hello neighbors
play

HELLO NEIGHBORS! Thank you for taking the time to learn more about - PowerPoint PPT Presentation

HELLO NEIGHBORS! Thank you for taking the time to learn more about the Collister Dr. Maintenance & Pedestrian Project between W. Quail Ridge Dr. and the cul-de-sac. The purpose of this information is to give you an opportunity to: LEARN


  1. HELLO NEIGHBORS! Thank you for taking the time to learn more about the Collister Dr. Maintenance & Pedestrian Project between W. Quail Ridge Dr. and the cul-de-sac. The purpose of this information is to give you an opportunity to: LEARN about upcoming work on Collister Dr. between W. Quail Ridge Dr. and the cul-de-sac. TELL US what you think. CONSTRUCTION CURRENTLY PLANNED FOR 2022 COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  2. Untitled map PROJECT PURPOSE PROJECT AREA Improve the roadway surface Update pedestrian facilities to current standards COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  3. PROJECT DESCRIPTION Remove existing, deteriorating concrete roadway and replace with asphalt . Replace the existing curb, gutter and four-foot sidewalk on the east side of the street with rolled curb and a five-foot sidewalk , matching the existing back of sidewalk. This is a Federal Aid Project. EXAMPLE OF ROLLED CURB COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  4. MINIMAL IMPACTS The intent is to have The intent is to have minimal impacts minimal impacts to private to private property; therefore, the new sidewalk will match the back property; therefore, the new sidewalk will match the back 4 FEET of the existing sidewalk. of the existing sidewalk. EXISTING SIDEWALK However, some temporary easements will still be needed However, some temporary easements will still be needed during construction. during construction. 5 FEET FUTURE SIDEWALK COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  5. WHAT IS A TEMPORARY EASEMENT? Temporary easements will allow for a working area and access as required for any driveway repairs, sprinkler/ sod/landscape repairs, or other minor repair work that may be required on private property for the installation of the new sidewalk. COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  6. WHY DOES THE ROADWAY SURFACE NEED TO BE REPLACED? The existing concrete surface is very deteriorated and COLLISTER in poor condition . ACHD uses a Pavement Condition Index score to rate Very Poor Poor Good Very Good its roadways from 0 (very poor) – 100 (very good) . The concrete on this portion of Collister Drive is rated 24, very poor , indicating a new roadway surface is necessary. COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  7. PROJECT CONSIDERATIONS Accessible Pavement sidewalks and condition pedestrian ramps Safety for Property pedestrians, impacts bicyclists and motorists COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  8. PROJECT TIMELINE SUMMER FALL SPRING SUMMER 2020 2020 2021 2022 Begin Public Final design submittal & Construction Design Outreach purchase temporary construction easements WE ARE HERE COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

  9. THANK YOU! Thank you for taking the time to review the information about the Collister Drive Maintenance and Pedestrian Project. The next step is to review the design slides and then tell us what you think. Design Survey While your comments are always welcome, they can be best used if received by October 19, 2020 . After the comment period closes, ACHD will review and address comments received from the public. COLLISTER DRIVE MAINTENANCE & PEDESTRIAN PROJECT OCTOBER 2020 • ADA COUNTY HIGHWAY DISTRICT

Recommend


More recommend