outline of talk transmission investment and access
play

Outline of Talk Transmission Investment and Access Valuing - PowerPoint PPT Presentation

Outline of Talk Transmission Investment and Access Valuing Transmission in Vertically Integrated (VI) Regime Engineering Reliability Valuing Transmission in Wholesale Market (WM) Regime Economic Reliability Why more


  1. Outline of Talk Transmission Investment and Access • Valuing Transmission in Vertically Integrated (VI) Regime – Engineering Reliability • Valuing Transmission in Wholesale Market (WM) Regime – Economic Reliability • Why more transmission capacity is needed in wholesale market regime Frank A. Wolak – Local market power – Transmission network as facilitator of commerce Department of Economics • Why very little transmission capacity has been built over past 30 years in US Stanford University • Methodology for Valuing Transmission Upgrades in VI Regime • Value of economically reliable transmission network to California Stanford, CA 94305-6072 • Paying for transmission expansion in wholesale market regime – Economic cost causation principles wolak@zia.stanford.edu • Congestion Revenue Rights (CRRs) under Locational Marginal Pricing (LMP) http://www.stanford.edu/~wolak – What they can and cannot hedge • Efficient CRR allocation Chairman, Market Surveillance Committee – A method for efficient CRR allocation of the California ISO 2 Valuing Transmission in VI Regime Valuing Transmission in VI Regime • VI utility has two choices for meeting an increase in demand at a given • VI utility has legal requirement to meet all demand at regulated retail price location – This implies that once retail price is set, revenue stream of VI utility does not depend on its production decisions – Construct local generation • VI may find it optimal to meet local energy need with high cost local – Increase transmission capacity to bring in more distant generation generation • VI utility’s retail price of electricity is regulated – Install 50 MW unit that costs $150/MWh to operate instead of upgrading local – Profit-maximizing response of VI utility is to choose system-wide least-cost transmission network solution to meet local load increase • Transmission upgrade with low-cost distant generation entails significantly • Value of transmission expansion in VI regime more regulatory risk – Displace high cost local generation with lower cost distant generation – Requires discrete transmission capacity expansion – Suppose it costs VI utility $50 MWh to produce energy locally but it can import • Much longer time horizon to construct transmission versus local generation energy at $20/MWh – Can require larger distant generation investment to realize economies to scale • Upgrade of 10 MW of capacity implies benefit of $300 = [($50/MWh - $20/MWh)*10 MWh] during hour – Commitments of previous regulator must be honored by current and future • Value of transmission is cost -saving to VI from increased ability to exploit regulators locational cost differences • Lower risk local generation solution creates regions with insufficient transmission capacity into region to meet all demand with distant generation – Reliability value of upgrade can be handled in this framework – San Francisco Bay Area • Upgrade of 10 MW to eliminate 0.01 probability of outage where 10 MWh of demand is curtailed at a cost of $10,000/MWh – San Diego Area (2,300 MW local generation to meet 4,500 MW peak load) • Expected benefit of upgrade is $998 = [0.01*($10,000/MWh - $20/MWh)*10 MWh] 3 4 1

  2. Engineering Reliability Differences in Supplier Incentives • Enough transmission capacity so that • Regime 1—VI utility (that owns local generation and – Demand at all locations in network can be met with pre- transmission network) had fixed price contract with retailer in specified probability DPL South – Assuming that vast majority of generation units in network – Strong incentive to limit locational price differences are owned and operated by same entity • Regime 2—Fixed price contract with retailer in DPL South • Because of structure of regulatory process in VI ended regime, strong incentive for VI to operate its – Strong incentive to increase locational price differences because this generation units to limit congestion increases value of VI utility’s local generation holdings and Congestion – Utility interested in minimizing total cost of supplying all Revenue Right (CRR) holdings of retail load • Regime 3—Large retailer divested large amount of DPL South – No incentive to operate high cost units more intensively to capacity to merchant generation owner increase locational price differences – Strong incentive to increase locational price differences between both • This only increases total costs of VI utility which reduces its profits DPL South (merchant supplier) and DPL North (large retailer) and • Recall VI utility’s revenue stream is independent of its actions other PJM locations 5 6 Incentives in Action in PJM Market Incentives in Action in PJM Market Average Real-Time Prices Real-Time Prices Average Regime 2: 07/23/99 - 06/24/01 Regime 1: 06/1/98 - 07/22/99 90.00 90.00 80.00 80.00 70.00 70.00 60.00 60.00 $/MWh 50.00 50.00 $/MWh 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Hour PJM West Hub DPL South DPL North PJM West Hub DPL South DPL North 7 8 2

Recommend


More recommend