h667 priority trunk mains rehabilitation phase 1 option 2
play

H667 Priority Trunk Mains Rehabilitation PHASE 1 - PowerPoint PPT Presentation

H667 Priority Trunk Mains Rehabilitation PHASE 1 (Option 2) Proposed Start Date 18 th March 30 th April 2019 Notes: 1, Bus lane closure is subject to TTRO. Currently waiting to speak to Rachael Goddard to Graeme


  1. H667 Priority Trunk Mains Rehabilitation – PHASE 1 (Option 2) Proposed Start Date 18 th March – 30 th April 2019 Notes: 1, Bus lane closure is subject to TTRO. Currently waiting to speak to Rachael Goddard to Graeme Oddy – Senior Traffic Manager confirm date for start on 20 th March. Alternative start date 6 th April. Mo Arshid – Site Manager 2, UTC to be consulted regarding the traffic signal operation on the junction Aghogho Amelia Asagba – Customer & of Christchurch/Norwood Stakeholder Co-ordinator Road. 3, Cycle Diversion around gyratory. 1

  2. Your Team on Norwood Road (The dream Team) Mo Arshid Site Graeme Oddy Phil Hawley Ian Welch Project Manager Senior Traffic Construction Manager Manager Manager Dan Walsh Dean Freedman Construction Construction Manager Manager 2 (Instalcom) (Instalcom)

  3. 3

  4. 4

  5. 5

  6. 6

  7. Where are we now ? 7

  8. Where are we now ? 8

  9. Phase 2/1 & 1A Challenges (Unchartered Services)  Low pressure 18” Gas Main  Existing 8” Cast iron water main (below Gas)  640mm between Gas & Water pipes  Hand dig around existing services  Redesign of trunk main to go below existing  Existing water pipe burst by Parade Mews 9

  10. Phase 2/1 Pipe Burst 10

  11. Phase 2/1 Pipe Burst 11

  12. Phase 2/1 Pipe Burst 12

  13. Phase 1A Challenges (Unchartered Services) 13

  14. 14

  15. H667 Priority Trunk Mains Rehabilitation – Options 1 & 2 Work Areas 15

  16. 16