extended detention basin design
play

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n - PowerPoint PPT Presentation

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1 Extended Detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 2 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and


  1. Extended Detention Basin Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1

  2. Extended Detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 2

  3. Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment w w w. t r a n s p o r t a t i o n . o h i o . g o v 3

  4. Extended Detention Basin Treatment Processes w w w. t r a n s p o r t a t i o n . o h i o . g o v 4

  5. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 5

  6. Siting Analysis - Considerations Space Enough R/W treatment Tributary area too large? Safety Environmental impacts Floodplain cut/fill R/W acquisition Vehicle access w w w. t r a n s p o r t a t i o n . o h i o . g o v 6

  7. Siting Analysis It can be difficult to find space. Intersections Interchanges R/W acquisition Underground detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 7

  8. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 8

  9. Detention Basin Sizing Calculate WQ V based on tributary area WQ V must be between lowest outlet primary outlet (10-yr) 10% WQ V additional for forebay Dead storage 10% WQ V additional for micropool Dead storage w w w. t r a n s p o r t a t i o n . o h i o . g o v 9

  10. Project Example - WQ V w w w. t r a n s p o r t a t i o n . o h i o . g o v 10

  11. Stage / Storage Curve w w w. t r a n s p o r t a t i o n . o h i o . g o v 11

  12. Project Example - WQ V w w w. t r a n s p o r t a t i o n . o h i o . g o v 12

  13. Project Example - Forebay w w w. t r a n s p o r t a t i o n . o h i o . g o v 13

  14. Project Example - Forebay w w w. t r a n s p o r t a t i o n . o h i o . g o v 14

  15. Project Example - Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 15

  16. Project Example - Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 16

  17. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 17

  18. Water Quality Outlet Design Drain WQ V in 48 hours or more 50% of WQ V or less drained in 1/3 rd of the drain time 0.422 ac-ft * 50% = 0.211 ac-ft 48 hrs * 1/3 = 16 hrs Provide time for sedimentation w w w. t r a n s p o r t a t i o n . o h i o . g o v 18

  19. Water Quality Outlet Design Orifices w w w. t r a n s p o r t a t i o n . o h i o . g o v 19

  20. Water Quality Outlet Design A Hydrograph drawdown curve is necessary Calculate a stage / discharge curve Or Use Pond Pack or HydroCAD Pond Pack is part of Bentley Hydraulics Suite w w w. t r a n s p o r t a t i o n . o h i o . g o v 20

  21. Project Example – WQ Outlet w w w. t r a n s p o r t a t i o n . o h i o . g o v 21

  22. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 22

  23. Outlet Structure 3 parts of detention basin outlet Water quality outlet(s) Slowly draw down the WQ V Primary outlet(s) Convey the 10-yr design storm (L&D Vol. 2, 1117.3.3 Overflow weir Convey the 25-yr design storm (L&D Vol. 2, 1104.2.2 w w w. t r a n s p o r t a t i o n . o h i o . g o v 23

  24. ODOT SCD WQ-1.1 Grate Primary Outlets Water Orifices Quality Outlets Pipe w w w. t r a n s p o r t a t i o n . o h i o . g o v 24

  25. Project Example – WQ Outlet No “Cleaning” above 799.00’ w w w. t r a n s p o r t a t i o n . o h i o . g o v 25

  26. Primary Outlet Design Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grate has the capacity to pass the 10-yr storm w w w. t r a n s p o r t a t i o n . o h i o . g o v 26

  27. Project Example – WQ Outlet Discharge Pipe w w w. t r a n s p o r t a t i o n . o h i o . g o v 27

  28. Primary Outlet Design Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grade has the capacity to pass the 10-yr storm w w w. t r a n s p o r t a t i o n . o h i o . g o v 28

  29. Project Example – Grate Elevation w w w. t r a n s p o r t a t i o n . o h i o . g o v 29

  30. Project Example – Grate Elevation w w w. t r a n s p o r t a t i o n . o h i o . g o v 30

  31. 1.25 ft 14.79 cfs w w w. t r a n s p o r t a t i o n . o h i o . g o v 31

  32. Overflow Weir Elevation Grate elevation = 799.0 ft Head needed to pass 14.79 cfs = 1.25 ft Overflow weir elevation: 799.0 ft + 1.25 ft = 800.25 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 32

  33. Project Example – Overflow Weir 25-yr peak flow = 16.53 cfs Assume top of basin is 0.5 ft higher than overflow weir Weir elevation = 800.25 ft Top of basin = 800.25 ft + 0.5 ft = 800.75 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 33

  34. Project Example – Overflow Weir Q = CLH 1.5 Q = 16.53 cfs C = 3 (L&D Vol. 2, 1102.3.4) H = 800.75 ft – 800.25 ft = 0.5 ft 16.53 cfs = 3 * L * 0.5 1.5 L = 15.6 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 34

  35. Project Example – Overflow Weir w w w. t r a n s p o r t a t i o n . o h i o . g o v 35

  36. Overflow Weir Flow rates over the 25-yr storm may overtop the detention basin uncontrolled. Consider erosion / scour protection Consider catastrophic failure w w w. t r a n s p o r t a t i o n . o h i o . g o v 36

  37. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 37

  38. Consider Catch Basin Invert Orifice Invert Pipe Invert w w w. t r a n s p o r t a t i o n . o h i o . g o v 38

  39. Call Out Catch Basin Invert w w w. t r a n s p o r t a t i o n . o h i o . g o v 39

  40. Other Det. Basin Considerations Velocity / Scour Anti-Seep Collars Safety Slope Stability and Item 670 Maintenance Access FEMA Floodplain ODNR Dam Permit? w w w. t r a n s p o r t a t i o n . o h i o . g o v 40

  41. Velocity / Scour w w w. t r a n s p o r t a t i o n . o h i o . g o v 41

  42. Anti-Seep Collars Reference: Dept. of Interior, 1982 w w w. t r a n s p o r t a t i o n . o h i o . g o v 42

  43. Anti-Seep Collars ODOT Standard Drawing WQ-1.2 w w w. t r a n s p o r t a t i o n . o h i o . g o v 43

  44. Project Example – Collar Design Berm Slope 4:1 10-yr Elev. 800.25 ft Pipe Inv. Pipe Dia. 24” 795.0 ft Saturated Pipe Slope 0.005 ft/ft Zone w w w. t r a n s p o r t a t i o n . o h i o . g o v 44

  45. Project Example – Collar Design Berm Slope 4:1 10-yr Elev. 800.25 ft 10 ft Pipe Inv. Pipe Dia. 24” 795.0 ft Pipe Slope 0.005 ft/ft Ls = 42.86 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 45

  46. Project Example – Collar Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 46

  47. Safety Detention basins are safety risks Clear zone: grading and 12” ponding Drowning hazard Local requirements? Fencing, trash rack, aquatic bench Impacts to upstream or downstream flooding w w w. t r a n s p o r t a t i o n . o h i o . g o v 47

  48. Slope Stability Do not locate on uncompacted fill or steep slopes (2:1 or more). Vegetate sides of basin Item 670, Slope Erosion Protection Don’t plant grass under water Forebay Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 48

  49. Maintenance Access Regular maintenance necessary Flat bench wide enough for a truck Grass needs to be mowed Woody vegetation cut from berm Regular unclogging of WQ outlet Every 6 months w w w. t r a n s p o r t a t i o n . o h i o . g o v 49

  50. Maintenance Access w w w. t r a n s p o r t a t i o n . o h i o . g o v 50

  51. FEMA Floodplain No BMPs in FEMA Floodplain Floodplains have open space for a reason No fill in FEMA Floodplain Unless compensatory cut/fill analysis Confirm limits of det. basin berms outside floodplain w w w. t r a n s p o r t a t i o n . o h i o . g o v 51

  52. ODNR Dam Permit Only for big detention basins No permit needed if: <10’ Berm and <50 ac-ft storage; or < 15 ac-ft storage; or < 6’ Berm w w w. t r a n s p o r t a t i o n . o h i o . g o v 52

  53. Re-Run the Numbers! Many iterations After values are set, re-run the analyses and check w w w. t r a n s p o r t a t i o n . o h i o . g o v 53

  54. BMP Calcs Spreadsheet w w w. t r a n s p o r t a t i o n . o h i o . g o v 54

  55. Sample Plan Note W106 w w w. t r a n s p o r t a t i o n . o h i o . g o v 55

  56. Questions ? Jon Prier, P.E. jonathan.prier@dot.ohio.gov 614-644-1876 w w w. t r a n s p o r t a t i o n . o h i o . g o v 56

Recommend


More recommend