Bulge Construction Update Meeting Wednesday 15 th June 2016
Agenda • Welcome and Introductions • Questions so far? Where are the answers? • ARJ Construction • Questions
Overview of f Bulge Cla lass Accommodation Project • To accommodate up to three bulge classes from starting in September 2016, then 2017 and 2018. Final class would leave in Summer 2025 • Upgrade / remodel school to sustain delivery of 2 form entry (with three bulge classes). • Building – relocation of nursery to Early Years block. • Demolition of Care takers house • Construction of new hall, three classrooms and kitchen • Remodelling of administrations spaces (reception, school business manager, site manager and head’s officer), SENCO and meeting rooms, breakfast club and food technology spaces.
Answers to Questions • Bulge Class page on school website – see http://www.st- marks.ealing.sch.uk/calender- news/bulge-class-information- updates/ • Answers to questions from parents. • Phase and detailed drawings • FAQs with 49 responses from Ealing Council
Questions?