earl pumping station community liaison working group
play

Earl Pumping Station Community Liaison Working Group 24 September - PowerPoint PPT Presentation

Earl Pumping Station Community Liaison Working Group 24 September 2018 Construction update 2 EARPS Earl Pumping Station 3 EARL PUMPIN PING S G STATIO ION PROG OGRES ESS 4 Current Progress fence: Silo slab Bundwall and Started


  1. Earl Pumping Station Community Liaison Working Group 24 September 2018

  2. Construction update 2

  3. EARPS Earl Pumping Station 3

  4. EARL PUMPIN PING S G STATIO ION –PROG OGRES ESS 4

  5. Current Progress fence: Silo slab Bundwall and Started installation of fence piping: line 95% of the bund wall and pipe connections Silo slab 1 to 2 Pipe completed duct connection: 95% finished installation of pipe ducts and connection of pipes between the two silo slabs. Croft street hoarding: 50% finished installation new hoarding at croft street Geomix: Completed a further 12 panels and UKPN substation: the 2 soft panels as well as 90% completion of palisade fencing continuing backfilling the bound 5 around UKPN sub-station trenches.

  6. What w we a are bu building ng 6

  7. September 2018 7

  8. Earl P Pumpin ing S Statio tion September 2018 8

  9. 9 September 2018

  10. September 2018 10

  11. September 2018 11

  12. 12

  13. Construction Work Sewer coring Offices in operation Muck bin construction Grout Bag Trials Foul water pipe diversion Platform partly constructed 13

  14. Ov Over p pumpi ping a and si site d e drainage 14

  15. Platform form exca cavation, on, over p pumping e exca cavation on and local se al sewer er d diver ersi sions 15

  16. Muck b k bin c constr truc uctio tion 16

  17. New w workin king e environme ment Start of shift briefing Welfare room Staff in the new office 17

  18. Upcoming work Obstructio ion cor orin ing Dia iaphragm wall ll construct uction Geom eomix ix 18

  19. Upcomin ing W Work k 2018 2019 Programme Overview May June July Aug Sept Oct Nov Dec Jan Feb March April Substations installation cable pulling (excavation on Chilton Grove and Croft Street) Temporary sewer diversion construction Platform construction (including muck bin) Water main diversion on Croft Street Coring of existing Earl sewer (obstruction coring) Geomix Diaphragm wall construction Standard Working (08:00 - 18:00) Monday to Friday, (08:00 - Hours 13:00) Saturday Extended Working (08:00 - 22:00) Monday to Friday, Hours (08:00 - 13:00) Saturday Working Hours Standard Extended Monday – Friday 08:00 – 18:00 Until 22:00 Saturday 08:00 – 13:00 Until 17:00 1 hour allowed before & after for mobilisation 19

  20. Traf affic Mo Movem ement Thames Water access to pumping station Entrance on Yeoman Street Earl Pumping Station site Temporary exit during road closure works Exit on Croft Street Croft Street road closure Note: abnormal loads will be allowed to use Yeoman Street gate as an exit 20

  21. Traffic Update – works completed 6-7 September 21

  22. Vehi ehicle Ho e Holding A Area rea – Bes estwood S Street reet CVB will use part of the bus lane on Bestwood Street as a vehicle holding area to manage deliveries to the site more efficiently. Vehicles will be registered on arrival, checked for safety compliance and then leave for site as soon as is reasonably practical. Duration: May 2018 to December 2021 Vehicle holding Wor orking h hou ours: area Monday to Friday, 07:00 – 18:00 Saturday, 07:00 - 13:00 What w we will do: • Schedule all vehicle movements • Ensure no vehicle engine idling within holding area 22

  23. Environment 23

  24. Noise e and Ai Air Qu Quali lity no exceedances Noise Monitor Air Quality Monitor Noise Air Quality Month S61 Exceedances 24h PM 10 Exceedance Jan-18 0 0 Feb-18 0 0 Mar-18 0 0 24 Apr-18 0 0

  25. Od Odour Ma Manag agement When excavating, odour from ground conditions may become more noticeable To minimise this, odour will be managed in the following ways: • Odorous excavated material will be covered and removed from site as soon as possible • Site personnel trained to identify and deal effectively with odour sources • Daily assessments at site boundary to confirm control measures are working • ‘Misting’ system to de-odourise or mask odour when necessary 25

  26. Legacy and Community Relations 26

  27. RIV IVER T TIME IMES – Summe ummer Editi dition n del eliver ered ed A digital copy of this publication can be found here https://www.tideway.london/media/4081/river-times_east_summer_18.pdf 27

  28. Staff C Char arity 20 2018 T 8 Tid ideway E Eas ast Great Ormond Street Hospital was chosen by staff in June to be this year's chosen charity Gre reat Orm Ormond Stre reet Ho Hospital The money was raised through a variety of staff activities including a raffle and a World Cup Sweepstake Since April, Tideway East has raised over £2,000 28

  29. Charity ity In July, five members of staff from Chambers Wharf completed the British 10K run. The team ran in support of the Deborah Ubee Trust, a Greenwich based mental health charity neighbouring our Greenwich Pumping Station site. The team managed to raise over £800 29

  30. Women in Engineering 2018 Brownies raise the bar As part of Women in Engineering Week 2018 in June, Tower Hamlets Guides and Brownies visited Chambers Wharf, and we visited a Brownie pack in Bow. They learnt that women can make a positive impact in Engineering and Construction - as well as taking part in some fun tasks. After a quick talk about engineering and the Tideway project, the girls got stuck into lots of activities to get them thinking like engineers. These included building spaghetti and marshmallow towers, balloon hovercrafts, lava lamps and lemon fizz volcanoes. And of course a challenge to ‘raise the bar’ #raisethebar 30

  31. Next Ge Gene neratio ion of of Eng ngine neerin ing Appren entic ices eships ips • Three new civil engineering apprentices have joined our team • Two are from Newham, one recently finished studying at the London Design Engineering UTC • Two are studying degree level 6 qualifications Work e exper erien ience Four work experience students with us over the Summer. World of Work visit from students Two from the St Michael's College, one from taking part in the National Citizen Walworth Academy and one from East Young Service summer programme ‘The Leaders Academy (EYLA). Here’s some of their Challenge’ feedback: They were working on a project to raise money for charity tackling “Thanks to my work experience I have been able to develop a wide range of skills, including working as part of a team, listening and domestic violence. organisation. It's also helped boost my confidence.” They practised their Dragon’s Den “Getting a feel of engineering at Tideway has really encouraged style presentation with us. me to go on and work in engineering.” “Engineering is now definitely an option for my future .” 31

  32. Foresh shor ore c e clean an-up up King Edward M rd Memori orial F Fore reshore ore S Site Tideway East volunteers headed down to the foreshore in July to clean up plastic rubbish. The team made a great effort and were able to collect many bags full of plastic. This waste is taken away and properly disposed of. Plastic is a hazardous material polluting our waterways. It’s putting wildlife at risk, harming and in some cases mutating aquatic life . 32

  33. Foresh shor ore c e clean an-up o p on th the I e Isl sle e of D Dogs s Staff volunteers, accompanied by the neighbouring Ecology Consultancy, based at Bermondsey Wall West, took to the Isle of Dogs foreshore to remove plastic waste embedded within its beach. Within the fifty bags of plastic rubbish collected they found a bag of Smiths salted peanuts with an expiry date of January 1984 - Which makes them 34 years old! Newcastle Draw Dock - August 2018 33

  34. More information can be found at: https://www.tideway.london/our-community/foreshore-festival/Shadwell-Activities 34

  35. Th Than ank y k you ou Any questions please contact the Tideway Helpdesk on: Telephone: 08000 3 00 308080 080 Email: Helpdesk@Tideway.London 35

  36. Thanks for attending Any questions?

  37. THANK YOU Earl Pumping Station Community Liaison Working Group 21 May 2018 37

Recommend


More recommend