OKI - SNK Workshop - March 8, 2016 Daniel Menetrey, P.E. Kentucky Transportation Cabinet District 6
Federal Funding Flow � Reimbursement Process � LPA pays for project first, then seeks reimbursement from KYTC. (80% reimbursement) LPA (80%) 2
Administering Office � KYTC District 6 Office � Administers State Funded Projects (SPP), and MPO (OKI) delegated Federal Funds (SNK) � Daniel Menetrey – D6 LPA Coordinator 3
Getting Started � Contact Administering Office � Get funds authorized � Get MOA signed � 20% local match required for all Federal Funds � Contact District LPA Coordinator � Schedule a Project Team Meeting early in the process � Federal Funded Projects require an Environmental Document to be completed 4
Professional Services � Professional Services Procurement � QBS Process – Advertise for at least 21 days � In House Staff � Engineer on retainer contract � Statewide Contracts – Contact Amanda Spencer 5
Design � Design must follow KYTC Standards � Standard Drawings can be found on KYTC’s Highway Design website � Submit all Plan submittals to the D.O. LPA Coordinator � Traffic Management Plan (TMP) � Design Review Checklist (LDRC) 6
Right of Way & Utilities � Right of Way Certification required � Environmental Document is required before R/W can be acquired � LPAs are required to follow the Uniform Act � Must be offered just compensation for their property � If the value is less than $10,000 – Minor Acquisition Review (MAR) � Utility Relocation � Contact Utility Companies early in project � Provide to bidders Utility Impact Notes 7
Utilities 8
Construction Procurement � Construction Notice to Proceed � Project Development Checklist (LPA-PDC) � Funding Authorization & MOA for Construction � Construction Procurement Packet � LPA must obtain an Engineering Estimate from the Designer � DBE Goal (Disadvantaged Business Enterprises) � Bid Advertisement, Bid Proposal & Design Plans � LDRC & LPA-PDC 9
Project Letting � LPA must advertise for at least 21 days before the bids are opened � Contract is to be awarded to the lowest responsive bidder � Contractor must be prequalified with KYTC (List found on KYTC’s website) � Send bid tabs to Administering Office (AO) � Have contractor sign contact � Notice to proceed from AO 10
Construction & Inspection � LPA must inspect the contractor’s work � Inspector must be onsite at some time every day � Verify that DBEs working on the project � Inspector must give a copy of all inspection reports to the LPA � Inspector or contractor must do materials testing 11
Construction & Inspection � Inspector helps LPA determine whether milestones are met for progress payments � LPA is required to promptly pay the contractor � LPA must notify the AO when the project is completed for Final Inspection and Acceptance & Project Closure � Change Orders 12
Reimbursement � Costs directly related to the project are reimbursable � LPA pays project expenses up front, then submits a request for reimbursement from Administering Office � Use Reimbursement Request Form � Include contractor invoices & cancelled checks (front and back) � LPA will be reimbursed 80% (Fed Funded) 13
Completed SNK LPA Projects Newport Carothers Road (KY 1892) Reconstruction 14
Completed SNK LPA Projects Covington Russell Street Resurfacing 15
Completed SNK LPA Projects Covington Caroline Ave Railroad Underpass 16
Completed SNK LPA Projects Covington – Latonia & Southern Ave Reconstruction (SNK) 17
Current SNK LPA Projects � Covington � 6 th Street Reconstruction � Riverfront Commons Trail (multi-city project) � Latonia Avenue Reconstruction � Johnson Street & Rivercenter Blvd Reconstruction � Edgewood � Dudley Road Reconstruction (Phase II & III) � Newport � Carothers Road Reconstruction (Phase II) � Riverfront Commons Trail Bridges 18
Current SNK LPA Projects � Crestview Hills � Thomas More Parkway Widening � Villa Hills � Buttermilk Pike Reconstruction � Ludlow � Riverfront Commons Trail � Kenton County � Bromley Crescent Springs Road Reconstruction (Phase I & II) 19
Current SNK LPA Projects � Kenton County Airport Board � Wendell Ford Boulevard Extension � Boone County � Longbranch Road Widening � Camp Ernst Road Turn Lane at Longbranch Road � Veterans Way Extension 20
Questions? Daniel Menetrey, PE KYTC D6 LPA Coordinator Daniel.Menetrey@ky.gov (859) 341-2700 http://transportation.ky.gov/Pages/default.aspx 21
Recommend
More recommend