Farmland Remediation Project Status Update Utilities Department April 3, 2018 Interactive graph here Alternative Discharge Final Report Discharge completed per KDHE approval Daily reports submitted 36.4 MG discharged to Kansas River


  1. Farmland Remediation Project Status Update Utilities Department April 3, 2018

  2. Interactive graph here

  3. Alternative Discharge Final Report • Discharge completed per KDHE approval – Daily reports submitted • 36.4 MG discharged to Kansas River through NPDES permitted outfall • Up to 3 years storage capacity restored

  4. Interactive graph here

  5. Land Application Final Report • 5.2 MG applied as fertilizer – Highest concentrations used for land app • 7 fields received water

  6. What the City has done • Ongoing Infrastructure Improvements – Well head automation – Tank inspections – Pipe improvements – Asset management & BMP for maintenance • Cross training – Between departments – Increased staff commitment and availability • Updating Operations and Procedures • Developed a Gatekeeper (stakeholder) group

  7. Consultant Selection • Selection process – Dr. Lines, from KU, alternative delivery methods – Blind process – Written proposal and interview stage – Risk based proposals • RFP posted 11/17 – 7 proposals – 4 interviews • Project tracking throughout

  8. Future of the Project • Contract with GHD – Site Assessment • Ensure the problems are well defined – Alternative Analysis – Stakeholder Engagement – Recommendation of Alternatives • Phase 1 complete by the end of 2018 • Update and maintain Farmland FAQ page Farmland FAQ's