presentation by presentation by indian sugar mills
play

Presentation by Presentation by Indian Sugar Mills Association 22 nd - PowerPoint PPT Presentation

CERC Public Hearing on Tariff Fixation for CERC Public Hearing on Tariff Fixation for Non conventional Energy Sources Presentation by Presentation by Indian Sugar Mills Association 22 nd July , 2009 1 22nd July , 2009 Bagasse based


  1. CERC Public Hearing on Tariff Fixation for CERC Public Hearing on Tariff Fixation for Non ‐ conventional Energy Sources Presentation by Presentation by Indian Sugar Mills Association 22 nd July , 2009 1 22nd July , 2009

  2. Bagasse based Cogeneration in India � Sugar Industry began cogen capacity addition following MNES promotional policy of 1993 ‐ 94. � Cogen capacity addition further boosted with preferential tariffs announced by SERC’s following direction given in Electricity Act 2003 and National Electricity Policy. � Present installed cogen capacity ‐ 3090 MW � Future investment in the sector largely dependant on the promotional policy & measures by the Govts. and Regulatory authorities. � CERC has already considered the directives laid down in Electricity Act 2003 and National Electricity Policy to promote co ‐ generation and, hence, we are limiting our National Electricity Policy to promote co generation and, hence, we are limiting our submission on the important parameters considered for determination of bagasse based cogen tariff in the draft Regulation. 2 22nd July , 2009

  3. Capital Cost � Capital cost of Rs 445 lacs/ MW for first year of control period (2009 ‐ 10) is considered in the draft Regulation ( Based on the data from IREDA and UNFCCC) � TNERC in its tariff order dated 06.05.2009 for co ‐ generation projects has considered capital cost of Rs. 4.67 crores / MW (Based on the average figure suggested by IREDA) � Evacuation cost of about Rs 25 ‐ 30 lacs per MW is to be borne by the developer. � Capital cost of about Rs 5.0 crores per MW need to be considered for tariff determination. 3 22nd July , 2009

  4. Depreciation � Depreciation of 6% considered in the draft Regulation based on term loan of 12 years. � The tenure of loan advanced by the banks and FIs is around 7 to 9 years. None of the cogen projects have got the loan period extending beyond this period. � TNERC in its recent order dated 06 05 2009 on cogen tariff has allowed � TNERC in its recent order dated 06.05.2009 on cogen tariff has allowed depreciation @ 7.84% per annum till depreciation accumulates to 90% of the project cost. � This may be considered in this Regulation also. 4 22nd July , 2009

  5. Plant Load Factor � Operational period of 240 days considered (uniform for all States) in the draft Regulation ‐ 180 days crushing season and 60 days non ‐ crushing season. � Crushing days of season vary significantly from State to State. Last 10 years average � C hi d f i ifi tl f St t t St t L t 10 data for major states indicate U.P. ‐ 126 days, A.P. ‐ 120 days, Karnataka ‐ 149 days Tamil Nadu ‐ 185 days � Crushing season of a State must be based on average crushing period of that State � PLF should be state specific � For operation during off season, tariff should take into account price of bagasse purchased at market price. 5 22nd July , 2009

  6. Bagasse Price � Proposed guidelines suggest bagasse price based on cost of equivalent calorific value of coal based on thermal power plants located in the respective States coal based on thermal power plants located in the respective States. � Wide variation in State to State bagasse price evaluated based on proposed guidelines ‐ Rs 761/MT in MP to Rs 1327/MT in Haryana � Cogen plants are located near load centers. Fair comparison could only be drawn with coal based thermal plants located near load centers. � The price of bagasse based on average coal price at Harduaganj, Panki and Parichcha Thermal Power Stations of Uttar Pradesh as reported in the generation tariff order of UPERC for the year 2008 ‐ 09 works out to be Rs.1300 per MT, against Rs 953/MT assumed in the draft regulations. � Market price of bagasse is now established & should ideally be the basis for price determination. This varies from state to State and in U.P. bagasse price is currently around determination. This varies from state to State and in U.P. bagasse price is currently around Rs 2300/MT ex ‐ factory. � Unless cogenerators get a fair and competitive price for bagasse , they will not be i incentivised to generate power. ti i d t t 6 22nd July , 2009

  7. Gross Station Heat Rate � Gross SHR of 4000 Kcal/KWH considered in draft regulation for bagasse based cogeneration plants . � The normative ratio of fuel cost between power and steam considered as 60:40 in the proposed guideline .This implies that fuel cost for power generation corresponds to SHR of 2400 Kcal/ KWH which is contradictory. � The bagasse consumption during season for power generation including process steam is found to be between 2.5 to 2.7 Kg per unit of electricity generated depending on the operating parameters of the plant. This translate into Gross SHR of 5625 to 6075 Kcal per Kg of bagasse. � A Gross SHR of 4000 Kcal/KWH has been considered in the draft regulation for bagasse based cogeneration plants. � It may be worth mentioning that the power and steam ratio varies from plant to plant during the season and the steam requirement for process is generally not more than 20 to 25% of the total steam generation. Therefore, a ratio of power to steam should be in the ratio of 75 to 25. � To have an actual idea of heat requirement of power generation, it would be prudent to consider off ‐ season operation when the plant is exclusively used for power generation. The SHR during off ‐ season is observed to be about 4000 KCal/KWH as per the actual operation data. 7 22nd July , 2009

  8. CDM Benefit Sharing � Proposal to pass on share of gross CDM proceeds to beneficiaries ‐ 10% in second year & increased by 10% every year till it reaches 50%. � Sharing of CDM benefits unfair and unjust ‐ CDM benefits are only for bridging viability gap. � Sharing of the CDM benefit will disqualify the project for CDM admissibility � Most cogen projects have faced rejection – Sharing CDM benefits with the beneficiary by way of a suitable adjustment in the tariff unjustified 8 22nd July , 2009

  9. Scheduling of electricity from renewable sources � Draft regulations propose that biomass power and non ‐ fossil fuel based cogen projects with installed capacity above 10 MW shall be be subjected to Scheduling and dispatch code under the Indian Electricity Grid Code (IEGC) and CERC (Unscheduled interchange and related matters) Regulations, 2009 � The cogen plants are continuous process by nature and any non despatch of � The cogen plants are continuous process by nature and any non ‐ despatch of power would render the heat for power generation waste � Cogen plants must be categorized as must run 9 22nd July , 2009

  10. Tariff Design � Draft Regulation proposes normative tariff on levellised basis for the Tariff Period. g p p � Renewable energy technologies having single part tariff with two components – Tariff on levellised basis for fixed cost component. Fuel cost component on year of operation basis operation basis. � Discount factor equivalent to cost of capital � Levellisation for the ‘useful life’ of the Renewable Energy project while Tariff for the period equivalent to ‘Tariff Period’. � Levellisation would affect project revenue stream – Insufficiency of funds in initial � Levellisation would affect project revenue stream Insufficiency of funds in initial years to service financial liabilities � Control period considered three (3) years. Tariff revision would affect the levellised value of tariff determined initially. � Tariff should be based on the normative parameters to cover annual financial obligations. obligations. 10 22nd July , 2009

  11. Summary of the parameters Parameters CERC Draft Regulation 2009 Comments by ISMA on Tariff for Renewable Energy Tariff Design Levelised tariff based on useful Normal yearly tariff based on actual parameters be lif life of the project. f th j t allowed. ll d Capital Cost Rs. 4.55 crores per MW Rs 5 Cr/MW including transmission evacuation charges PLF 60% based on 240 days y PLF should be State specific based on crushing p g operation season of respective states. Fuel Cost/ Bagasse price based on State Market price of bagasse should ideally be Bagasse price wise cost of equivalent calorific considered. value of coal varying from l f l i f If determined based on equivalent price of coal, Rs.761 per MT in MP to then price of bagasse based on coal price of Rs.1327 per MT in Haryana thermal plants located near load centres should be considered. id d SHR 4000 Kcal/ KWh with an SHR of 4000 Kcal/Kwh for power generation needs allocation of fuel cost between to be considered. power and steam in the ratio p of 60:40 11 22nd July , 2009

  12. Summary of the parameters ‐ contd Parameters CERC Draft Regulation Comments by ISMA 2009 on Tariff for Renewable Energy Auxiliary A ili 8 5% 8.5% Sh Should be 10% due to smaller capacities ld b 10% d t ll iti Consumption O&M Expenses 13.35 lacs/MW (3% of capital Should be 4% of capital cost as it is much higher in cost) ) comparison to conventional thermal plants p p Return on Equity 17% pre ‐ tax for first 10 year 18% post ‐ tax Depreciation 6% based on 12 year loan 7.84% depreciation should be allowed based on period period TNERC order dated 6 5 2009 for bagasse based TNERC order dated 6.5.2009 for bagasse based cogen plants. Carbon Credit Sharing proposed The CDM benefit therefore should remain with the developer. Scheduling As per scheduling and Must run status since cogeneration is a continuous despatch code. activity. 12 22nd July , 2009

  13. Th Thank you k 13 22nd July , 2009

Recommend


More recommend