NATIONAL GRID STREET LIGHT BUYOUT & LED CONVERSION Town of Lysander 8220 Loop Road Baldwinsville, New York 13027 Estimated Debt Service Calculation Includes The following Costs National Grid Buyout Cost LED Conversion Cost Soft


  1. NATIONAL GRID STREET LIGHT BUYOUT & LED CONVERSION Town of Lysander 8220 Loop Road Baldwinsville, New York 13027

  2. Estimated Debt Service Calculation Includes The following Costs • National Grid Buyout Cost • LED Conversion Cost • Soft Cost for Engineering and Legal Fees • Excludes Potential Energy Efficiency Grant Money From NYSERDA

  3. Projected Tax Rate Calculation Includes The following Costs • Debt Service @ 3.5% for 15 years • Estimated Maintenance Cost @ 5% of LED Conversion Cost Annually • Estimated Annual Energy Cost • Excludes Potential Energy Efficiency Grant Money From NYSERDA

  4. Indian Springs Lighting District • Assessed Value = $39,624,111 • National Grid Buyout Cost = $21,458 • Led Conversion Cost = $17,759 • Soft Cost = $2,382 • Estimated Annual Debt Service Cost = $3,568 • Estimated Annual Energy Cost = $1,078 • Estimated Annual Maintenance Cost = $888 • Estimated 2021 Tax Rate = $0.1397/$1,000 • 2020 Tax Rate = $0.1414/$1000

  5. Whitetail Woods Lighting District • Assessed Value = $12,353,600 • National Grid Buyout Cost = $5,939 • Led Conversion Cost = $5,346 • Soft Cost = $685 • Estimated Annual Debt Service Cost = $1,027 • Estimated Annual Energy Cost = $147 • Estimated Annual Maintenance Cost = $267.32 • Estimated 2021 Tax Rate = $0.1167/$1,000 • 2020 Tax Rate = $0.1540/$1000

  6. Whispering Oaks Lighting District • Assessed Value = $24,275,017 • National Grid Buyout Cost = $477 • Led Conversion Cost = $600 • Soft Cost = $65 • Estimated Annual Debt Service Cost = $98 • Estimated Annual Energy Cost = $68 • Estimated Annual Maintenance Cost = $30 • Estimated 2021 Tax Rate = $0.0081/$1,000 • 2020 Tax Rate = $0.0101/$1000

  7. Collington Point Lighting District • Assessed Value = $31,913,200 • National Grid Buyout Cost = $14,873 • Led Conversion Cost = $34,856 • Soft Cost = $3,020 • Estimated Annual Debt Service Cost = $4,524 • Estimated Annual Energy Cost = $337 • Estimated Annual Maintenance Cost = $1,743 • Estimated 2021 Tax Rate = $0.2069/$1,000 • 2020 Tax Rate = $0.1536/$1000 • Rate Increase Reflects New Lights In Tallamore

  8. Seneca Estates Lighting District • Assessed Value = $32,394,383 • National Grid Buyout Cost = $3,298 • Led Conversion Cost = $1,593 • Soft Cost = $297 • Estimated Annual Debt Service Cost = $445 • Estimated Annual Energy Cost = $88 • Estimated Annual Maintenance Cost = $80 • Estimated 2021 Tax Rate = $0.0189/$1,000 • 2020 Tax Rate = $0.0210/$1000

  9. Melia Park Lighting District • Assessed Value = $20,623,857 • National Grid Buyout Cost = $4,822 • Led Conversion Cost = $1,519 • Soft Cost = $385 • Estimated Annual Debt Service Cost = $576 • Estimated Annual Energy Cost = $33 • Estimated Annual Maintenance Cost = $76 • Estimated 2021 Tax Rate = $0.0333/$1,000 • 2020 Tax Rate = $0.0271/$1000 • Cost Increase Due to High National Grid Buy Out Cost

  10. Clinton Heights Lighting District • Assessed Value = $112,242,220 • National Grid Buyout Cost = $123,792 • Led Conversion Cost = $105,496 • Soft Cost = $13,926 • Estimated Annual Debt Service Cost = $20,861 • Estimated Annual Energy Cost = $2,740 • Estimated Annual Maintenance Cost = $5,275 • Estimated 2021 Tax Rate = $0.2573/$1,000 • 2020 Tax Rate = $0.3635/$1000

  11. Lysander Lighting District • Assessed Value = $7,021,419 • National Grid Buyout Cost = $10,491 • Led Conversion Cost = $8,682 • Soft Cost = $1,165 • Estimated Annual Debt Service Cost = $1,744 • Estimated Annual Energy Cost = $527 • Estimated Annual Maintenance Cost = $434 • Estimated 2021 Tax Rate = $0.3853/$1,000 • 2020 Tax Rate = $0.4344/$1000

  12. Radisson Lighting District • Assessed Value = $615,589,452 • National Grid Buyout Cost = $681,703 • Led Conversion Cost = $316,543 • Soft Cost = $60,631 • Estimated Annual Debt Service Cost = $90,820 • Estimated Annual Energy Cost = $11,075 • Estimated Annual Maintenance Cost = $15,827 • Estimated 2021 Tax Rate = $0.1912/$1,000 • 2020 Tax Rate = $0.3414/$1000 • Tax Rate Decrease With The Addition of 16 New Lights

  13. Fairways North Lighting District • Assessed Value = $35,794,314 • National Grid Buyout Cost = $954 • Led Conversion Cost = $879 • Soft Cost = $111 • Estimated Annual Debt Service Cost = $167 • Estimated Annual Energy Cost = $95 • Estimated Annual Maintenance Cost = $44 • Estimated 2021 Tax Rate = $0.0085/$1,000 • 2020 Tax Rate = $0.0188/$1000

  14. Valley View Lighting District • Assessed Value = $18,798,469 • National Grid Buyout Cost = $17,847 • Led Conversion Cost = $14,058 • Soft Cost = $1,938 • Estimated Annual Debt Service Cost = $2,903 • Estimated Annual Energy Cost = $706 • Estimated Annual Maintenance Cost = $703 • Estimated 2021 Tax Rate = $0.2294/$1,000 • 2020 Tax Rate = $0.2474/$1000

  15. West Phoenix Lighting District • Assessed Value = $6,921,919 • National Grid Buyout Cost = $10,491 • Led Conversion Cost = $8,682 • Soft Cost = $1,165 • Estimated Annual Debt Service Cost = $1,744 • Estimated Annual Energy Cost = $527 • Estimated Annual Maintenance Cost = $434 • Estimated 2021 Tax Rate = $0.3909/$1,000 • 2020 Tax Rate = $0.3747/$1000 • Cost Increase Due to High National Grid Buyout Cost

  16. Morgan Riverside Lighting District • Assessed Value = $6,463,049 • National Grid Buyout Cost = $7,153 • Led Conversion Cost = $5,920 • Soft Cost = $794 • Estimated Annual Debt Service Cost = $1,189 • Estimated Annual Energy Cost = $359 • Estimated Annual Maintenance Cost = $296 • Estimated 2021 Tax Rate = $0.2854/$1,000 • 2020 Tax Rate = $0.2708/$1000 • Cost Increase Due to High National Grid Buyout Cost

  17. Plainville Lighting District • Assessed Value = $5,335,402 • National Grid Buyout Cost = $8,106 • Led Conversion Cost = $6,708 • Soft Cost = $900 • Estimated Annual Debt Service Cost = $1,348 • Estimated Annual Energy Cost = $407 • Estimated Annual Maintenance Cost = $335 • Estimated 2021 Tax Rate = $0.3918/$1,000 • 2020 Tax Rate = $0.3468/$1000 • Cost Increase Due to High National Grid Buyout Cost

  18. Barbara Lane Lighting District • Assessed Value = $2,716,418 • National Grid Buyout Cost = $3,338 • Led Conversion Cost = $2,762 • Soft Cost = $371 • Estimated Annual Debt Service Cost = $555 • Estimated Annual Energy Cost = $168 • Estimated Annual Maintenance Cost = $138 • Estimated 2021 Tax Rate = $0.3169/$1,000 • 2020 Tax Rate = $0.2946/$1000 • Cost Increase Due to High National Grid Buyout Cost

  19. Timber Banks Lighting District • Assessed Value = $36,352,380 • National Grid Buyout Cost = $47,399 • Led Conversion Cost = $88,294 • Soft Cost = $8,238 • Estimated Annual Debt Service Cost = $12,340 • Estimated Annual Energy Cost = $442 • Estimated Annual Maintenance Cost = $4,415 • Estimated 2021 Tax Rate = $0.4731/$1,000 • 2020 Tax Rate = $0.1503/$1000 • Cost Increase Due to New Lights

  20. Town Lights Lighting District • Assessed Value = $0 • National Grid Buyout Cost = $15,682 • Led Conversion Cost = $3,288 • Soft Cost = $1,152 • Estimated Annual Debt Service Cost = $1,726 • Estimated Annual Energy Cost = $342 • Estimated Annual Maintenance Cost = $164

  21. Highland Meadows Lighting District • Assessed Value = $15,173,685 • National Grid Buyout Cost = $0 • Led Conversion Cost = $48,419 • Soft Cost = $2,941 • Estimated Annual Debt Service Cost = $4,405 • Estimated Annual Energy Cost = $166 • Estimated Annual Maintenance Cost = $300 • Estimated 2021 Tax Rate = $0.3210/$1,000 • Includes 9 New Post Top Lights

  22. Springwoods Lighting District • Assessed Value = $2,853,800 • National Grid Buyout Cost = $0 • Led Conversion Cost = $10,760 • Soft Cost = $654 • Estimated Annual Debt Service Cost = $979 • Estimated Annual Energy Cost = $37 • Estimated Annual Maintenance Cost = $300 • Estimated 2021 Tax Rate = $0.4611/$1,000 • Includes 2 New Post Top Lights