industry briefing 29 november 2016 agenda
play

Industry Briefing | 29 November 2016 Agenda Project Overview - PowerPoint PPT Presentation

Industry Briefing | 29 November 2016 Agenda Project Overview Target Programme Designation and resource consent conditions Ground investigations Mana Whenua Design Status Tunnels Stations


  1. Industry Briefing | 29 November 2016

  2. Agenda • Project Overview • Target Programme • Designation and resource consent conditions • Ground investigations • Mana Whenua • Design Status • Tunnels • Stations • Sustainability • Design Management and Interfaces • Questions - followed by afternoon tea

  3. Planned Outcomes A safe reliable and attractive railway • 24 trains per hour in each direction ultimate track capacity • 18,000 passengers per hour in each direction as the ultimate patronage capacity through two new stations and two modified stations • Future proofing oversite development opportunities at each station • Sustainability IS project target rating 'excellent' • Operating in 2023/24

  4. Route Context

  5. Climbing the Hill

  6. Designation Boundaries

  7. Contract Split

  8. C3/C7 Interface • Trackwork • Signalling • Overhead line • Communications • Fire engineering • Tunnel ventilation • Controls • Integration • Testing • Commissioning

  9. Procurement Programme

  10. Target Construction Programme • C1,C2, DSC complete in 2019 • C3 2019-2023/24 • C5 2019-2022 • C6 2018-2019 • C7 2019-2023/24 • C8 TBA • C9 2023/24

  11. Designation and Resource Consent Conditions • Surface and subsurface designations • 3 resource consent packages • Noise and vibration • Traffic impacts • Business disruption • Settlement impacts

  12. Ground Investigations • Approx. 130 BHs and CPTs carried out (excluding non-CRL BHs) • Extensive network of groundwater monitoring installations and core sample storage • Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR) will be available to tenderers

  13. Geotechnical Longsection

  14. Mt Eden Geology

  15. Utilities Investigations • Utility surveys undertaken in Albert Street and Beresford Square • Further utility potholing to be carried out in open cut sections Anticipated completion end of 1 st quarter 2017 • • Potential early utilities diversions and/or removal of canopies

  16. CRL's Mana Whenua forum The eight Mana Whenua who self-identified their interest in CRL, and who are part of the forum : • Ngāi Tai Ki Tāmaki • Ngāti Maru • Ngāti Paoa • Ngāti Tamaoho • Ngāti Te Ata Waiohua • Ngāti Whātua o Ōrākei • Te Ᾱkitai Waiohua • Te Kawerau a Maki

  17. Cultural Narratives Illustration Aotea station - indicative expression of narratives

  18. Mandated Design

  19. STEPS Modelling

  20. Design Document Structure

  21. BIM Model

  22. Tunnels Bored Tunnels Mined Tunnels Cut and Cover Tunnels

  23. Tunnels & Alignment

  24. Tunnels & Alignment - Aotea to Karangahape

  25. Tunnels & Alignment Newton Junction N

  26. Tunnels & Alignment - East Connection

  27. Tunnels & Alignment - West Connection

  28. C1 and C2 N

  29. C9 Britomart East • Modification of existing platforms, tracks and signals • Addition and alteration works of operation support entities i.e. offices, gates, stairs etc

  30. Stations - Aotea N

  31. Aotea Station - Existing Structures Crown Plaza Deck Bluestone Wall Public Trust Building Verandahs

  32. Aotea Station - Utilities & Stormwater Diversion • Albert Street stormwater pipe jack • Orakei Main Sewer • Existing subsurface utilities to be diverted/protected

  33. Aotea Station - Connection to Structure • Connect to C2 cut and cover tunnel south of Wyndham Street • C2 expected completion 3 rd quarter 2019 • Potential future integration with NDG’s development at Albert Street/Victoria Street junction • Potential future connection to SkyCity

  34. Aotea Station Construction Site - Bledisloe Carpark • Available as site support area during construction • Carpark side entrance along Wellesley to be maintained

  35. Aotea Station Geology

  36. Aotea Station - Plan (North)

  37. Aotea Station - Plan (Middle)

  38. Aotea Station - Plan (South)

  39. Aotea Station - Typical Section (North)

  40. Aotea Station - Typical Section (South)

  41. Aotea Station

  42. Architecture

  43. Stations - Aotea

  44. Aotea Station - Future Oversite Development • Feasibility and space proofing carried out • Resource Consent granted • Structural enabling works within station structure

  45. Virtual Station Tour

  46. Karangahape Station Location Plan N

  47. Karangahape Station - General Arrangement

  48. Karangahape Station - Construction Support Area • Beresford Square • Current carpark area

  49. Karangahape Station - Construction Support Area • Mercury Plaza site • Available as construction support area • Building possibly demolished as advanced work

  50. Karangahape Station - Geology

  51. Karangahape Station - Existing Structures Methodist Church (Former) George Courts Building N Mercury Theatre Beresford Square

  52. Existing Structures - Verandahs • Existing verandahs may obstruct construction of station • Potentially advanced work • Verandahs to be removed and reinstated/ replaced

  53. Stations - Karangahape

  54. Stations - Karangahape

  55. Stations - Karangahape

  56. Stations - Karangahape

  57. Mt Eden Plan

  58. Structures - Cross Over Shaft

  59. C6 Mt Eden Stormwater Diversion • Diversion of 1950mm SW pipe • 3 shaft locations • Approximately 450m length • Pipe jack launch at Mt Eden Rd shaft • Tunnelling largely below basalt layer

  60. Structures - Station Box N

  61. Construction Sites Mt Eden

  62. Geology

  63. Stations - Mt Eden

  64. Pedestrian Bridges - Western Line

  65. Perspective of Normanby Road

  66. Western Line • Western Line Metro and freight services maintained • Limited full blocks of line • Staged testing and commissioning • Civil, structural, trackwork, railway systems scope

  67. Delivering CRL Sustainably • Decision making that considers social, environmental and cultural impacts, risks and opportunities • Truly integrated design • Understanding and considering whole of life costs • Collaboration around interfaces

  68. Focus areas • Reducing resource consumption - measuring CRL’s carbon footprint - energy, water, materials • Zero waste to landfill - aspirational goal - designing out waste - avoiding construction waste • Social outcomes - workforce development, employment, social enterprises • Mana Whenua outcomes - kaitiakitanga • Reporting - qualitative and quantitative

  69. Carbon footprint Comparing three options for constructing 200m long, 7-9m deep platform trench

  70. Infrastructure Sustainably Infrastructure Sustainability Council of Australia • 'Excellent' Design and As-built rating for whole project • Each contract package will be contributing their own rating - C1, C2, C3, C5, C7 and C9 - (not C6 and C8) • New Zealand pilot - CRL version: - NZ criteria - incorporates Mana Whenua cultural values

  71. Kaitiakitanga, Sustainability & CRL Kaitiakitanga includes: • protecting, restoring, enhancing the mauri of te Ao Māori; • fulfilling spiritual, emotional and inherited responsibilities to the environment; • maintaining mana over te taiao; and • ensuring the welfare of the people. In Tamaki Makaurau it is Mana Whenua who are Kaitiaki. In meeting their sustainability commitments the CRL project is supporting kaitiakitanga and Mana Whenua as kaitiaki.

  72. Social Outcomes for Auckland • There are eight local boards with higher than average numbers of people Not in Employment Education or Training (NEET) • There is a significant skills shortage in construction and infrastructure • Creating positive social value through the delivery of CRL

  73. Journey so far Contracts 1 & 2

  74. Infrastructure Sustainably Work undertaken: • Materiality assessment for the scope of each contract package • Reference design level footprints - for operations only • Principal’s evidence

  75. Design Management Process • Particular requirements • Planning conditions • Mandated design elements • Interface management and control • DOORS Database • Multi-discipline Gateway Reviews • Systems Assurance

  76. Gateway Reviews • Progressive information co-ordination and delivery - Intermediate gate in interactive pre-award period - Gates through detailed design - Final gate at completion of detail design • On line real time demonstration of the co-ordinated information delivery and compliance with requirements

  77. Interfaces • Interface boundary mapping and ownership- DOORS - C3-C6, C3-C2, C3-C7, C3-C5, C3-C9 - C7-C1, C7-C2, C7-C3, C7-C5, C7-C9 • Interface control documents - Geographical co-ordination - Cross boundary co-ordination • Collaborative development - cross contract resolution • Collective responsibility

Recommend


More recommend