Kopeopeo Canal Remediation Project Community Liaison Group Meeting 23 January 2018 1
Meeting agenda topics • Welcome & introduction – John Pullar • Approval of minutes from previous meeting • Communications update – Abby Tozer • Project update – Ken Tarboton • Independent Monitor – Matt James • Health, Safety and Monitoring – Des McLeary • Other business • Light lunch 2
Communications • Newsletters • Media coverage • Website www.boprc.govt.nz/kopeopeo • Community notices on 1XX • Public notices • Flood Managers briefing & site visit • CLG Chair site visit 3
Project update Overview • Progress made over last period • CS1 • Flood management (& control structures) • Enabling works • Eel removal • Activities planned for next period 4
Overview of Progress (22 Nov 2017 – 22 Jan 2018) Containment Site 1 complete, geobags ready for sediment Water treatment plant complete, tested and commissioned Truxor dredging completed for control structures Flood Control structures close to complete Turbidity & level monitoring in place Enabling flood mitigation works complete Eel removal complete Main dredging started (22 January 2018) CS3 design underway 5
Containment Site 1 – CS1 6
CS1 7
CS1 Aerial view – 4 December 2017 Bullseye Productions Youtube https://youtu.be/bmtDdLJL2EU 8
Water Treatment Area (WTA) 9
Water Treatment Area 10
Water Treatment Area 11
Truxor Dredging 12
Flood Control Structures 13
FCS-East (1 st attempt) 14
Control Structure re-design FCS- West (SH30) 15
FCS- West at SH30 16
FCS-East at Confluence 17
Confluence East at FCS 18
Flood Control Enabling Works Reverse Flow Prevention Blanket Inflatable Plugs 19
Enabling Works: Kope Control Gate Culverts 20
Enabling Works: Kopeopeo Canal East Stopbank Topup 21
Eel Removal 22
Bone find – discovery protocol 23
Access- CS3 & Kope Canal Rd 24
Vandalism 25
Dredging Pre-dredging testing Canal water over shakers Polymer (flocculant) mixing and calibration 26
Dredging 22 January 2018 27
28
29
Flocculent testing 30
Dredging Control 31
Project Schedule Activities proposed through end February • Progress dredging with 2 lifts before Paroa Rd bridge • Complete CS3 design • Establish site at CS3 • Undertake preliminary works at CS3 32
Independent Monitor update • Control structures • Truxor dredging • Stop bank upgrades • Eel removal • CS3 test pits • Stump removal • Turbidity monitoring • CS1 HDPE liner installed • Police emergency • Flood Managers tour • Water/Sediment treatment plant • Dust suppression/monitoring 33
Independent Monitor update • Emergency Response • NZPGS helping emergency services • Dust Complaint Friday 12 th January • • Kope Canal Road • Other traffic within project area • Dust monitoring https://whakatanebeacon.co.nz/2017/12/police-officer-hit-by-fleeing- driver/. Sourced 20/12/2017. • Turbidity Monitoring • Issues during set up • Exceedances • On-going monitoring 34
Turbidity Monitoring 35
Health, Safety & Monitoring H EALTH & S AFETY I tem No# Comment - Actions - Outcome 178 To date Inductions 0 Safety Contacts Near Hits 0 First Aid 0 Medical Treatment 0 Injury Lost Time 0 General Several H&S audits undertaken 36
Contamination precautions • CS1 – hot, warm, cold areas • PPE • Wash down & decontamination procedures 37
Traffic Management • Managed at CS1 • 30km limit on Kope Drain Rd when truck movements • At CS3 38
Environmental Monitoring • Turbidity at 10 locations • Water levels at 4 locations (within site) • Dust monitoring at CS1 and Kope Pump station • Mobile dust monitor for CS3 construction • Dioxin air quality (14 day) tests(3) during early stages of dredging 39
Other Business • Next meeting: Tuesday 6 th March 40