New Tyne Crossing Construction Activity Summary May 2009
North Cut and Cover Summary Transition structure Cut and cover excavation within Howdon Yard Tyne View Terrace diversion over temporary bridge Ongoing excavation (bottom up construction) Diaphragm wall work areas Crossover section (top down construction) Sewer diversions physically complete – testing and commissioning phase North cut and cover Current works – D-walls Excavation C&C Excavation Transition Preparation for crossover slabs Gas main diversion (Aerial Photo Mid March)
North Cut and Cover Cut and cover excavation beneath Tyne View Terrace temporary bridge – view north from Howdon Yard 12 May 09 Level of top slab of tunnel structure Bottom of excavation -6m AOD approx Third level of propping is remaining to be installed before base slab Howdon Yard Current works – Excavation C&C Excavation – Transition
North Cut and Cover Cut and cover excavation within Howdon Yard. View South View North Connection for Transition wall roof of tunnel Sewer bridge Second and south of Tyne propping levels – Howdon Yard View Terrace mid tunnel Current works – Excavation C&C Excavation – Transition 21 May 09
North Cut and Cover Cut and cover excavation within Howdon Yard. Excavation heading north Exposing roof connections on east wall Howdon Yard Current works – Excavation C&C Excavation – Transition 21 May 09
North Cut and Cover – Crossover section Gas main crossing Crossover section to be constructed using top down technique. Roof slab to be constructed first, the excavation beneath the slab to follow. Slurry wall to support reduced depth D-wall in crossover section (green material) Couplers for roof slab
North Transition Structure Ground level First intermediate propping level (-2.60 m AOD) Tunnel roof level Excavation approx 1- 2m short of final level for concrete base slab April 09 Second intermediate propping level – mid tunnel 21 May 09 (-9.70 m AOD)
North Approach – Gas main diversion East Howdon Bypass crossing A19 crossing Connection to existing mains Gas main diversion Works complete mid June De-mobilisation end June Cycleway diversion Cut and cover spoil stockpiles A19 crossing Connection to existing mains
Immersed Tube Units – TE 2D TE 1A Dock 4 TE 2C TE 1B Completed tunnel sub elements TE 2B TE 1C TE 2A TE 1D Wall / roof pours completed since TE 4D photo was taken in TE 3A mid March TE 3B TE 4C TE 3C TE 4B Dock 4, Wallsend Current works – Concreting of tunnel elements and TE 4A TE 3D internal fit out of ballast tanks and intermediate floors 11 No. of 16 sub sections complete (base and wall / roof pours)
Immersed Tube Units – Dock 4 Tunnel Element 2 Section D View from dock gate across TE 1 and TE 2 Ballast tank and intermediate floor installation in completed units Dock 4, Wallsend Current works – Concreting of tunnel elements and internal fit out of ballast tanks and intermediate floors 11 No. of 16 sub sections complete (base and wall / roof pours)
South Transition Structure View from southern river bank looking north-west Excavation depth approximately 16m below capping beam level. Photograph taken 27/5/09 3 No. levels of props installed, 2No. further prop levels required to be installed. Photograph taken 27/5/09
South Tunnel D-wall construction south of transition structure ongoing. Proposed completion Mid June 2009. Excavation of SCL 1 South access shaft in progress. Proposed completion end June 09. SCL construction proposed July 09. D-Wall Construction of SCL 2 north and south access shafts complete. D-Wall Construction of South cut and cover section in progress. Proposed completion for section July 09. View from Monastery Court looking north Photograph taken 11/5/09
Excavation of SCL No 1 northern shaft SCL Shaft Photograph taken 27/5/09
South Tunnel Construction of P4 Bridge abutments and central pier ongoing. Retaining wall adjacent A19 part demolished Bulk excavations ongoing New Jarrow Albion Sub-Station live Salem Street temporarily closed 22/5/09 High Street re-opened 22/5/09. Jarrow Albion Sub-Station now demolished CFA piles and capping beams complete Diaphragm wall construction ongoing. Proposed completion of section July 09. View from Monastery Court looking south. Photograph taken 11/5/09
South Tunnel Salem Street and Friar Way footpath closed following re-opening of High Street on 22 nd May 2009. Photograph taken 27/5/09 High Street re-opened on 22 nd May 2009. Road construction is temporary and will therefore be closed once again following construction works at Salem Street. Photograph taken 27/5/09
South Portal Excavations ongoing at CFA Section Looking north along access point Looking south Photograph taken 27/5/09 Photograph taken 27/5/09
South Junction Aerial photograph of south junction taken Mid March 2009 Demolition of existing tunnel entrance retaining wall adjacent to A19 to facilitate construction of Bridge P4 Construction of P4 Bridge ongoing Proposed tunnel closure for 11/12 th July for lifting in of bridge beams for P4 and P6 structures Construction of P6 Bridge ongoing Construction of P7 and P8 retaining walls ongoing Straker Street. Lane temporarily closed mid May for construction of retaining wall
South Junction - P7 and P8 Retaining Wall Construction of block faced reinforced earth structures P7 and P8 adjacent southern loop road Photograph taken 27/5/09
South Junction – P6 Bridge Central pier East Abutment West Abutment Central pier Construction of P6 bridge at southern junction Photographs taken 27/5/09
Recommend
More recommend