dominion diamond s lynx project wek eezhii land and water
play

Dominion Diamonds Lynx Project Wekeezhii Land and Water Board - PowerPoint PPT Presentation

Dominion Diamonds Lynx Project Wekeezhii Land and Water Board Public Hearing Feb 6, 2014 1 Dominion Diamond is the NWTs Largest Mining Company We are a Canadian owned Company Dominion owns: Most of the Part of the Ekati Diamond


  1. Dominion Diamond’s Lynx Project Wek’eezhii Land and Water Board Public Hearing Feb 6, 2014 1

  2. Dominion Diamond is the NWT’s Largest Mining Company We are a Canadian owned Company Dominion owns: Most of the Part of the Ekati Diamond Diavik Diamond Mine (80%) Mine (40%) Lorem ipsum Dominion employs more Northerners than any other mining company in the NWT 2

  3. Dominion’s Ekati Diamond Mine The Ekati Mine is in the Coppermine River drainage area 3

  4. Dominion’s Ekati Diamond Mine (cont’d) Ekati Main Camp is on the North side of Lac de Gras Misery Camp is 29km from Ekati Main Camp 4

  5. Location of Lynx Kimberlite Pipe Lynx Pipe is ~3km southwest of the Misery Camp / Mine Operations 5

  6. Lynx Project – Proposed Land Use Permit Area 6

  7. Misery Pushback and Proposed Lynx Project Schedule Lynx Project General Development Schedule (reflects current operational scheduling, December 2013, that is subject to change) 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Misery Pit Mining Reclamation Pump Flooding Reclamation Pit Lake Monitoring est. +10 years Lynx Pit Water Licence / Land Use Permit Road Work Fishout Dewatering Mining *see note below Reclamation Pump Flooding Reclamation Pit Lake Monitoring est. +10 years *The final scheduling for mining of Lynx Pit may be adjusted based on integration with possible future projects (yet to be approved), where this enables the direct and efficient use of granite waste rock for construction purposes. 7

  8. Lynx Project – Baseline Studies 2002 Lynx area aquatic baseline studies 2013 Lynx area aquatic baseline studies • Water quality • Sediment quality • Phytoplankton, zooplankton and benthic invertebrates • Fish and fish habitat 2013 Lynx area terrestrial baseline studies • Air and noise • Soils • Vegetation • Wildlife (raptors, upland birds, waterfowl, caribou, carnivore dens) • Archeology 8

  9. The Lynx Project Extends the Operation of Misery Site Lynx development will extend the life of the Misery site for approximately 1-2 years The Misery camp, haul road, waste rock storage area, and minewater management facilities are already in place Lynx development will provide 4-5 months of kimberlite feed to the Ekati Process Plant 9

  10. The Lynx Project requires Minimal New Development 3km road upgrade between Misery and Lynx sites 1km new road to support Lynx activities Lynx pit dewatering and minewater pipelines Fish-out and dewatering of Lynx Lake to expose the Lynx pipe Mining of the Lynx pipe 10

  11. Lynx Access Road Caribou crossings will be constructed along Lynx access road • • Locations to be identified in discussion with Aboriginal communities 11

  12. Lynx Access and Misery Haul Roads – Road Usage Lynx Access Road (new) • Approximately 19,000 tonnes per day of material may be hauled from Lynx Pit to a stockpile and/or waste rock storage area located at Misery • Approximately 17 truck movements (loaded and unloaded) per hour (95 tonne capacity trucks) Misery Haul Road (existing) • Lynx Project would extend the duration of haulage from Misery to Ekati by approximately 5 months Caribou Protection Measures • Established procedures involving reduced speed limits and road closures are effective in keeping caribou from being harmed 12

  13. Lynx Project – Baseline Hydrology 13

  14. Lynx Lake – Two Dewatering Options The Dewatering Plan will be provided to the Board for review prior to dewatering DEWATERING ALIGNMENT ALTERNATIVE 1 (PIPELINE) DEWATERING ALIGNMENT ALTERNATIVE 2 (PIPELINE OR EXISTING CHANNEL) 14

  15. Lynx Lake Dewatering – Negligible Potential for Effects to Lac de Gras • Volume of Lynx Lake is 0.01% the volume of Lac de Gras • Rate of dewatering (0.1 m 3 /s over two months) will be relatively low • General water quality in both lakes is similar; Lynx flows seasonally into Lac de Gras • Mitigation strategies applied during the dewatering process will limit the potential for total suspended solids loading to Lac de Gras • Lynx Lake water with elevated total suspended solids (TSS) will be pumped to the Misery water management system to allow for settlement of the solids prior to discharge to the receiving environment 15

  16. Lynx Lake – Fish-Out and Off-setting Planning • A Fisheries Act Authorization will be required for the Lynx Project • Initial discussions have occurred with DFO regarding the Project • The fish-out plan and off-setting plan will be developed in consultation with DFO and with input from the communities 16

  17. Lynx Project – Bedrock Geology Lynx Pit is in granite 17

  18. Lynx Project – Surface Runoff Management • Deflection structures are a contingency that may or may not be required • If required, will likely only comprise berms to redirect surface water flow away from the pit • Surface water flow will be of natural runoff that will continue to flow down Lynx Creek, not into the pit • This water will not pick up lakebed sediments and will not be a large volume 18

  19. Lynx Project – Waste Rock and Ore Storage Management 19

  20. Lynx Project – Misery Site Water Management Proposed to also include: • late stages of Lynx Dewatering • Lynx pit sump 20

  21. Lynx Project – Water Management • Lynx mine water will be pumped to the Misery water management system • Current effluent quality criteria (EQC) have been accepted by the WLWB as adequately protective for effluent discharge volumes from Desperation Pond and King Pond • Dominion proposes to add an annual maximum discharge volume for Desperation Pond to: • Maintain protection of the receiving environment provided by the EQC • Maintain operational flexibility 21

  22. Lynx Project – Monitoring and Management Plans • Activities at the Lynx Project will be incorporated into existing monitoring and management plans related to the Water Licence: • Waste Rock and Ore Storage Management Plan • Wastewater and Processed Kimberlite Management Plan • Interim Closure and Reclamation Plan • Aquatic Effects Monitoring Program • Surveillance Network Program • Other monitoring programs will be updated to include the Lynx Project: • Air Quality Monitoring Program • Wildlife Effects Monitoring Program 22

  23. Lynx Project – Reclamation The Lynx open pit, road and rock pile (if not used for construction) will be reclaimed under the existing Ekati Mine Interim Closure and Reclamation Plan (ICRP): • The pit will be filled with natural runoff, precipitation and water pumped from Lac de Gras (~ 6 months to refill) • An outlet from the final pit lake will be established to join natural flow channels • Design of shallow zones will be considered according to the ICRP • Water quality during and after filling will be monitored • All areas will be safe for people and wildlife Reclamation Security was estimated using the existing Reclaim model and accepted by AANDC 23

  24. Masi Cho 24

Recommend


More recommend