UNIVERS ITY OF M AS S ACHUS ETTS AM HERS T Faculty Senate – Construction Project Impacts to Campus January 29, 2015
FY15 to FY19 Capital Activity In Construction and Design Project Funding Status Project Cost Current John F . Kennedy Champions Center Debt Construction $29,900,000 Furcolo Renovation Debt/UMA Construction $22,500,000 South College Academic Facility Debt Construction $65,000,000 Tillson Electrical Substation Debt Construction $40,000,000 LSL Mass Life Sciences Fit-out & Equip State Construction $95,000,000 Wilder Hardscape and Landscape UMA Construction $400,000 Future Central Chilled Water Plants Debt Design $30,000,000 Design Building Debt/State Design $53,000,000 Physical Sciences Building State/Debt Design $101,800,000 Old Chapel Renovation Debt Design $21,000,000 Robsham Solar PV Parking Canopies UMA/Grants Design $1,700,000 TOTAL $462,300,000
Current Major Projects • John Francis Kennedy Champions Center
John Francis Kennedy Champions Center • $29.9M – Debt/Gifts • GSF 53,000 • Under construction; to be completed July, 2015. • Comm. Ave. stairs and crossing construction - Spring, 2015 • Features: o 2 full basketball courts o Locker rooms o Direct connection to Mullins Center o Hydrotherapy and sports medicine o Strength training o Coaches offices o Legacy hall
John Francis Kennedy Champions Center – Impacts
John Francis Kennedy Champions Center – Impacts
John Francis Kennedy Champions Center View from the southeast
John Francis Kennedy Champions Center Interior - courts
John Francis Kennedy Champions Center
John Francis Kennedy Champions Center
Current Major Projects • John Francis Kennedy Champions Center • Furcolo Renovation
Furcolo Renovation • $22.5M – Debt/UMA • 100,100GSF • In construction; scheduled for occupancy Spring, 2016. • Selective demolition, abatement, and construction is underway. • Upgraded and expanded home for the College of Education. • Allows for relocation of staff and eventual demolition of Hills House.
Furcolo Renovation – Impacts
Furcolo Renovation – Impacts
Furcolo Renovation Classroom
Furcolo Renovation North Portal
Current Major Projects • John Francis Kennedy Champions Center • Furcolo Renovation • South College Academic Facility
South College Academic Facility • $65M – Debt • 97,500GSF total • Associated steam line work substantially complete • Building construction began in January with selective interior demolition • Scheduled opening for spring semester, 2017 • Home of the College of Humanities & Fine Arts • Enables demolition of Bartlett Hall
South College Academic Facility – Utilities
South College Academic Facility – Impacts
South College Academic Facility – Impacts
South College Academic Facility – Impacts
South College Academic Facility – Impacts
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
South College Academic Facility
Current Major Projects • John Francis Kennedy Champions Center • Furcolo Renovation • South College Academic Facility • Tillson Substation
Tillson Substation • $40M – Debt • In construction; completion Fall, 2015 • Tie to regional 115KV transmission lines • Annual transmission line savings of $1M • Expands electrical capacity and system reliability • Supports expansion of on-campus sustainable electrical generation
Tillson Substation – Impacts • Duct bank installation underway • Crossing East Pleasant Street scheduled for mid-April to early May
Current Major Projects • JFK Champions Center • Furcolo Renovation • South College Academic Facility • Tillson Substation • LSL Mass Life Sciences Fit-out
LSL Mass Life Sciences Fit-out • $33.2M – State • In construction; occupancy scheduled for Spring, 2016 • 3.5 floors; 60,500 GSF • Creates the Institute for Applied Life Sciences (IALS) at UMass • Home to: Center for Bioactive Delivery, Models to Medicine Center, Center for Personalized Health Monitoring • Core research facilities used by one or more centers and their off campus partners in industry and academia
LSL Mass Life Sciences Fit-out – Impacts
Current Major Projects • JFK Champions Center • Furcolo Renovation • South College Academic Facility • Tillson Substation • LSL Mass Life Sciences Fit-out • Wilder Hardscape and Landscape
Wilder Hardscape and Landscape • $400K – UMA • Much of the project substantially complete; construction resumes in April; to be completed in May • Includes 144’ stone wall o Extensive sub-drainage o system Rebuilt manholes o Granite stairway o Clay and asphalt pavers o Sustainable landscaping o Creates accessible pathways o
Wilder Hardscape and Landscape – Impacts
Future Projects • Chilled Water Plant Expansion & Upgrades
Chilled Water Plant Expansion & Upgrades • $30M – Debt • Construction scheduled for Fall, 2015 through Spring, 2017 (prior to PSB completion) • Expands chilled water capacity • Reduces chiller DM
Chilled Water Plant Expansion & Upgrades – Impacts
Future Projects • Chilled Water Plant Expansion & Upgrades • Design Building
Design Building • $50M – Debt, $3M – State • 80,000GSF • Scheduled construction: Spring 2015 – Fall 2016; occupancy January, 2017. • Programs for Landscape Architecture and Regional Planning, Architecture + Design, Building Construction Technology. • Wood structure • Enables demolition of Hills House. • Requires a loss of parking spaces in Lot 62. Parking lot completed on the former French Greenhouse site.
Design Building – Impacts • Early site prep: April, 2015 • Construction: June, 2015 • Coordinating with Parking Services to minimize impact to Lots 62 and 63
Design Building View from North Pleasant St.
Design Building View from North Pleasant St.
Design Building Atrium
Design Building Commons
Future Projects • Chilled Water Plant Expansion & Upgrades • Design Building • Physical Sciences Building
Physical Sciences Building • 94,000GSF • In design; scheduled to start construction in spring 2015 for completion in early 2018 • Organic Chemistry (out of Lederle high rise) • Physics, including High Bay Labs. Moves faculty out of Hasbrouck • Improved loading dock to serve PSB, Lederle, & Goessmann • Move and renovate West Experiment Station
Physical Sciences Building – Impacts
Physical Sciences Building – Impacts
Physical Sciences Building – Impacts
Physical Sciences Building View from the east
Physical Sciences Building Aerial view from the southeast
Physical Sciences Building
Physical Sciences Building
Future Projects • Chilled Water Plant Expansion & Upgrades • Design Building • Physical Sciences Building • Old Chapel Renovation
Old Chapel Renovation • $21M – Debt/Gifts • 21,000GSF • In design; construction scheduled for Spring, 2015 – October, 2016 • Built in 1885 – iconic core campus structure • Planned multi-purpose use, exhibit space, function rooms, offices and gathering space
Old Chapel Renovation – Impacts
Old Chapel Renovation
Old Chapel Renovation
Old Chapel Renovation
Old Chapel Renovation
Future Projects • Chilled Water Plant Expansion & Upgrades • Design Building • Physical Sciences Building • Old Chapel Renovation • Robsham Solar PV Parking Canopies
Robsham Solar PV Parking Canopies • $1.7M – UMA/Grants • Construction scheduled to begin in late summer through December • Annual savings: approx. $169,000/yr • 7-10 year payback • Solar PV Parking Canopy in Parking Lot 34 will provide 300 kW (DC) ~250kW (AC) of electricity • Will contribute to campus electrical grid, electric vehicle charging stations
Robsham Solar PV Parking Canopies – Impacts • Vehicle access to back lane of the parking (adjacent to Lincoln Apartments) to be maintained • Temporary parking will be available in Lot 34
Physical Plant Projects • Paving Mass. Ave. between Comm. Ave. and Welcome sign – March/April • Paving Infirmary Way from UHS to Clark Hill – June/August • New sidewalk on N. Pleasant St. from ILC to FAC – Summer