fy 09 aes phase i crab cavity sbir progress
play

FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), - PowerPoint PPT Presentation

Advanced Energy Systems, Inc. FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), Rama Calaga (BNL), Zenghai Li (SLAC) Prototype Crab Cavity SBIR Objectives Advanced Energy Systems, Inc. Collaborators are AES, BNL, SLAC, and


  1. Advanced Energy Systems, Inc. FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), Rama Calaga (BNL), Zenghai Li (SLAC)

  2. Prototype Crab Cavity SBIR Objectives Advanced Energy Systems, Inc. • Collaborators are AES, BNL, SLAC, and LBL • Phase 1 – Preliminary Design of Cavity (3 man months supported by SBIR) • Coordinate transfer of Physics Design - Complete • Develop initial mechanical solid model - Complete • Perform Initial Thermal and Structural Analysis – Underway – Principle issue currently is cooling requirement for coaxial beam pipes • Preliminary Mechanical Design and Fabrication Feasibility Study – Largely Complete • Phase 2 – Complete mechanical design with supporting thermal/structural analysis. – Generate complete fabrication drawing package for the Crab Cavity. – Fabricate Prototype Crab Cavity – Perform BCP and HPR on Prototype Crab Cavity at AES if our facilities can accommodate it. We anticipate that we will be able accommodate an 800 MHz elliptical crab cavity. – Support Crab Cavity VTF testing at BNL

  3. Overall Cavity Configuration Advanced Energy Systems, Inc. FPC END GROUP PORTS FOR LOM/HOM-v COUPLER ADJACENT BEAM PIPE, Accounted for but not included Double Walled Beam Pipe Inner Conductors FPC PORT Coaxial Beam Pipes SHORT END GROUP � Most of the cavity will be surrounded by a LHe vessel in the operational design but not in the prototype. � Cooling of the Beam Pipe Inner Conductors could be flood cooled 2K LHe or forced 5K He, this question is currently being addressed. � 5K He adds significant complications for VTA testing

  4. Parted out Welded Assembly Advanced Energy Systems, Inc. � 39 Welding steps joining 32 parts will be required to fabricate each cavity. � In addition there are machining operations between many of the welds.

  5. Welding Sequence A: Inner & Outer Conductor Advanced Energy Systems, Inc. 2 Welding steps required to connect the inner and outer 8 Welding steps conductor required to fabricate the inner conductor 6 Welding steps required to fabricate the outer conductor

  6. Welding Sequence B: End Groups Advanced Energy Systems, Inc. 9 Welding steps required to fabricate FPC side End Group 2 Welding steps required to fabricate short side End Group

  7. Welding Sequence C: Coax BP ICs Advanced Energy Systems, Inc. � 3 Welding steps are required to fabricate each double walled beam pipe inner conductor. � Fabricating the inner conductors in the fashion is actually cheaper than machining them from bar. They are too thick to roll and seam weld.

  8. RF Analysis: Normalization Advanced Energy Systems, Inc. Magnetic Field (HY) Scaled for Transverse voltage of 5MV/cavity 4.0E+04 3.0E+04 Magnetic Field A/m 2.0E+04 1.0E+04 0.0E+00 -1.0E+04 -2.0E+04 -3.0E+04 -4.0E+04 0.0 0.2 0.4 0.6 0.8 1.0 Disatance Along Center of Cavity meters � Magnetic field on Axis used to normalize cavity fields. � Surface Fields will be used to calculate heat loads

  9. RF Analysis: Surface H Fields and Initial Wall Powers Advanced Energy Systems, Inc. Surface Power Loss 2K = 11.2 watts 4.2K = 70.5 watts Magnetic Field A/m 2.14e-2 9.14e3 1.82e4 2.74e4 3.65e4 4.56e4 5.47e4 6.38e4 7.29e4 8.21e4

  10. Work Remaining Advanced Energy Systems, Inc. • Phase 2 proposal due May 20 • Complete mechanical design work and determine fabrication cost for cavity • Complete thermal and structural analysis, primary concern will be cooling requirement for coaxial beam pipes • We are on track for May 20

Recommend


More recommend