MINISTRY OF INFRASTRUCTURE OF UKRAINE TRANSPORT INFRASTRUCTURE INVESTMENT OPPORTUNITIES CONCESSION: COMPLETION AND OPERATION OF BORYSPIL AIRPORT CAR PARKING PROJECT CAR PARKING FACILITY Balanced growth in imports and exports Exports 58% growth over 5 years Imports 42% growth over 5 years 24.11.2015 Ukraine Ministry of Infrastruture 1
PROJECT DESCRIPTION GENERAL BORYSPIL INFORMATION PARKING The area of the land plot 30 000 sq.m. Percent project completed 50% The area of the construction 18 398,0 sq.m. Investment estimated to complete the garage $10,8mln. Total area 72 615,1 sq.m. Return on investments 6 years (apx.) Number of parking spots 2 038 Dynamics of passengers flow in Boryspil Total estimated value $22,5mln. airport 2008-15, mln. Passengers; Current passenger activity has been impacted by the war. Airport forecasts a recovery to previous passenger levels within the next 2 years. 9000 8000 7000 6000 5000 4000 3000 2000 1000 0 2008 2009 2010 2011 2012 2013 2014 2015 9 24.11.2015 Ukraine Ministry of Infrastruture 2 month
CURRENT SITUATION At the moment the car parking structure is 50% completed. All legal hurdles to permit completion of the garage are . Today there are 4 surface car parking lots in the Boryspil airport: Parking Number of parking Price (UAH) Cars per day $/UAH=23 (calculated spaces 29/01/2015) B1 610 day -50, hour -20 84 B2 200. day -60, hour -10 153 D2 184 hour-30 958 D3 ( future bus station) 195 hour -20 699 24.11.2015 Ukraine Ministry of Infrastruture 3
TECHNICAL PLAN 1 floor 2,3 floor roof 24.11.2015 Ukraine Ministry of Infrastruture 4
TECHNICAL PLAN 24.11.2015 Ukraine Ministry of Infrastruture 5
Opportunity for an Investment Banking Firm to lead the tender for completion and operation of the car parking garage at Boryspil International Airport A tender for Investment Banker to be issued in December 2015 Investment Banking tender awarded on two criteria: 1. Quality of Proposal 2. Fee Proposed 24.11.2015 Ukraine Ministry of Infrastruture 6
Requirements of Investment Banker • To develop a Feasibility Study of car parking garage • To develop a list of potential bidders • To assist in the development of the tender for car parking garage with MIU and KBP • To marketing the tender – Investment memo • To make a recommendation to award bid 24.11.2015 Ukraine Ministry of Infrastruture 7
Requirements of KBP and MIU • Engineering Reports of current status of Car Parking Garage – KBP is preparing the engineering analysis • Including potential rusted steel recovery • Provide full engineering drawings of garage • Historical records – Car parking activity – Aviation activity • Passenger Activity forecast • Conduct the tender for Investment Banker cooperatively with MIU and Investment Banker • Award the tender for the completion and operation of the car parking garage 24.11.2015 Ukraine Ministry of Infrastruture 8
Requirements of Tender • Tender to provide information necessary to bid on the car parking garage project – Engineering studies, feasibility study, etc. – Timing requirements • Request information on how the construction will be completed and how the operations of the car parking garage be conducted. for example: – Ideas to increase usage of garage – Proposed payment to airport* • Request proposals for alternate operations. For example: – Phased completion of garage – Alternate uses of garage 24.11.2015 Ukraine Ministry of Infrastruture 9
Contract Award • Investment Banker to recommend criteria to award contract – Conditions of award • *Joint Activity payment to airport • Length of time of contract for joint activity • Ability to award contract based on alternative presented by bidders – Regulatory responsibilities • Investment Banker’s compensation will be included in the award 24.11.2015 Ukraine Ministry of Infrastruture 10
Timeline • Announcement of Tender – October 2015 • Teaser released – November 2015 • Bidder’s conference for Investment Bankers – Today! • Tender for selection of Investment Banking Firm – late December 2015 • Construction lease expires - December 31, 2015 (access to car parking garage obtained) • Investment Banking Firm selected - January 2016 • Tender for Garage Project completed - March 2016 • Approval of Cabinet of Minister - March 2016 • Tender issued - April 2016 • Tender awarded - June 2016 24.11.2015 Ukraine Ministry of Infrastruture 11
Questions? 24.11.2015 Ukraine Ministry of Infrastruture 12
CONTACT INFORMATION Aleksandra Klitina Advisor to the Deputy Minister Ministry of Infrastructure of Ukraine E-mail: aklitina@mtu.gov.ua aklitina@gmail.com Tel. : +38 099 760 15 78 Engineering specifications and current condition reports will be available to prospective bidders 24.11.2015 Ukraine Ministry of Infrastruture 13