energy conservation award nomination by
play

Energy Conservation Award Nomination: By Dr.M.S.Kele , Chief - PowerPoint PPT Presentation

Energy Conservation Award Nomination: By Dr.M.S.Kele , Chief Engineer (Commercial),Mumbai 1 0 Power Sector In Maharashtra MSEDCL At A Glance Current Installed Capacity In Maharashtra Yearly Average Peak Demand & Availability


  1. Energy Conservation Award Nomination: By Dr.M.S.Kele , Chief Engineer (Commercial),Mumbai 1

  2. 0 • Power Sector In Maharashtra • MSEDCL At A Glance • Current Installed Capacity In Maharashtra • Yearly Average Peak Demand & Availability • Sales And Revenue Mix For Fy 2011-12 murharikele@gmail.com 2

  3. Power Sector in Maharashtra Maharashtra State : Supplied Electricity through Four Power Distribution Utilities. • BEST Mumbai • Tata Power company • Reliance Energy limited • MSEDCL • MSEDCL Only Maharashtra Maharashtra State Electricity Board (MSEB) was unbundled into three companies on 6th June, 2005 murharikele@gmail.com 3

  4. MSEDCL AT A GLANCE LARGEST DISTRIBUTION COMPANY IN INDIA. Area: 3.08 Lakh Sq. km; Villages: 41095; Towns : 457 Consumers: 1.94 Cr. (Agricultural: 34 Lakhs /Residential: 143 Lakhs) Sub-stations & Switching Stations: 2514 (33/11 & 22/11 kV) HT & LT Lines: 8.70Lakh ckts km , Distribution Transformers: 3.90 Lakh Monthly Revenue : Rs 3100Cr (Approx) Average Cost of Supply: Rs. 5.56 per unit Zones: 14/ Circles: 43/ Divisions: 138/ Sub Divisions: 629 / Section Offices: 3294 Employees: 77,109 Departmental & 10,335 Outsourced murharikele@gmail.com 4

  5. CURRENT INSTALLED CAPACITY IN MAHARASHTRA Paras 500 Khaparkh URAN GTPS eda Chandrap 672 MW 840 Total ur 2340 MSPGCL MSPGCL HYDRO 2585 MW Total Koradi MSPGCL & 620 installed MSPGCL Thermal=7230 MW Capacity GAS 672 MW SMALL HYDRO 629 MW 10487 MW Nasik KOYNA HYDRO 1956 MW 880 Parali 1130 Bhusaval 920 CENTRAL RGPPL (1967 MSPGCL SECTOR MW) +NCE TATA & 23648 Installed (3354 MW)+ +GoM RELIANCE Capacity IPPs (780 MW Hydro 2527 MW MW)+Dodson 10487MW 4487 MW Hydro 46 MW Maharashtra State 7230 Thermal 2639 Gas 2631 Hydro Central +GOM Hydro+TATA 7014 3354 NCE 780 CPP / IPP (Major) 5 murharikele@gmail.com Total (MW) 23648

  6. YEARLY AVERAGE PEAK DEMAND & AVAILABILITY 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 YEAR MW MW MW MW MW MW MW MW Demand 12404 12797 13137 12507 12624 13157 14043 14173 Availability 9212 9638 10130 10203 10921 11917 12841 13286 Shortfall 3192 3159 3007 2304 1703 1240 1202 886 Shortfall Availability 15000 10000 5000 0 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 Demand Supply Gap Reduced: MSEDCL is near about to Power Surplus Position 6 murharikele@gmail.com

  7. SALES AND REVENUE MIX FOR FY 2011-12 No. of cons in % Sale in % HT (Ind) LT (Ind) Comm (LT+HT) HT (Ind) LT (Ind) Comm (LT+HT) Residential Agri.(LT+ HT) Others Residential Agri.(LT+ HT) Others 0%1% 1% 7% 13% 18% 32% 27% 6% 6% 16% 73% Revenue in % HT (Ind) LT (Ind) Comm (LT+HT) Residential Agri.(LT+ HT) Others 20% 41% 5% 15% 11% 8% 7 murharikele@gmail.com

  8. Transformation-MSEB to MSEDCL Parameters MSEDCL-2013 % Change MSEB-2005 Installed capacity in 9856.MW 23648 MW 139.93 % Shortage of power 4025.MW 886 MW -77.98 % 40806 Crs 170.74 % Annual Turnover 15072 Crs Distribution Losses: 31.72 % 16.03% -49.46 % AT & C losses 18.41% -32.31 % 36.06 % 97.21% 14.10 % Collection efficiency: 85.19 % 83.87% 21.79 % Billing Efficiency 68.86 % Transformer failure rate 18.52 % 5.68% -69.33 % Agriculture connections 23.24,Lackhs 34 Lackhs 46.29 % murharikele@gmail.com 8

  9. 1 Absolute Energy saving & Investment Made • Loss Reduction & Energy Saving – AT&C Loss: Schematic Diagram – Reasons: AT&C Loss – Performance of MSEDCL – DISTRIBUTION TRANSFORMER FAILURE RATE Energy Conservation is Practice for: -- Ensuring judicial use of Energy & --- Decreasing quantity of Energy Consumed. murharikele@gmail.com 9

  10. Efficiency at Different Level EHV Step up Generation Transmission Station Efficiency Stn 400kV 400kV ( PLF 30%) (99.5%) (99%) Efficiency Consumer Distribution at Gen to Level 33kv Supply Side Efficiency (1% Loss) Door Step End User & 11kV (95%) (87%) (87%) Demand Side Efficiency (13% Loss) HV Sub Step Down Transmission Level at 33 Transmission Stn (220kV) at or 11kV 97.5% 132kv/66kV (95.5%) (96%) Meter Appliances Energy Side Side Realized Transmission Side Efficiency (4.5% Loss) Consumer Side Efficiency (18 % & More) murharikele@gmail.com 10

  11. Can We Think in this Direction? • Loss to MSEDCL as Distribution Co . – Total Power Purchase =1,00,000 MUs/Yr – 1% Loss of MSEDCL= 1000 Mus – Av. Cost of Supply= Rs.5.56/Unit – Revenue Loss for 1% Loss=556 Crs/Yr – Present AT & C Loss of MSEDCL= 18.41 % – Permissible loss for such utility= 13.5 % – Yearly We are loosing revenue of Rs. 2700 Crs (Approx)/Yr ------------------------------------------------------------------------------ – One Units Saved is two units generated? – Allied Issues: • Capital Cost, Fuel Cost • Pollution • Transportation • Plant Load Factor • Administrative & General Expenses. • ROW & Land & Forest Problems ----------------------------------------------------------------------------------------------------------  Loss reduction Means Increase in Supply Side Efficiency murharikele@gmail.com 11

  12. AT & C Loss –Schematic Diagram Energy Energy Billed to Energy Input consumption Consumers (Units) (Units) (Units) Billing Gap AT &C Loss Recovery Gap Amount Amount Billed Energy Realized Recovered to Consumers (Units) (Units) (Units)  Formulae:  AT&C Loss (%)=(Energy Input-Energy realized) x 100/ Energy input  Energy realized= Energy billed x Collection efficiency  Collection Efficiency(%)= Amount realized x100/ Amount billed  Average tariff = Amount billed / Units Billed  Energy Realized = Amount recovered / Average tariff 12 murharikele@gmail.com

  13. Reasons: AT&C Loss  Technical Loss  Commercial Loss  Universal Service Obligation  Metering:  Large scale rural  Theft – hooking electrification  Tampering of meter  Ad-hoc expansion without  Old/electromechanical proper planning meters  Old technology & fragile  Nature & Locations of meters infrastructure  Billing  Too many transformation  Inaccurate Reading stages  Low power factor  Methodology of billing  Improper load management  Average/in accessible cons.  Improper location of DTC  Improper tariff & Wrong calculations  Substandard material  Collection  Poor construction methods  Payment mode & facilities  Non-effective disconnection Loss of opportunity by any reason, to serve consumers is biggest loss of utility 13 murharikele@gmail.com

  14. Performance of MSEDCL Particulars 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 Input ( MUs) 64847 69813 73400 74559 80526 86170 95433 Sale ( MUs) 44279 49148 55716 58171 63941 71279 80132 Dist. Loss (MUs) 20568 20655 17684 16388 16585 14891 15301 % Dist. Loss 31.72 29.6 24.09 21.98 20.6 17.28 16.03 % AT & C Loss 34.72 33.98 26.08 24.62 21.41 18.45 18.41 % Coll. efficiency 85.19 94.07 97.8 96.61 98.98 98.52 97.21 250000 140 Dist. Loss (MUs) Sale ( MUs) Input ( MUs) 120 200000 100 150000 80 % Coll. efficiency % Dist. Loss 60 100000 40 50000 20 0 0 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 Loss Reduction approx.by 50% after company formation i.e.in 7 years 14 murharikele@gmail.com

  15. DISTRIBUTION TRANSFORMER FAILURE RATE No of Distribution No of Transformers Distribution Transformers Year Transformers Installed Failed during year failure rate in % 2005-06 226824 36618 16.14% 2006-07 239333 40483 16.91% 2007-08 256793 33375 13.00% 2008-09 271251 38785 14.30% 2009-10 284633 38084 13.38% 2010-11 321351 36495 11.36% 2011-12 358408 33973 9.48% 2012-13 376329 21386 5.68% Distribution T/F failure rate in % 400000 18.00% 350000 16.00% 300000 14.00% 250000 12.00% 10.00% 200000 8.00% T/F failure rate is reduced by: 66 % 150000 6.00% 100000 4.00% As Compared with last year: 45% 50000 2.00% 0 0.00% 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 murharikele@gmail.com 15

  16. Separate Budget Allocation for EC 2 • Implementation of various schemes – Infrastructure plan – RGGVY – APDRP & R-APDRP • Demand Side management – Single phasing Scheme – Gaothan feeder Separation murharikele@gmail.com 16

  17. MSEDCL - Infrastructure Plan Reliable and Quality Results of scheme: Power • HT/LT ratio reduced Supply • Technical losses are reduced. • Transformer failure rate Aim & Meet the Reduce Objectives Load DTC reduced by 2-3 % Growth Failure of Infra • Demand. Strengthen infrastructure has Rate Plan increased consumers satisfaction. Reduce • Reliability & Quality of supply Distribution Losses. improved. Progress of Activity Scope of work Commissioned New Substation 613 348 Augmentation of Power Transformer 330 272 Additional Power Transformer 428 349 H.T. Lines (Km) 50323 25344 L.T. Lines (Km) 15657 6395 Distribution Transformer ( *** rated T/F) 68147 46734 HVDS 13256 8365 Pole Mounted Capacitor Banks 2896 1707 Cost of Infra.plan project Rs.9013.96 crs Rs.5184 crs 17 murharikele@gmail.com

Recommend


More recommend