oak chan elementary school modernization project
play

Oak Chan Elementary School Modernization Project SCHOOL - PowerPoint PPT Presentation

Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017 OVERALL SITE PLAN PROJECT OVERVIEW Phase 1 Milestone #1 (April 17 July 31, 2017): Grading, Placement of all temporary portable classroom, restroom,


  1. Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017

  2. OVERALL SITE PLAN

  3. PROJECT OVERVIEW Phase 1 – Milestone #1 (April 17 – July 31, 2017): Grading, Placement of all temporary portable classroom, restroom, administration and student care buildings,  including all utilities Multipurpose (Building B) modernization  Phase 1 – Milestone #2 (June – December 2017): Administration (Building A) modernization  Phase 1 – Milestone #3 (June 2017 – July 2018): Construction of Buildings C-10-plex Classroom, D – Learning/Media Center, E – 8-plex Classroom and F - Kindergarten  Phase 2 – Milestone #1 (June 2018 – July 2018): Hardcourt, apparatus yard, parking lot  Phase 2 – Milestone #2 (July 2018 – September 2018) Removal of temporary trailers, playfield restoration 

  4. Phase and Milestone Schedule

  5. SITE PLAN – April and May, 2017 & July – September 2018 – The entire playfield

  6. SITE PLAN – Summer 2017

  7. SITE PLAN – School Year 2017 - 2018

  8. SITE PLAN – Summer 2018

  9. Temporary Classroom & Restroom Buildings

  10. Administration Building

  11. Kindergarten

  12. Unit D - Learning/Media Center Building

  13. Exterior

  14. QUESTIONS & ANSWERS

Recommend


More recommend