FRAMINGHAM PUBLIC SCHOOLS FY18 CAPITAL PROJECTS PROJECT STATUS - PowerPoint PPT Presentation

FRAMINGHAM PUBLIC SCHOOLS FY18 CAPITAL PROJECTS PROJECT STATUS PROJECT STATUS PRIORITY # 1 PRIORITY # 1 REMOVAL OF FRAMINGHAM HIGH SCHOOL UNDERGROUND FUEL STORAGE TANK $ 5 0 ,0 0 0 Scope of work includes removal of the storage tank and


  1. FRAMINGHAM PUBLIC SCHOOLS FY18 CAPITAL PROJECTS

  2. PROJECT STATUS PROJECT STATUS

  3. PRIORITY # 1 PRIORITY # 1 REMOVAL OF FRAMINGHAM HIGH SCHOOL UNDERGROUND FUEL STORAGE TANK $ 5 0 ,0 0 0 Scope of work includes removal of the storage tank and disposal of the contaminated soil at Framingham High School as well as associated analytical, LSP services, and associated work with managing the contaminated soils- should this work become necessary during the course of the project .

  4. STORAGE TANK REMOVAL STORAGE TANK REMOVAL

  5. PRIORITY # 1 - STATUS PRIORITY # 1 - STATUS The project is 100% complete and the site has been restored and repaved at the Framingham High School.

  6. PRIORITY # 2 PRIORITY # 2 ROOF REPAIR WORK FOR 7 SCHOOLS $ 225 ,0 0 0 There are seven schools that require repairs in order for the five year warranty to be renewed. No warranty will be renewed without 100% compliance and without the required documentation. • Hemenway Elementary • King Elementary School • Barbieri Elementary • Woodrow Wilson Elementary • Potter Road Elementary School • Dunning Elementary School • Cameron Middle School

  7. TREMCO WARRANTY EXTENSION/RENEWAL PRICING MATRIX TREMCO WARRANTY EXTENSION/RENEWAL PRICING MATRIX $225,000 $225,000 CURRENT WARRANTY TERM PREVIOUS WARRANTY REPLACE.COST WARRANTY RENEWAL COST WTI REPAIR COST SCHOOL/SITE SQ.FT./AREA (INSTALLATION YEAR) RENEWAL EST. (2016-2020) (JULY 2016) (2016) HEMENWAY ELEM. 10 + 5+ 5 Years March 2009 $21,112 65,126 SQ/FT $1,855,116 $13,025 SCHOOL (Sep 1996) *(FIVE YEAR) WTI REPAIR COST 10 + 5 + 5 Years KING ADMIN. March 2009 $27,795 45,803 SQ/FT (Nov 1998) $1,304,700 $9,161 BUILDING *(FIVE YEAR) WTI REPAIR COST 10 + 5 + 5 Years BARBIERI March 2009 $58,944 69,383 SQ/FT (Nov 1998) $1,976,376 $13,877 ELEMENTARY SCHOOL *(FIVE YEAR) WTI REPAIR COST 10 + 5 + 5 Years WOODROW WILSON March 2009 $18,285 58,000 SQ/FT (Aug 1998) $1,652,132 $11,600 SCHOOL *(FIVE YEAR) WTI REPAIR COST 10 + 5 + 5 Years POTTER ROAD March 2009 $19,749 46,984 SQ/FT (Sep 1996) $1,338,341 $9,397 SCHOOL *(FIVE YEAR) WTI REPAIR COST 10 + 5 + 5 Years CHARLOTTE DUNNING March 2009 $68,522 65,841 SQ/FT (Sep 1996) $1,875,483 $13,168 SCHOOL *(FIVE YEAR) WTI REPAIR COST 15 Years January 2001 $18,544 CAMERON SCHOOL 70,000 SQ/FT $2,125,760 $14,000 (Sep 1996) *(FIVE YEAR) WTI REPAIR COST TOTAL 421,137 $12,127,908 $84,228 $213,202 WARRANTY RENEWAL $0.51, per sq./ft. $0.20, per sq./ft. (FIVE YEARS)

  8. PRIORITY # 2 - STATUS PRIORITY # 2 - STATUS This work is ongoing and once complete, the warranties on 7 school roofs will be extended for 5 years. **Note** $210,411 will be paid out of the Operating Budget to cover the remaining expense of this project to assure the extension of the warranties.

  9. PRIORITY # 3 PRIORITY # 3 ASBESTOS REPLACEMENT AND ABATEMENT PROJECT - KING $ 415 ,0 0 0 Estimated cost for the asbestos abatement and replacement of floor tile, ceiling tile throughout • the King Elementary School.

  10. CRACKED FLOOR TILE CRACKED FLOOR TILE

  11. LIFTING FLOOR TILE S LIFTING FLOOR TILE S

  12. PATCHED FLOOR TILES PATCHED FLOOR TILES

  13. CRACKED FLOOR TILES CRACKED FLOOR TILES

  14. NEW TILE HALLWAY 2 ND FLOOR NEW TILE HALLWAY 2 ND FLOOR

  15. NEW TILE FLOORING NEW TILE FLOORING

  16. PRIORITY # 3 - STATUS PRIORITY # 3 - STATUS THIS PROJECT IS 100% COMPLETE

  17. PRIORITY # 4 FURNISH NEW AND REPLACE OUTDATED FURNITURE FURNISH NEW AND REPLACE OUTDATED FURNITURE $ 15 0 ,0 0 0 $ 15 0 ,0 0 0 In order to address District population growth at the elementary level, the King School has been reopened as an elementary school in FY17, and new furniture has been purchased. Current population growth is prompting changes in the District with the King School being converted to a ninth elementary school. Kindergarten students were placed at the King School in FY16 with an additional grade level added each subsequent year until it reaches capacity as a K-5 school in 5 years. In addition, the majority of the District’s schools have the same furniture that was purchased during their construction in the sixties. Although there are many pieces of new furniture in the schools, there are several that still use outdated furniture. Current teaching methods and modern technology in the elementary and middle school grades requires the use of laptops and other devices. Modern furniture will better accommodate the use of these devices, instructional techniques and curriculum delivery.

  18. EXISTING OUTDATED FURNITURE EXISTING OUTDATED FURNITURE

  19. EXISTING OUTDATED FURNITURE EXISTING OUTDATED FURNITURE

  20. NEW KINDERGARTEN FURNITURE NEW KINDERGARTEN FURNITURE KING ELEMENTARY SCHOOL KING ELEMENTARY SCHOOL

  21. NEW CLASSROOM FURNITURE NEW CLASSROOM FURNITURE

  22. PRIORITY # 4 - STATUS PRIORITY # 4 - STATUS This phase of the project is complete however, with the re-opening of King Elementary School 4 th and 5 th grades, furniture is required as well as upgrade requests from other district schools for FY19.

  23. PRIORITY # 5 PRIORITY # 5 ATHLETIC EQUIPMENT – FRAMINGHAM HIGH SCHOOL $ 35 0 ,0 0 0 The current artificial turf field at Framingham High School was installed in 2006 and is showing signs of wear and tear. Artificial Turf Removal and Replacement – Framingham High School: Remove, dispose and replace existing artificial turf with a new artificial turf field .

  24. EXISTING TURF FIELD AT FRAMINGHAM HIGH SCHOOL EXISTING TURF FIELD AT FRAMINGHAM HIGH SCHOOL

  25. NEW TURF FIELD FRAMINGHAM HIGH SCHOOL NEW TURF FIELD FRAMINGHAM HIGH SCHOOL

  26. NEW TURF FIELD FRAMINGHAM HIGH SCHOOL NEW TURF FIELD FRAMINGHAM HIGH SCHOOL

  27. PRIORITY # 5 - STATUS PRIORITY # 5 - STATUS THIS PROJECT IS 100% COMPLETE

  28. PRIORITY # 6 BARBIERI PLAYGROUND REPLACEMENT BARBIERI PLAYGROUND REPLACEMENT $ 10 0 ,0 0 0 $ 10 0 ,0 0 0 Barbieri Elementary School is in need of new playground Equipment. Cost estimate details excluding installation: Main Equipment $92,719 Add’l item – Conga Drums $ 920 Add’l item – Emperor Chimes $ 2,970 Estimated Total $96,609

  29. NEW MODEL PLAYGROUND NEW MODEL PLAYGROUND

  30. NEW MODEL PLAYGROUND NEW MODEL PLAYGROUND

  31. NEW MODEL PLAYGROUND NEW MODEL PLAYGROUND

  32. NEW MODEL PLAYGROUND NEW MODEL PLAYGROUND

  33. COMPLETED PLAYGROUND COMPLETED PLAYGROUND

  34. COMPLETED PLAYGROUND COMPLETED PLAYGROUND

  35. PRIORITY # 6 - STATUS PRIORITY # 6 - STATUS THIS PROJECT IS 100% COMPLETE

  36. PRIORITY # 7 PARKING LOT EXPANSION AND REPLACEMENT PARKING LOT EXPANSION AND REPLACEMENT $ 5 6 2,0 0 0 $ 5 6 2,0 0 0 The School Department is requesting parking lot expansion and replacement for Dunning Elementary School for FY18. Funding request is for the scope of work required to improve the Dunning Elementary School site to include excavation, drainage, paving, seeding and playground improvements described in the proposal from BETA Engineering. Requested funding amount reflects the amount of construction work that can be completed in a limited time frame. As in the past, the Town unit pricing contracts will be utilized.

  37. DUNNING PROPOSED PARKING LOT DUNNING PROPOSED PARKING LOT EXPANSION EXPANSION

  38. DUNNING EXISTING PARKING AREA DUNNING EXISTING PARKING AREA

  39. EXISTING ENTRANCE EXISTING ENTRANCE

  40. EXISTING ENTRANCE EXISTING ENTRANCE

  41. EXISTING PARKING SPACES EXISTING PARKING SPACES

  42. EXISTING PARKING SPACES EXISTING PARKING SPACES

  43. NEW ENTRANCE NEW ENTRANCE

  44. NEW PARKING SPACES ENTRANCE NEW PARKING SPACES ENTRANCE

  45. NEW DUNNING PARKING SPACES NEW DUNNING PARKING SPACES

  46. PRIORITY # 7 - STATUS PRIORITY # 7 - STATUS This project is 99% complete. There are still plantings that need to be installed.

  47. PRIORITY # 8 PRIORITY # 8 HEATING , VENTILATION, & AIR CONDITIONING - UPGRADES $ 330 ,0 0 0  Dunning Elementary School  Remove and replace 19 rooftop exhaust fans  Woodrow Wilson Elementary  Replace Cooling Tower CT-1  McCarthy Elementary School  Cooling Schematic Design  Framingham High School  Cooling Schematic Design

  48. COOLING TOWER COOLING TOWER WOODROW WILSON - FULL VIEW WOODROW WILSON - FULL VIEW

  49. COOLING TOWER COOLING TOWER WOODROW WILSON - SIDE VIEW WOODROW WILSON - SIDE VIEW

  50. COOLING TOWER COOLING TOWER WOODROW WILSON - INSIDE GRIDS WOODROW WILSON - INSIDE GRIDS

  51. DUNNING SCHOOL ROOFTOP FANS DUNNING SCHOOL ROOFTOP FANS E1 & E2 AND E4 E1 & E2 AND E4

  52. DUNNING SCHOOL ROOFTOP FANS DUNNING SCHOOL ROOFTOP FANS E5 AND E7 AND E8 E5 AND E7 AND E8

  53. DUNNING SCHOOL ROOFTOP FAN DUNNING SCHOOL ROOFTOP FAN E9 E9

  54. DUNNING SCHOOL ROOFTOP FANS DUNNING SCHOOL ROOFTOP FANS E14 AND E15 AND E18 E14 AND E15 AND E18

  55. PRIORITY # 8 - STATUS PRIORITY # 8 - STATUS The Dunning Roof Fans project is 100% complete. The Wilson Cooling Tower project is scheduled for this winter. The Schematic Designs for adding cooling to McCarthy and the Framingham High School are 80% complete by CES.