PGE Salem Smart Power Center Demonstrations and Studies of Utility Scale Energy Storage Kevin Whitener, Project Manager – Dispatchable Standby Generation September 22, 2017
Salem Smart Power Center • 5 MW Power Capacity • 1.25 MWh Energy Capacity 2
South Salem – Oxford and 22 nd St. SE Portland General Electric 3
20 Eaton Inverters – 250kW each Portland General Electric 4
2,440 Li Ion Battery Modules ( ∼ 500Wh each) Portland General Electric 5
How Do We Control It? Three Programmable Logic controllers (PLC’s) • Schneider • Allen Bradley • Cooper Power Systems Dell PC running Archestra provides the HMI Portland General Electric 6
Use Cases • Use cases can be classified as PGE Power being energy System- Local Use Case or use cases or wide Benefits power use Energy Benefits cases Transactive Node Energy • Use cases Reliability Power can benefit PGE’s Solar Integration Both overall system Demand Response Energy operations or local Non-Spinning Reserve Energy conditions Frequency Response Power such as voltage and Power Factor Control N/A power factor Voltage Control N/A Portland General Electric 7
Noise on DC Side of Inverter Portland General Electric 8
Typical Solar Day in May Portland General Electric 9
Typical Load Curve in July Portland General Electric 10
Integration of Solar and Load Portland General Electric 11
Volt/VAr Control Portland General Electric 12
Volt/VAr Control – Inner Loop Portland General Electric 13
Volt/VAr Control – Outer Loop Portland General Electric 14
Frequency Response Portland General Electric 15
Portland General Electric 16