York Road  Scope:  Removal is existing NB channelized right turn  Adjustment to existing traffic signal poles  Ditching to ensure positive drainage to existing ditch  Benefit:  Improves safety for vehicles entering or leaving trading post, gas station

  35. Highway 49 and Old Highway 2  Contract details:  To be completed in Year one of Contract prior to October 31, 2018  Access to entrances to remain open  Traffic permitted to travel on granular grade  No open granular permitted on weekends

  36. Summary  Construction Start: Spring 2018  Late season work anticipated  All Traffic lanes restored during seasonal shutdowns.  Contract Completion: May 2024

  37. Thank you

Recommend


More recommend