I-35E Phase 2 Project Texas Transportation Commission I-35E Phase 2 Project April 30, 2020 April 30, 2020
Minute Order authorization Sum ummary o y of Commission A n Acti tion: Authorize TxDOT to issue a request for qualifications (RFQ) to design, construct and potentially maintain the I-35E Phase 2 Project in the Dallas District from I-635 to the Denton County Line. I-35E Phase 2 Project April 30, 2020 2
Purpose Top 100 ranking: Direct - 60 Indirect – 15, 57 Project limits: I-635 to the Denton County line Project purpose: – Improve safety and mobility – Relieve congestion – Reduce travel time – Accommodate projected growth through the region I-35E Phase 2 Project April 30, 2020 3
Overview Texas Clear Lanes Project Total length: 6.39 miles PRESENT CONDITION Project Scope: – Reconstruct and widen general purpose lanes from 6 to 8 lanes – Reconstruct “grandfathered” existing 2 reversible tolled managed lanes (no PROPOSED CONSTRUCTION increase in capacity) – Reconstruct continuous frontage roads – Numerous intersection improvements Design-build cost estimate: $600M Added capacity shown with purple arrows I-35E Phase 2 Project April 30, 2020 4
Alternative delivery support tool Decision support tool – Used to determine best delivery method: • Design-bid-build • Design-build – Tool considers TxDOT’s goals and specific project characteristics. Results – Tool indicates design-build as most appropriate delivery method with a score of 0.48 (scale of -1.00 to 1.00). I-35E Phase 2 Project April 30, 2020 5
Design-build anticipated timeline Milestone Date Commission action to issue RFQ April 30, 2020 Issue RFQ May 2020 Qualification statements due June 2020 Commission action to issue RFP Summer 2020 Issue final RFP Fall 2020 Proposals due Spring 2021 Commission action for conditional award Spring 2021 Contract execution Summer 2021 Construction completion Late 2025/Early 2026 I-35E Phase 2 Project April 30, 2020 6