project risk management a new approach
play

Project Risk Management: A New Approach Stefan Creemers Erik - PowerPoint PPT Presentation

Project Risk Management: A New Approach Stefan Creemers Erik Demeulemeester Stijn Van de Vonder Risk management 101 Risk identification Risk analysis Risk mitigation Risk control Risk management 101 Risk identification Quantify


  1. Project Risk Management: A New Approach Stefan Creemers Erik Demeulemeester Stijn Van de Vonder

  2. Risk management 101 Risk identification Risk analysis Risk mitigation Risk control

  3. Risk management 101 Risk identification • Quantify probabilities and impacts of risks • Assess the impact on project objectives Risk analysis • Calculate the project objectives Risk mitigation Risk control

  4. Risk management 101 Risk identification • Quantify probabilities and impacts of risks • Assess the impact on project objectives Risk analysis • Calculate the project objectives Risk mitigation Where to start? Risk control

  5. Project risk management: current approach Uncertainty is captured in activity durations:  Normal distribution  Triangular distribution  Beta distribution Monte Carlo simulation is used to obtain estimates of project objectives (e.g. cdf of the completion time)

  6. Project risk management: current approach Uncertainty is captured in activity durations:  Normal distribution  Triangular distribution  Beta distribution Monte Carlo simulation is used to obtain estimates of project objectives (e.g. cdf of the completion time)

  7. Risk mitigation: how is it done? TORNADO GRAPH

  8. Risk mitigation: how is it done? TORNADO GRAPH Focus mitigation efforts on the most sensitive activity; the activity that has the highest rank

  9. Ranking activities: existing measures Criticality index Significance index Cruciality index Schedule sensitivity index

  10. Problems with the current approach • Project managers have a very hard time to model uncertainty • All of the previous ranking measures have been criticized • It is not clear where the uncertainty originates from • It is unclear how to mitigate uncertainty

  11. New approach: risk-driven (instead of activity-based)! Risk 1 ACT 1 Risk 2 Activity duration distribution (ACT 1) Risk 1 ACT 2 Risk 3 Risk 4 ACT 3 Risk 5 … Project Risk 1 Risk 2 Risks 1&2

  12. Ranking risks: proposed measures Cruciality index Critical Delay Contribution (CDC)

  13. Advantages of the new approach • Risks are much easier to predict than uncertainty • CDC is calculated on risk per activity basis and can be aggregated on the level of risks and activities • Risks root causes are ranked => we know which risk to mitigate!

  14. Risk-driven = ranking of risks rather than activities TORNADO GRAPH

  15. Risk-driven = ranking of risks rather than activities TORNADO GRAPH

  16. Evaluation of the new approach using a computational experiment For a large set of projects (600 projects of PSPLIB 120): – Model uncertainty (i.e. define risks, impacts, probabilities…) – Simulate the project execution – For each ranking measure:  Calculate the highest-ranked risk according to the measure  Eliminate the highest-ranked risk (i.e. focus our mitigation efforts on this risk How good do the measures perform when mitigating 10 risks?

  17. Computational experiment: ranking measures ACTIVITY-BASED RISK-DRIVEN => => SELECT THE LARGEST RISK THAT IMPACTS THE SELECT THE LARGEST RISK HIGHEST-RANKED ACTIVITY CDC ACT CDC RISK CI ACT CI RISK SSI SI ACI

  18. Results

  19. Results Project Delay Number of risks eliminated

  20. Results Project Delay Random Number of Solution space risks eliminated Greedy Optimal

  21. Results ACI SI

  22. Results CI act SSI

  23. Results CDC act CDC = best of activity- based measures

  24. Results CI risk CDC act

  25. Results CI risk CDC risk CDC = best of risk-driven measures

  26. Conclusions • A risk-driven approach to project risk analysis is better than a activity-based approach • CDC is able to outperform current best practice measures (activity-based AND risk-driven) • CDC is very close to greedy optimal • Results are robust/hold for a wide variety of settings

Recommend


More recommend