RANGITIKEI DISTRICT COUNCIL ROADING NETWORK PRESENTATION BY REUBEN POKIHA AND PAUL MURPHY
INTRODUCTION Rangitikei District comprises 4,500 Km 2 Population of 14,500 Total network = 1237 Km’s 783 Km sealed 454 Km unsealed 222 bridges (includes culverts greater than 3.4 m 2 ) Approx 4673 culverts 80 Kms Footpaths
ROADING TEAM Shared Services with MDC Asset Manager- Roading 3 Project Engineers: • Project Engineer – Maintenance (Engineers Rep) • Project Engineer – AWPT /Reseals/Emergency Works • Project Engineer – Footpaths/Lighting/Trees/Public Enquiries
CONTRACT • Contract awarded to Downers • July 1 2010 – June 30 2015 • Contract price is approx $11.4m that includes AWPT and Reseals as separable proportions • AWPT Programme approx 9 Km’s per annum • Resurfacing Programme approx 70 Km’s per annum • Footpath Programme – $85,500 (Maintenance) $80,000 (Renewals) $60,000 (Capital)
CONTRACT • The aim District Plan to have a footpath at least down one side of the street • Streetlights approx 1890 in number • The latest NZTA/Audit NZ audit of the network indicated that the network is in good condition • Concerns the affect Forestry Industry may have to the roads
Taihape Napier Road 2 Finish Start AWPT site
Taihape Napier Road 2 Local Material 30T Excavator Greywacke (Sandstone)
Taihape Napier Road 2 Corner Visibility Improve Sightline
Taihape Napier Road 2 Test Results Existing Top 150mm – 200mm not suitable (Failing) Hard base
Taihape Napier Road 2 Rock Stockpile
Taihape Napier Road 2 Problems! 30T Excavator unable to move Suggestions please!!
Taihape Napier Road 2 Construction Milling
Taihape Napier Road 2 Construction Batter Work
Taihape Napier Road 2 Construction Batter Work
Taihape Napier Road 2 Construction
Taihape Napier Road 2 Savings • Local rock extraction - reduced metal import • Reduced number of truck movements • Estimated saving of $110,000
Taihape Napier Road 2 Savings • Stabilising v Traditional construction option - $100,000
Taihape Napier Road 2 Savings • Reduced number of truck movements across RDC network • Estimated reduction in pavement deterioration - $100,000
Taihape Napier Road 2 Savings • Rock extraction of corners on minor improvement sites - $200,000 • Taihape Napier 1 minor Improvement local material use - $60,000
Taihape Napier Road 2 Savings • Surplus rock crushed and utilised as maintenance metal - $100,000