erec g99 technical compliance requirements
play

EREC G99 Technical Compliance Requirements Webinar 30 th April 2019 - PowerPoint PPT Presentation

EREC G99 Technical Compliance Requirements Webinar 30 th April 2019 Peter Twomey and Gill Williamson Welcome to our webinar Gill Williamson Peter Twomey Strategic Planning Policy Webinar format 15 minutes 45


  1. EREC G99 Technical Compliance Requirements Webinar – 30 th April 2019 Peter Twomey and Gill Williamson

  2. Welcome to our webinar Gill Williamson Peter Twomey Strategic Planning Policy

  3. Webinar format 15 minutes 45 minutes presentation questions & answers Please submit written questions online during the webinar

  4. Agenda EREC G99 Demonstrating Compliance Process Terminology Compliance Technical Further Information Questions & Answers Requirements

  5. Terminology 5

  6. EREC G99 - Types (GB) • Types affect technical requirements and which forms you use Type A Type B Type C Type D <110 kV <110 kV <110 kV >110 kV Power Generating 0 800W 1 MW 10 MW 50 MW Module Registered Capacity 6

  7. Compliance and Installation Process 7

  8. EREC G99 - What part of the connection process is changing? Now After 27 April 2019 From Generator Concept to Connection Information Phase Information Phase Design Phase Design Phase Connection Offer Connection Offer Connection Acceptance Connection Acceptance Compliance Checking Compliance Checking Construction Phase Construction Phase Energisation/Commissioning Energisation/Commissioning Final Compliance Check Operational Notifications

  9. EREC G99 Connection Process - Compliance Checking Technical requirements Generators can choose vary with Type how they demonstrate compliance Type Testing is expected Type B, C & D Compliance to be used for Type A is tracked in the PGMD DNO approval is required

  10. EREC G99 Connection Process Compliance forms – Type A • For Type A, the form depends on the use of type testing Type A Manufacturer’s Information Site Tests Fully Type Tested No specific form Form A2-4 completed if site compliance tests are being Reference is made in the installation form undertaken for some or all Initial Submission to the registration on ENA website of Type A generator requirements and if Partially Type Tested Form A2-1 Synchronous PGM  50kW Interface Protection is not Form A2-2 Synchronous PGM >50kW Type Tested Form A2-3 Inverter connected PGMs Installation forms: Form A3-1 Type A PGMs From A3-2 Integrated micro generation and storage Prior to Synchronising

  11. EREC G99 Connection Process Compliance forms – Types B, C & D • We expect compliance methods and the submission programme will be agreed between the Generator and DNO soon after acceptance of the Connection Offer. Type Manufacturer’s Information Site Tests Type B Form B2-1 Form B2-2 completed if generator Interface Protection Power Generating Module is not Type Tested and other compliance tests that are Initial Submission Document (PGMD) being undertaken on site. Form B3 Installation and Commissioning Confirmation Type C Form C2-1 Form C2-2 completed if generator Interface Protection & D Power Generating Module is not Type Tested and other compliance tests that are Document (PGMD) being undertaken on site. Form C3 Installation and Commissioning Confirmation Prior to Synchronising

  12. Methods for Demonstrating Compliance 12

  13. EREC G99 Connection Process Compliance Options Generator S – Simulation study gathers/ creates evidence P – Design data DNO MI – Manufacturers information Submit G99 Feeds back / evidence and Compliance Approves Checking PGMD D – correspondence or other documents confirming requirements are met T – Site tests or monitoring to demonstrate DNO compliance (may be witnessed) reviews evidence TV – Type Test reports

  14. EREC G99 Connection Process Non Type Tested Protection Tests Non Type Tested Protection Site Tests - Forms A2-4, B2-2, C2-2 Calibration, accuracy and stability tests:- • Over and under voltage protection • Over and under frequency • Loss of mains protection (ROCOF)

  15. EREC G99 Connection Process Installation Checks Installation Checks - Installation forms A3-1 or A3-2, B3, C3 Check the requirements of BS7671 (IET Wiring Regulations) are satisfied Check points of isolation between the PGMs and the rest of the Generator’s Installation Check labels have been installed at all points of isolation Check that settings schedule has been provided and settings applied correctly Check interlocking that prevents PGMs being connected in parallel with the DNO system Check that the PGM successfully synchronises , runs in parallel and disconnects Check that i nterface Protection operates and disconnects the DNO’s Distribution Network quickly (within 1s) when switch opens between the PGM and the DNO and remains disconnected for 20s.

  16. EREC G99 Connection Process – Witnessing Site Tests We will not normally We may witness Partially witness site checks for Type Tested Type A fully type tested >100kW Exceptions include new We will witness all installer, random checks Type B, C & D site tests or quality concerns Electricity North West Witness Test Requirements

  17. Technical Requirements 17

  18. EREC G99 Technical Requirements – document sections Section 8 Section 9 Section 10 All Types - Network All Types - Connection Design All Types - Earthing Protection & Operation Section 11 Section 12 Section 13 Type A Type B Type C & D

  19. EREC G99 Technical Requirements - document sections Section 8 Section 9 Section 10 Network Connection Earthing Protection Design & Operation Minor changes Moderate changes Minor changes Sections 11, 12 & 13 Significant changes & new material • Control • Reactive Capability • Frequency Response • Fast Fault Current Injection • Fault Ride Through • Black Start • Voltage Limits & Control • Operational Monitoring

  20. EREC G99 Technical Requirements - Protection Protection Technical Requirements Changed  Same for all Types Type A There are different protection settings depending 10 Type B on the PGM connection voltage (LV or HV)  Under Voltage (1 stage); Type C&D  Over Voltage (2 stage); Demonstration  Under Frequency (2 stage); Methods  Over Frequency (1 stage);  MI  Loss of Mains (LoM).  TV  No change to short term parallel settings.  T

  21. EREC G99 Technical Requirements – PGM Performance and Control Requirements General Control Technical Requirements New Type A 11.1.3  Type A PGM will have logic interface (input port) Type B 12.1.3 to cease Active Power output within 5s Type C&D 13.1.3  Type B PGM will have communication interface Demonstration (input port) to reduce Active Power output Methods  MI  Type C PGM shall be capable of adjusting the  TV Active Power setpoint in accordance with instructions issued by the DNO

  22. EREC G99 Technical Requirements – Frequency Response Frequency Withstand Technical Requirements Changed  Same for all Types Type A 11.2.1 Frequency Range Time Type B 12.2.1 47 Hz – 47.5 Hz 20s Type C&D 13.2.1 47.5 Hz – 49.0 Hz 90minutes Demonstration Methods 49.0Hz – 51.0 Hz Continuous  MI 51.0 Hz – 51.5 Hz 90minutes  TV 51.5 Hz – 52 Hz 15minutes

  23. EREC G99 Technical Requirements – Frequency Response Rate of Change of Frequency Withstand Technical Requirements Changed  Same for all Types Type A 11.2.2 Type B 12.2.2 Type C&D 13.2.2 “capable of staying connected to the Distribution Network and operate at rates of change of Demonstration frequency up to 1 Hzs -1 as measured over a period Methods of 500 ms”  via protection settings

  24. EREC G99 Technical Requirements – Frequency Response Active power output with falling frequency Technical Requirements New  Same for all Types Type A 11.2.3 Type B 12.2.3 Type C&D 13.2.3 Demonstration Methods  T  MI  TV

  25. EREC G99 Technical Requirements – Frequency Response Limited Frequency Sensitive Mode – Over Frequency Technical Requirements New  Similar for all Types Type A 11.2.4 Type B 12.2.4 Type C&D 13.2.4 Demonstration Methods  S  MI  TV

  26. EREC G99 Technical Requirements – Frequency Response Limited Frequency Sensitive Mode-Under Frequency Technical Requirements New  Type C & D – respond without undue delay Type A - Type B - Type C&D 13.2.5 Demonstration Methods  S  MI  TV

  27. EREC G99 Technical Requirements – Frequency Response Frequency Sensitive Mode Technical Requirements Grid Code  Type C & D – only activated if providing Type A - ancillary service to National Grid Type B - Type C&D 13.2.6 Demonstration Methods  S (model validation)  MI  TV  T

  28. EREC G99 Technical Requirements – Fault Ride Through Fault Ride Through Technical Requirements New  Definite requirements for Types B, C & D Type A 11.3 Different Voltage vs Time curves for different Type B 12.3 Types and technologies e.g. Type C&D 13.3 Demonstration Methods  S  MI  TV

  29. EREC G99 Connection Process - New / Modified Technical Requirements Voltage Control Technical Requirements New  Not Type A Type A 11.4 Type B 12.4 Ability to control voltage and contribute, as agreed with the DNO, to voltage control or Type C&D 13.4 Reactive Power control or Power Factor control at Demonstration the Connection Point. Methods  S  MI  TV

Recommend


More recommend