north santiam school district long range facility
play

North Santiam School District Long-Range Facility Planning Committee - PowerPoint PPT Presentation

North Santiam School District Long-Range Facility Planning Committee December 5, 2019 THE CONSTRUCTION MARKET: PAST & PRESENT NATIONAL CONSTRUCTION COST INDEX COMPARATIVE COST INDEX 2019 3 RD QUARTER 2014-present North Santiam School


  1. North Santiam School District Long-Range Facility Planning Committee December 5, 2019

  2. THE CONSTRUCTION MARKET: PAST & PRESENT NATIONAL CONSTRUCTION COST INDEX COMPARATIVE COST INDEX 2019 3 RD QUARTER 2014-present North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  3. THE CONSTRUCTION MARKET: PAST & PRESENT COST $/SF AVERAGE K-12 COST $/SF 2019 3 RD QUARTER 2016 TO PRESENT 425 375 325 275 225 175 2016 2017 2018 2019 portland seattle North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  4. OREGON SCHOOL BONDS PASS FAIL $1,600,000,000 $1,400,000,000 $1,200,000,000 $1,000,000,000 $800,000,000 $600,000,000 $400,000,000 $200,000,000 $0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  5. OREGON SCHOOL BONDS $5,283,881,925 CURRENTLY UNDER CONTRACT PASS FAIL $1,600,000,000 $1,400,000,000 $1,200,000,000 $1,000,000,000 $800,000,000 $600,000,000 $400,000,000 $200,000,000 $0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  6. REGIONAL SCHOOL CONSTRUCTION 2019 2017 West Linn-Wilsonville 206.8 Hillsboro 408.0 Dayton 11.0 N. Marion 42.2 Bend 268.3 North Lake 5.0 Lake Oswego 187.0 Santiam Canyon 17.9 Portland 790.0 Tillamook 4.0 Vernonia 6.8 2018 2016 Astoria 70.0 Crow 4.0 Eugene 319.3 Gresham-Barlow 291.2 Oregon City 158.0 Monroe 6.0 Warrenton-Hammond 38.5 N. Clackamas 433.0 Corvallis 199.9 Seaside 99.7 Harrisburg 8.9 Sherwood 247.5 Nestucca 25.7 St. Helens 49.6 Tigard-Tualatin 291.3 Salem-Keizer 619.7 Gaston 12.0 Hood River 57.2 Junction City 14.6 Mapleton 4.0 McMinnville 89.4 Yamhill-Carlton 14.2 South Lane 35.9 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  7. REGIONAL SCHOOL CONSTRUCTION OSCIM Program Pre-Election Commitment Results for May 2020 • Centennial • Harney County • Baker • Pilot Rock • Sutherlin • Perrydale • North Santiam • Roseburg • Canby • Newberg (waiting list) • Estacada (waiting list) North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  8. EXPLANATION OF PROJECT COSTS Construction Cost The value paid to the general contractor to complete the project. In the case of a competitive hard-bid project, this is synonymous with the “bid price”. Soft Costs The costs paid to administer the project including, but not limited to: jurisdictional permits, survey and special inspections consultants, project management, design services, furniture fixtures & equipment, and construction contingencies. Total Project Cost = Construction Cost + Soft Cost Typically, a project budget is about 67% Construction Cost, 33% Soft Cost depending on scale and complexity. North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  9. MASTER PLANNING North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  10. MASTER PLANNING – Mari Linn Elementary 2 NEW CLASSROOMS & $1,923,437 SUPPORT SPACES NEW COVERED PLAY AREA $954,844 KITCHEN EXPANSION $267,356 SECURE ENTRY VESTIBULE $336,105 TOTAL $3,481,742 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  11. MASTER PLANNING – Security Vestibules EXISTING REMODEL Mari Linn Sublimity Elementary Stayton Middle North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  12. MASTER PLANNING – Stayton Middle & Intermediate 4 NEW CLASSROOMS & $3 037 625 SUPPORT SPACES NEW COVERED ½-COURT $702,765 ADDED PARKING & $763,875 STORMWATER SECURE ENTRY VESTIBULE $504,158 FOR MIDDLE SCHOOL SECURE ENTRY VESTIBULE $504,158 FOR INTERMEDIATE SCHOOL TOTAL $5,512,580 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  13. MASTER PLANNING – Stayton HS Stadium NEW COVERED STADIUM FOR 1,200 $1,663,720 SPECTATORS. INCLUDES PRESSBOX. CONCESSIONS & $259,437 TICKETBOOTH TOTAL $1,923,437 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  14. MASTER PLANNING – Stayton HS Overall 8 CLASSROOMS AND MEDIA CENTER / CAFÉ ADDITION / $21,856,297 REMODEL INCLUDING (OPTION 1) MECHANICAL UPGRADES AND NEW BOILER. NEW COVERED AREA AT CTE $229,163 SECURE ENTRY VESTIBULE $134,442 SEISMIC UPGRADES TO MAIN $4,575,611 GYM LOCKER ROOM EXPANSION $1,749,274 AND NEW FIRE SPRINKLER KITCHEN REMODEL AND $458,325 COMMUNITY USE SPACE TOTAL $29,003,112 North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  15. MASTER PLANNING – Sublimity Elementary 5 NEW CLASSROOMS + 1 NEW $3 037 625 MAKERSPACE WETLAB ADDED PARKING & $702,765 STORMWATER COVERED PLAY UPGRADES/ $763,875 REPAIR SECURE ENTRY VESTIBULE $504,158 TOTAL ELEMENTARY $6,048,209 TOTAL MIDDLE SCHOOL $4,870,849 MULTIPURPOSE BUILDING North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  16. North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

  17. Next Steps North Santiam School District– Long-Range Facility Planning Committee December 5, 2019

Recommend


More recommend