overview of the environmental management system
play

Overview of the Environmental Management System for HVac/HVdc - PowerPoint PPT Presentation

Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project October 8, 2015 1 2 Project Overview 4 Muskrat Falls HVac/HVdc Project Components Two 315 kilovolt High Voltage


  1. Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project October 8, 2015 1

  2. 2

  3. Project Overview

  4. 4

  5. Muskrat Falls HVac/HVdc Project Components • Two 315 kilovolt High Voltage alternating current (HVac) transmission lines between Muskrat Falls & Churchill Falls (Labrador Transmission Assets) • 1,100 km High Voltage direct current (HVdc) transmission line between Muskrat Falls & Soldiers Pond near St. John’s (Labrador-Island Transmission Link) • Strait of Belle Isle Marine Cable Crossing (3 X 30 km long cables) 5

  6. AC Transmission: Muskrat to Churchill Falls • Clearing for right-of-way complete – 250 km – Clearing: 2,450 hectares • Towers and foundations – 1,250 Towers – 8,125 foundations • Conductors and Fiber Optic cables – 2-315 Kv, 3 phase conductors – Fiber Optic Cable – Approx. 40% complete • Work will be substantially complete in 2015

  7. 7

  8. 8

  9. DC Transmission: Labrador-Island Link • Clearing for right-of-way ongoing across province – 1,100 km – ROW Clearing – 6,554 ha • Towers and foundations – First tower erected in Labrador in April 2015 – 1,760 Towers (Labrador) – 2,225 Towers (Island) – Tower erection ongoing in Labrador; start tower assembly on island in October 2015

  10. 10

  11. 11

  12. Conductor Stringing HVac Line 12

  13. Strait of Belle Isle Marine Cable Crossing • First land cables installed in Shoal Cove, Sept. 2015 • Marine cable manufacturing underway in Japan; last of three cables expected in September each 30 kms. in length • Successfully completed horizontal directional drilling (HDD) program; longest landfall application in world • On track for marine cable installation across the Strait next year 13

  14. 14

  15. 15

  16. Environmental Management System Integration of EMS into Project Execution – All Components • Design Requirements • Technical Specifications • Procurement Packages • Bidder Evaluation • Kick-Off Meeting Support • Weekly Reports to Stakeholders • On-Going Field Monitoring • Use of Powerline by all stakeholders 16

  17. Collaborative Regulatory Framework Blanket Permits • – Water crossings (>1900) – Quarries (>500) – Historic resources – Vegetation clearing Proactive Reporting • – Online reporting – Powerline updated constantly – Weekly report to all regulators Monitoring Tools • – Electronic forms (iPad) – Real-time field reports and constraint monitoring 17

  18. HVac/HVdc Construction Monitoring • Dedicated on-site environmental monitors at each work front • Real-time access to all EMS components via satellite and internet connections • All monitors use an interactive prontoform database and iPad that provide inspection forms and direct connection to Powerline and the project office • Dedicated environmental permit coordinators, engineers and planners 18

  19. Real-Time Internet Reporting • Pre-set Prontoform templates • GIS / GPS Mapping functions • Real-time photograph transfers • Immediate distribution to project office coordinators and engineers • Field (Camp) access to Powerline database and constraint mapping 19

  20. Environmental Effects Monitoring Program Purpose is to monitor the overall project • effects and to confirm the predictions of EA and fulfill EA commitments LCP has implemented more than 15 • comprehensive environmental effects monitoring programs Key programs include: • RWM caribou – MM caribou – Newfoundland marten – Newfoundland caribou – Avifauna – HHRA – 20

  21. LCP Powerline (Internet Based Environmental Management )

  22. LCP Powerline  Web-based  Project GIS database  Real-time data upload  Real-time connection to: Project documents/permits Government databases Contractor work locations Photograph library 22

  23. LCP Powerline - Layers GROUP SUB-GROUP DISPLAY NAME GROUP SUB-GROUP DISPLAY NAME Upper Labrador N/A Work Camps IMAGERY N/A Quarries - New Applications Lower Labrador N/A Quarries - Permits N/A Lower Island Centerlines Upper Island Towers Churchill River 2006 TRANSMISSION - INFRASTRUCTURE Tower Boxes SUPPLIES WATER Public Water Supplies INFRASTRUCTURE - ROW N/A AC Line ROW Chainage (250m) Drainage Outside Protected ROW Chainage (5km) As-built Access Road (Valard) Stream Crossing Plan of the Day AC (Valard) Salmon Rivers - 30m Buffer AQUATIC Centerline Salmon Rivers - 200m Buffer Towers Wetlands Tower Boxes Archaeological Site HISTORIC ROW Archaeological Sites - 50m Buffer RESOURCES Portage Trails Electrode Lines ROW Chainage (250m) - Labrador Nesting Site - Raptors INFRASTRUCTURE - Nesting Sites - Raptors (Construction - 200m Buffer) ROW Chainage (5km) - Labardor DC Line Nesting Sites - Raptors (Helicopter - 300m Buffer) ROW Chainage (250m) - Island AVIFAUNA Nesting Sites - Raptors (Blasting - 500m Buffer) ROW Chainage (5km) - Island ENVIRONMENT Nesting Sites - Raptors (Clearing - 800m Buffer) Approved Access Trails (Valard) Bird Surveys (Edited) As-built Access Road (Valard) Bird Surveys (Buffer Zone) Plan of the Day DC (Valard) Listed Plants - Critical Habitat LCP Transmission Corridor Access Study (iii, 2011-2012) VEGETATION / Regionally Uncommon Plants - obs Forest Density PLANTS CLEARING AC LINE Red Pine Stands Clearing Status Caribou - Winter Habitat (Labrador) Forest Density Caribou - Calving Habitat (Labrador) DC LINE Clearing Status Caribou - Core Habitat (Island) Construction Blocks WILDLIFE Marten - Core Habitat Grants Marten - Critical Habitat Easements Beaver Lodge / Dam License To Occupy Parks and Nature Reserves LANDS Permission To Occupy PPWSA - Stream Buffer N/A LCP - Private Lands OTHER Winter Head Pond - 25m Municipal Boundaries Full Supply Level - 39m Planning Area Boundaries Outfitters NL Road Network 23

  24. LCP Powerline – Basemaps/Imagery 24

  25. LCP Powerline – Bog & Watercourse Constraint Layers 25

  26. Typical Watercourse Crossing and Bog Access 26

  27. Powerline – Caribou Constraint Layers 27

  28. Powerline – Raptor Buffer Constraint 28

  29. LCP Powerline – Field Integration 29

  30. LCP Powerline – Permit Compliance 30

  31. Thank you / Questions? 31

Recommend


More recommend