Downtown Infrastructure Construction Schedule and Coffee w/ the Commissioner Economic Development Update The day everything changed!! Strategic Objectives 2013 Tornado 2014 Citizens Survey 2015 Comprehensive Plan


  1. Downtown Infrastructure “Construction Schedule” and Coffee w/ the Commissioner “Economic Development Update”

  2. The day everything changed!!

  3. Strategic Objectives • 2013 Tornado • 2014 Citizens Survey • 2015 Comprehensive Plan • 2016 Downtown M aster Plan • 2017 Community Improvement Plan

  4. Drumbeat of Progress 2016 2014 2015 2018 2017 M ay 2013

  5. HP Grant Program 1. 101 S Dallas Complete 2. 207 W. Ennis Ave Complete 3. 213 N. Dallas Complete 4. 107 S. Dallas In-Const 5. 213 W. Ennis Ave In-Const 6. 218 W. Ennis Ave In-Const 7. 108 W. Ennis Ave 3 Complete 22 8. 208 W. Knox Complete 9. 117 N. Dallas In-Const 15 8 10 20 16 10. 204 W. Knox Complete 11. 101 SW M ain J an 2018 25 21 9 12. 103 SW M ain J an 2018 24 13. 112 W Brown J an 2018 23 26 14. 115 S Dallas J an 2018 17 7 6 15. 114 W Knox J an 2018 16. 116 W Knox J an 2018 11 19 18 5 2 1 17. 110 W Ennis Ave J an 2018 12 4 18. 105 W Ennis Ave J an 2018 19. 107-109 W Ennis Ave J an 2018 14 13 20. 200 W Knox Complete 21. 113 W Knox Complete 22. 210 N Dallas Complete 23. 120 N Dallas Complete 24. 112-114 N Dallas Complete 25. 116 N Dallas Complete 26 Grants 26. 113 N Dallas Complete Private Investment: $10,399,708 Public Investment: $2,463,202

  6. Downtown M aster Plan • Adopted M ar 7 th , 2016 • Vision to guide Downtown Revitalization

  7. Value Gradient / Value Transfer Downtown - YESTERDAY • Center of Commerce • High Point of Value • Value Radiates Outward Downtown - TODAY • LOW point of Value • Value Depreciates Downtown - TOM ORROW • Experiential Destination • High Point of Value • Value Radiates Outward Intellectual Citation: M ESA Planning (Robin M cCaffrey)

  8. Downtown Investment Public $ Private $ 2013-2018 • Historic Preservation Grants (26) $2,463,202 $10,399,708 • Façade Improvement Grants (14) $91,656 $264,554 2017-2019 • Water & Sewer • Dallas Street $8,200,000 • Alleys & Storm Wtr • M innie M cDowal Park $800,000 • Welcome Center $4,000,000 $15,554,858 $10,664,262 $26,219,120

  9. Imperative 1 IH 45 M arket to Downtown M arket IH 45 I-45 M arket $$ Downtown M arket Bus 45 IH 45 $$ X Bus 45

  10. Imperative 2 North Plaza to South Plaza 8 blocks (off-System) North Bus 45 Plaza Bus 45 South Plaza Spur 437

  11. Downtown M aster Plan Project Allocation M ap:

  12. Downtown M aster Plan Catalyst Projects: • Tier One • Water & Sewer 2018-2019 Project • Dallas Street 2018-2019 Downtown Infrastructure • Alleys & Grease Traps 2018 • Grade Separated Crossing Active Project UP Safety Zone • Ennis Avenue Active • North Plaza Active Project Plaza P3 • South Plaza Active • M ain Street M all Active • Tier Two • Tier Three • M innie M cDowal Park Complete • Welcome Center 2018-2019

  13. Downtown M aster Plan Implementation Strategy: • M ultiyear Journey • How do we get from the current state to the future state Current State Future State

  14. Downtown M aster Plan Implementation Strategy (10 years): Catalyst Projects Current State Future State M M Park Infrastructure North Plaza Under-Pass South Plaza Dallas Street Welcome Center M S M all (N) Ennis Avenue M S M all (S) 1-2 3-4 5-6 7-8 9-10 Time (Y ears)

  15. Downtown M aster Plan The Future • Revitalized Downtown • Better “Quality of Life” • Shopping • Dining • Entertainment • Residential Lofts • A place to “ hang out ” Foundation of Essential Services

  16. M innie M cDowal Park The VISION

  17. M innie M cDowal Park The REALITY

  18. Welcome Center The VISION

  19. Grade Separated Crossing & M ain Street M all

  20. North Plaza

  21. South Plaza

  22. Project Downtown Infrastructure UPDATE

  23. Project Scope North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas M cKinney Street

  24. Water Lines North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  25. Sewer Lines North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  26. Grease Trap S ystems North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  27. Electrical S ystems North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  28. Alley Streetscape North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  29. Dallas Streetscape North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Dallas Dallas M cKinney Street

  30. Work Areas North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Work Area 6 Work Area 5 Work Area Work Area Work Area Work Area 1 2 3 4 M cKinney Street

  31. Construction Schedule Four Phase Operation: Work Area Timeframe • Phase 1 1 and 4 M ar-Apr-M ay • Phase 2 2 and 3 Jun-Jul-Aug • Phase 3 Dallas North Sep-Oct-Nov-Dec • Phase 4 Dallas South Jan-Feb-M ar-Apr • Welcome Ctr 201 NW M ain Apr 2018 to Apr 2019

  32. Phase 1 (M ar-Apr-M ay) North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Work Area 6 Work Area 5 Work Area Work Area Work Area Work Area 1 2 3 4 M cKinney Street

  33. Phase 2 (J un-J ul-Aug) North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Work Area 6 Work Area 5 Work Area Work Area 2 3 M cKinney Street

  34. Phase 3 (Sep-Oct-Nov-Dec) North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Work Area 6 Work Area 5 M cKinney Street

  35. Phase 4 (J an-Feb-M ar-Apr) North Side South Side M ain Street Crockett Baylor Knox Brown St St St St Ennis Ave Work Area 6 M cKinney Street

  36. Downtown Parking UPDATE

  37. Walmart Comparison

  38. Public Parking

  39. Dallas Street

  40. Dallas Street

  41. Dallas Street

  42. Dallas Street

  43. Coffee w/ the Commissioner Economic Development UPDATE

  44. Economic Development Corp. • Created in 1995 • Type B • Funded by a half cent 4b sales tax ($1.8 per year) • Board of Directors (7) • M ike M ontgomery (President) • Russell Thomas (Secretary) • Angie Juenemann (Treasurer) • T om Abram (Director) • Jess Haupt (Director) • Betty Glaspy (Director) • Phil Newsom (Director)

  45. Economic Development Corp. VISION: Every resident will have the opportunity to maximize their economic potential. M ISSION: Facilitate the diversified economic growth of our community presenting Ennis as the preferred industrial, commercial and residential choice. PURPOSE: Enhance the quality of life within our community and to promote continuing development for the City of Ennis.

  46. EcDev T eam M EM BERS City Commission Economic Development Corporation Director, Economic Development M arty Nelson Director, Communications and M arketing Ashley Colunga Director, T ourism and Guest Services Gina Rokas M anager, M ain Street Becky M cCarty Executive Assistant Rhonda Winters Ginger Gonzales Secretary, Receptionist, Grant Writer M ary Davis Farmers M kt & Downtown Event Coordinator

  47. EcDev Goals and Objectives LINES OF OPERATION • Communications & M arketing • T ourism / Visitor Guest Services • Industrial Development • Downtown Revitalization • Kaufman Development District • Retail Development • Residential Development • Workforce Development • Bardwell Lake Development

  48. Economic Development Imperatives: 1. I-45 M arket connection to the Downtown M arket • M ust be physically connected to allow the free flow of commerce • Railroad X-ing is a physical obstacle that M UST be overcome • Grade separated crossing 2. North Anchor connection to South Anchor: • M ust be physically connected to allow the free flow of commerce • Ennis ave is a physical obstacle that M UST be overcome • Ennis Ave (Off-System) 3. Growth in TIRZ#2 (East IH 45) • Creates economic vitality that will transfer into the Downtown

  49. Imperative 1 IH 45 M arket connected to Downtown M arket IH 45 I-45 M arket $$ Downtown M arket Bus 45 IH 45 $$ X Bus 45

  50. Imperative 2 North Plaza connected to South Plaza 8 blocks (off-System) North Bus 45 Plaza Bus 45 South Plaza Spur 437

  51. Imperative 3 TIRZ# 2 • Growth drives economic vitality into the City • Property Tax Driven • Value Capture 446.22 A • 75% City of Ennis • 75% Ellis County • 30 Y ear Duration

  52. Communications & M arketing BRANDING CAM PAIGN • Phase 1 EXPLORE • What does Ennis say about itself • What do outsiders say about Ennis • Phase 2 EVALUATE • Brand Truths • Brand Strategy • Phase 3 EXPRESS • Brand Story • Logo • Video • Phase 4 ENGAGE

  53. Communications & M arketing

  54. Communications & M arketing