downtown redmond link extension
play

Downtown Redmond Link Extension Project Update Sound Transit Board - PowerPoint PPT Presentation

Downtown Redmond Link Extension Project Update Sound Transit Board of Directors June 28, 2018 Overview Includes Refinements 3.4-mile light rail extension (previously 3.7 miles) Two stations: At-grade SE Redmond, Elevated


  1. Downtown Redmond Link Extension Project Update Sound Transit Board of Directors June 28, 2018

  2. Overview – Includes Refinements • 3.4-mile light rail extension (previously 3.7 miles) • Two stations: • At-grade SE Redmond, • Elevated downtown Redmond (previously at-grade) • 1400 parking spaces • Design-Build Delivery – single contract • Open for service in 2024 2

  3. Project schedule 2007 - 11 2016 2017 2018 2019 2019 - 24 East Link EIS System Restart Begin property Complete Complete and Record of expansion environmental acquisition AHJ Property Decision approved by and conceptual Agreements Acquisition Board selected voters engineering Begin project to be contractor Select Design and built Funded DRLE Project procurement Design-Build Construction through refinements Contractor Two construction Complete Systems at-grade Begin design- environmental Issue NTP Testing stations build procurement Select project Continue 1400 parking documents to be built property Revenue spaces acquisition Service Begins Baseline 3 Project

  4. Environmental Status • East Link Records of Decision (FTA & FHWA) – 2011 • Includes Downtown Redmond Link Extension Project refinements evaluated in SEPA Addendum to the Final EIS • Anticipate publication this summer • • Board Consideration of Refined Project to Build – September • Refinements included: • Elevated in downtown (previously at-grade) • Additional Property impacts 4

  5. Design-Build RFP Development • RFP documents ~90% (design concepts, project requirements, Special Conditions, etc.) • Scope alignment with Project Partners nearly complete • Developing Design-Build Permit Process with City of Redmond • Final RFP released – Fall 2018 5

  6. Project Challenges • ROW Acquisition • Market Conditions – price escalation • Compressed Schedule – timely decisions & approvals 6

  7. Upcoming Project Activities • Advertise Request for Qualifications – Summer 2018 • SEPA Addendum publication – Summer 2018 • Board Selects Project to Build – Fall 2018 • Project Baseline – Fall 2018 • RFP Stipend – Fall 2018 • Issue RFP – Fall 2018 • AHJ Agreements Fall ‘18 – Spring ’19 * Board Action 7 * Board actions to be determined

  8. Upcoming Project Activities 2018 2019 J F M A M J J A S O N D J F M A M J J A S O N D SEPA Addendum Publication Select Project to build Phase Gate 4 - Baseline RFP Stipend DB Contract ~14 mo to NTP DB Procurement Approval RFQ RFP AHJ Agreements * DBPM Phase 1 DBPM Phase 2 Board Action Board actions to be determined * 8

  9. 12

Recommend


More recommend